That Executive agree to: (i) Note the 2016/17 revised budget of £100.146m as set out inparagraph 6 and Table 1 of the report. (ii) Note the restated capital programme for 2016/17 – 2020/21 as set out in paragraph 17, Table 2 and detailed in Annex A of the report. Reason: To enable the effective management and monitoring of the Council’s capital programme. That Executive agree to: (i) Note the 2016/17 revised budget of £100.146m as set out inparagraph 6 and Table 1 of the report. (ii) Note the restated capital programme for 2016/17 – 2020/21 as set out in paragraph 17, Table 2 and detailed in Annex A of the report. Reason: To enable the effective management and monitoring of the Council’s capital programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1 The purpose of this report is to set out the projected outturn position for 2016/17 including any under/over spends and adjustments, along with requests to re-profile budgets to/from current and future years.
2 The 2016/17 capital programme approved by Council on 25 February 2016, updated for amendments reported to Executive and Council in the July Outturn Report resulted in an approved capital budget of £98.035m.
Recommendations
3 Executive is asked to:
Recommend to Full Council the adjustments resulting in an increase in the 2016/17 of £2.111m as detailed in the report and contained in Annex A.
Note the 2016/17 revised budget of £100.146m as set out in paragraph 6 and Table 1. Note the restated capital programme for 2016/17 – 2020/21 as set out in paragraph 17, Table 2 and detailed in Annex A.
Reason: to enable the effective management and monitoring of the Council’s capital programme.
Consultation
4 The capital programme was developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 25 February 2016. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals and associated capital receipt sales do follow a consultation process with local Councillors and residents in the locality of the individual schemes.
Summary of Key Issues
5 An increase of £2.111m is detailed in this monitor resulting in a revised capital programme of £100.146m. There is an increase of £2.216m in 2016/17 attributable to an increase in government grants available, use of S106 funds and use of capital receipts. This is offset by a £0.105m decrease in 2016/17 due to re-profiling of budgets to future years.
6 Table 1 outlines the variances reported against each portfolio area.
Department Current Projected Variance Paragraph Approved Outturn Ref Budget £m £m £m Children’s Services, Education & Skills 11.853 11.853 0.000
Adult Social Services 1.472 2.996 1.524 8-9
Communities Culture & Public Realm 2.235 2.386 0.151 10-15
Housing & Community Safety 26.232 26.232 0.000
Highways & Waste 8.568 8.815 0.247 14
Transport 19.366 19.635 0.269 15-17
Community Stadium 19.000 19.000 0.000
Asset Management 5.095 5.095 0.000
West Offices - Admin Accom 0.498 0.498 0.000
IT Development Plan 3.043 3.043 0.000
Misc(Contingency ) 0.673 0.593 (0.080) 20
Total 98.035 100.146 2.111
Table 1 Capital Programme Forecast Outturn 2016/17 Analysis
7 A summary of the key exceptions and implications on the capital programme are highlighted below.
Adult Social Services & Public Health
8 The Older Persons Accommodation Review scheme has been updated to reflect approvals by Executive in reports on 19th May and 14th July in relation to increases in the scheme budget of £981k to reflect enabling works at Burnholme and £600k to meet acquisition and legal costs and fund demolition costs at Haxby Hall.
9 A number of other minor adjustments have been made to the Adult Social Care programme resulting in a net reduction to the programme of £57k in 16/17.
Communities, Culture and Public Realm
10 A number of amendments have been made as part of this report resulting in a net increase to the capital programme of £151k in 16/17.
11 A budget of £80k has been allocated to the York Explore scheme from Capital contingency in order to fund a proposed capital grant to York Explore to contribute to the purchase of a mobile library vehicle in Haxby following the closure of Haxby library on 16th July on the grounds of public safety following a structural survey.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.