That Executive: (i) Note the 2016/17 revised budget of £71.066m as set out in paragraph 6 and Table 1 of the report. (ii) Note the restated capital programme for 2016/17 – 2020/21 as set out in paragraph 40, Table 2 and detailed in Annex A. Reason: To enable the effective management and monitoring of the Council’s capital programme. That Executive: (i) Note the 2016/17 revised budget of £71.066m as set out in paragraph 6 and Table 1 of the report. (ii) Note the restated capital programme for 2016/17 – 2020/21 as set out in paragraph 40, Table 2 and detailed in Annex A. Reason: To enable the effective management and monitoring of the Council’s capital programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1 The purpose of this report is to set out the projected outturn position for 2016/17 including any under/over spends and adjustments, along with requests to re-profile budgets to/from current and future years.
2 The 2016/17 capital programme approved by Council on 25 February 2016, updated for amendments reported to Executive and Council is £100.146m.
Recommendations
3 Executive is asked to:
Recommend to Full Council the adjustments resulting in a decrease in the 2016/17 programme of £29.080m as detailed in the report and contained in Annex A.
Note the 2016/17 revised budget of £71.066m as set out in paragraph 6 and Table 1.
Note the restated capital programme for 2016/17 – 2020/21 as set out in paragraph 40, Table 2 and detailed in Annex A.
Members are also asked to recommend to Full Council to approve the Loan of £1.110m the Council will provide to Yorwaste, as set out in paragraphs 23 – 29 of this report. This will be funded from the Waste reserve so will have no impact on the Council‟s overall borrowing levels. Reason: To enable the effective management and monitoring of the Council‟s capital programme. Consultation
4 The capital programme was developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 25 February 2016. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals and associated capital receipt sales do follow a consultation process with local Councillors and residents in the locality of the individual schemes.
Summary of Key Issues
5 A decrease of £29.080m is detailed in this monitor resulting in a revised capital programme of £71.066m. £31.803m of this decrease is due to re- profiling of budgets to future years. Offsetting this is a net increase of £2.723m mainly due to an Adjustment to the York Central Scheme budget funded by external contributions as detailed in paragraph 35 and the Harewood Whin Transfer Station which is detailed in paragraphs 23-29 and is funded by the Waste Reserve.
6 Table 1 outlines the variances reported against each area. It should be noted the Capital programme headers have been amended to reflect the new council directorate structure.
Department Current Projected Variance Paragraph Approved Outturn Ref Budget £m £m £m Children, Education & Communities 12.716 9.006 (3.710) 8-15 Health, Housing & Adult Social Care – 3.551 3.593 0.042 Adult Social Care Health, Housing & Adult Social Care – 26.115 24.900 (1.215) Housing & Community Safety 16-21 Economy & Place – Transport, 18.753 17.627 (1.126) Highways & Environment 22-32
Economy & Place – Regeneration & 13.557 8.595 (4.962) Asset Management 33-37 Community Stadium 19.000 1.000 (18.000) 38 Corporate Schemes 3.411 3.363 (0.048) 37 IT Development Plan 3.043 2.982 (0.061)
Total 100.146 71.066 (29.080)
Table 1 Capital Programme Forecast Outturn 2016/17 Analysis
7 A summary of the key exceptions and implications on the capital programme are highlighted below.
Children, Education & Communities
8 A number of amendments have been made as part of this report resulting in a net decrease to the capital programme of £3.710k in 16/17. Key variances are summarised in the table below, referenced to further narrative
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.