Directorate of Place Capital Programme - 2016/17 Monitor 1 Report
ApprovedExecutive4 papers
Decision Session - Executive Member for Transport - Expired approved this item on Thursday 13 October 2016. Below is the council's own wording, with the papers it was decided on.
( i ) That the amendments to the 2016/17 Directorate of Place Capital Programme set out in Annexes 1 and 2 be approved. (ii) That the reduction to the 2016/17 Director of Place Capital Programme be noted and the movement of funding to 2017/18, subject to the approval of the Executive. (iii) That the list of the priority pedestrian crossing requests in Annex 3 of the report be noted. Reason: To enable the effective management and monitoring of the Directorate of Place Capital Programme. ( i ) That the amendments to the 2016/17 Directorate of Place Capital Programme set out in Annexes 1 and 2 be approved. (ii) That the reduction to the 2016/17 Director of Place Capital Programme be noted and the movement of funding to 2017/18, subject to the approval of the Executive. (iii) That the list of the priority pedestrian crossing requests in Annex 3 of the report be noted. Reason: To enable the effective management and monitoring of the Directorate of Place Capital Programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired, 8 pages
Recommendations
3. The Executive Member is requested to:
1) Approve the amendments to the 2016/17 Directorate of Place Capital Programme set out in Annexes 1 and 2.
2) Note the reduction to the 2016/17 Directorate of Place Capital Programme and the movement of funding to 2017/18, subject to the approval of the Executive.
3) Note the list of priority pedestrian crossing requests in Annex 3. Reason: To enable the effective management and monitoring of the Directorate of Place Capital Programme.
Background
4. The Directorate of Place Capital Programme budget for 2016/17 was confirmed as £3,793k at Full Council on 25 February 2016, and details of the programme were presented to the Executive Member at the April Decision Session meeting. The programme was finalised on 14 July 2016 when the Executive Member was presented with the Consolidated Capital Programme, which included all schemes and funding that had carried over from 2015/16.
5. The programme includes the Integrated Transport and Place-Based Services Maintenance budgets, and is funded through the Local Transport Plan (LTP) grant, the Better Bus grant, the Department for Transport’s Local Pinch Point Funding (Tranche 3) grant, developer contributions, and council resources.
6. Table 1 shows the current approved capital programme.
Table 1: Approved 2016/17 Directorate of Place Capital Programme Gross External Capital Budget Funding Receipts £1,000s £1,000s £1,000s Transport Capital 3,793 3,110 683 Programme Variations approved at 4,403 3,682 722 Consolidated Report Current Approved Capital 8,197 6,792 1,405 Programme External funding refers to government grants, non government grants, other contributions, developer funding, and supported capital expenditure.
7. The current spend and commitments to the end of August 2016 is £857k, which represents 10% of the current budget (the programme minus overprogramming). This is in line with the expected spend profile, as the majority of the expenditure is programmed for the latter part of 2016/17.
Key Issues
8. At this stage of the year, feasibility and outline design is being carried out for schemes in the capital programme. A review of the current programme has been carried out, which has identified a number of schemes where the allocations need to be amended to reflect scheme progress and updated cost estimate. 9. The council has received £72k of Section 106 funding from the developer of the former Grain Stores site on Water Lane, which will be added to the capital programme and used to fund improvements to bus stops in the vicinity of the development site.
10. The council received £800k grant funding from the government’s Office of Low Emission Vehicles (OLEV) to fund the installation of rapid charging points around York. It is proposed to move part of this grant funding to 2017/18 as the programme of work is expected to be carried out over two years.
11. Network Rail have now provided a revised timescale for their feasibility and outline design work for the improvements to the Scarborough Bridge footbridge, and it is proposed to move some of the CYC Resources funding to 2017/18 due to the changed timescales for the scheme.
12. The current budget and proposed adjustments are shown in Table 2.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.