Review of the York City Walls Restoration Programme Phase 1

Noted Executive 1 paper

Decision Session - Executive Member for Transport - Expired noted this item on Thursday 9 June 2016. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

That the findings of the report be noted and the scheme programme be approved. Reason: Council officers and the appointed structural engineer have identified and ranked the urgent structural defects affecting the Bar Walls. In particular three schemes have been identified for repairs this financial year, Micklegate Bar Roof, Monk Bar Steps, Tower 32. That the findings of the report be noted and the scheme programme be approved from 2016/2017 to 2020-2021. Reason: Council officers and the appointed structural engineer have identified and ranked the urgent structural defects affecting the Bar Walls. In particular three schemes have been identified for repairs this financial year, Micklegate Bar Roof, Monk Bar Steps, Tower 32.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for Transport - Expired, 6 pages

Summary

1. This report presents a review of how the following approach will place us on an evidence-based 5 year programme for managing repair and restoration on York City Walls (2016/17 to 2020/21). This approach represents best practice in conservation of complex monuments and is used extensively in the management of ecclesiastical properties and National Trust properties.

Recommendations

2. The Executive Member is requested to note the findings of the report, and approve the scheme programme. Reasons: Council officers and the appointed structural engineer have identified and ranked the urgent structural defects affecting the Bar Walls. In particular three schemes have been identified for repairs this financial year, Micklegate Bar Roof, Monk Bar Steps, Tower 32.

Background

3. The monitoring programme has identified 10 locations where urgent repair and restoration works are required. The team have been working with Robert Thorniley Walker, Robert was the appointed structural engineer, employed to monitor the extent of the defects and the direction of movement. 4. Following approval at Full Council on 25 February 2016, the CES Capital Programme budget for the Bar Wall‟s 2016/17 has been confirmed as £90k. + allocation through the Cram Bid of £260K In total £350K allocation.

5. This bid in effect forms Phase 1 of what will be a 5 year programme. The content of the Phase 2 bid of this 5 year programme will arise from the continuing programme of monitoring and inspection of the City Walls.

6. For the Executive Member‟s information Council officers are also currently reviewing a longer term approach to public realm funding which would include the Bar Wall asset. The review is exploring third party funding options alongside CYC funding. The team will be seeking to speak with all interested parties in the future of the Bar Walls and the public realm later in the year. A separate Executive report that will address these issues is in preparation.

7. The allocations shown in Table 1 below include funding for schemes identified in previous years and an allowance for over programming. Over programming is used in the capital programme to ensure the funding allocation is fully spent within the year. It allows reserve schemes to be developed and delivered if other schemes are delayed due to unforeseen circumstances.

Table 1: Proposed 2016/17 Restoration Programme Phase 1 are shaded below.

Proposed BW Programme £1,000s Micklegate Bar Roof 75 Monk Bar Steps 75 Tower 32 190 Red Tower Utilities 10 Tower 2 75 Bootham Bar to Robin Hoods Tower 350 St Marys Abbey Wall 70 Mint Yard (City Wall, Roman Wall, 50 Anglian Tower) Road Arch / Station Rise 10 Deans Garden Wall 30 Grays Court Pier 15 8. The proposed programme for 2016/17 has been developed to target identified structural failures within the Bar Walls and Tower Buildings. It includes schemes which have continuing monitoring to assess the level of movement from the 2015/16 programme. Schemes which were identified 2015/16 will continue to be monitored to assess for the hierarchy of implementation in future years.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Review of the York City Walls Restoration Programme Phase 1Report 6 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 3 attended
IG
Councillor Ian GilliesCommittee Member, present
JB
Judith BettsSecretary, expected
DC
Councillor Denise CraghillAttendee, in attendance

On this subject at York

Search all
  1. Review of the York City Walls Restoration Programme Phase 1This decision
  2. The Determination of an Application by Home Office Immigration Enforcement for a Review of a Premises Licence [Section 52(2)(a)] in respect of Yakamoz, 55 Goodramgate, York, YO1 7LS. (CYC-064644) (10:22am)Decided
  3. The Determination of an Application for Review of a Premises Licence by Home Office Immigration Enforcement [Section 52(2)(a)] in respect of of Sky Blue, 16 Barbican Road, York YO10 5AA. (CYC-068154) (11:00am)Decided
  4. Healthwatch York Reports: "Mental Health in York: A Progress Review" and "Mental Health: What good should look like" (6:26pm)Decided
  5. Recommendations of the Executive: Review of the City of York Council Scrutiny Function (7:54 pm)Approved
  6. Review of the City of York Council Scrutiny Function (17:37)Approved

More from York Decision Session - Executive Member for Transport - Expired

All decisions
MeetingDecisionOutcome
21 Mar 2023 Acomb Road Safety Updatei. That the council promote and relaunch the existing campaign to recruit a school crossing patroller on Acomb Road; ... Noted Open
21 Mar 2023 Active Travel Programme Updatei. Noted the update on the progress of the Active Travel Programme contained within this report; Reason: To provide i... Noted Open
21 Mar 2023 Active Travel Programme – Hospital Fields Road Schemei. Approved the advertisement of amendments to the Traffic Regulation Order (TRO) to implement the parking restrictio... Approved Open
21 Mar 2023 Resident Parking (Recommendations from Scrutiny)i. Noted the response to the scrutiny recommendations detailed within paragraph 25 of this report; ii. Noted that the... Noted Open
14 Mar 2023 Exclusion of Press and PublicThat the press and public be excluded from the meeting during the consideration of annexes D and E for Agenda Items 5... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies