That Executive agree: (i) To take up the West Yorkshire Transport Fund (WYTF) funding allocated for York Central and to confirm that the York Central access route will be part funded by CYC; (ii) To undertake further consultation on the access route for York Central as part of a future York Central planning strategy, with high level, ongoing engagement across the City in relation to the access route, with particular regard being given to residents most directly affected; (iii) Subject to the council agreeing to join the West Yorkshire Transport Fund, to agree to fund the access route definition and design outlined in the report from the £2.15 WYTF Gateway 1 allocation; (iv) To note the appointment of Development and Technical Advisors to develop a detailed planning strategy for the York Central Partners. Reason: (i) To ensure the delivery of York Central. (ii) To ensure that a range of access options have been considered. (iii) To enable timely progress on the York Central project. (iv) To ensure that a development scheme for the York Central site can be delivered. That Executive agree: (i) To take up the West Yorkshire Transport Fund (WYTF) funding allocated for York Central and to confirm that the York Central access route will be part funded by CYC; (ii) To undertake further consultation on the access route for York Central as part of a future York Central planning strategy, ... view the full minutes text for item 71.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Portfolio of the Executive Member for Finance and Performance and Executive Member for Economic Development & Community Engagement
York Central – Consultation on Access Options Summary 1. York Central is a 72 hectare (ha) area of land adjacent to the railway station and is one of the largest brownfield sites in northern England. It provides a huge opportunity for regeneration providing new homes and Grade A commercial office space. The site is identified in the Local Plan for residential development of up to 1,500 dwellings and 80,000 sqm floor space of high quality grade A office.
2. Informal public consultation to guide regeneration of the York Central site took place earlier this year through the ‘Seeking Your Views to Guide Redevelopment’ document. A York Central Community Forum has being established to engage with and represent the views of the local community as the site progresses. All this work will inform the development of a formal planning framework which can be updated to form a Supplementary Planning Document (SPD) on the adoption of the Local Plan Preferred Sites Consultation (2016). Work to establish the partnership, assemble the land and put in place appropriate funding arrangements is ongoing.
3. This report sets out a proposal to fund the access route using the West Yorkshire Transport Fund and to undertake further consultation on the route of the proposed new access. Recommendations
4. Executive is asked : i. To agree to take up the WYTF funding allocated for York Central and to confirm that the York Central access route will be part funded by CYC. Reason: - To ensure the delivery of York Central.
ii. To agree to undertake further consultation on the access route for York Central as part of a future York Central planning strategy
Reason: - To ensure that a range of access options have been considered.
iii. Subject to the council agreeing to join the West Yorkshire Transport Fund to agree to fund the access route definition and design outlined in the report from the £2.15 WYTF Gateway 1 allocation
Reason: - To enable timely progress on the York Central project
iv. To note the appointment of Development and Technical Advisors to develop a detailed planning strategy for the York Central Partners Reason: - To ensure that a development scheme for the York Central site can be delivered. Background
5. The York Central site is entirely circumscribed by rail lines, with the rail station at the bottom of the teardrop of land, the East Coast Main Line (ECML) forming a barrier to the north and east, and the Freight Avoiding Lines (FAL) to the south and west. Current roads onto the site already run through minor residential streets in the Salisbury Terrace area, or under the Marble Arch Rail Bridge and have limited capacity and low bridges, limiting access for high vehicles. They are not suitable to serve a comprehensive re-development of York Central. It is therefore necessary for a new route to be constructed.
6. There has been significant work undertaken over a number of years to identify access options to unlock the York Central site. A range of options to access the site were identified in study work (available at this link) and these are set out on a map at Annex 1. The majority of these routes would access the site from Holgate Road (options B-E) with one option to the north of the site on Water End (option A), and a further option from the South (option F), which is no longer deliverable due to the subsequent creation of Network Rail’s Route Operating and Workforce Development centre.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.