Executive, Wednesday 7 December 2016 at 5.30pm

Community Stadium Update Report

Agreed Executive 1 paper

Executive agreed this item on Wednesday 7 December 2016. Below is the council's own wording, with the papers it was decided on.

Item87

Resolved

That Executive agree to: (i) Approve the proposed York City Knights RLFC (YCK) financial support towards first team playing arrangements at Bootham Crescent, as set out at table one of this report. This being Council financial support payable per YCK game played at Bootham Crescent up to a net cost of £45,000 per Rugby League season, paid from the existing Project budget. (ii) Note the financial position of the Project and the associated financial risks present until Financial Close can be met, as set out at paragraphs 57 to 60 of the report. (iii) Note the latest position of the Project’s Community Partners and Sport Clubs, as set out in the report. (iv) Note the current anticipated Project timetable for delivery of the New Stadium Leisure Complex, as set out at table two of the report. (v) Note the position of the ongoing Yearsley Swimming Pool Review and that a further recommendation report on this matter will be brought to Executive early in 2017. (vi) Note the highlighted Project risks that have changed since the March 2016 Executive Report, as summarised at table three of the report. Reason: To ensure continued progress of the Project. That Executive agree to: (i) Approve the proposed York City Knights RLFC (YCK) financial support towards first team playing arrangements at Bootham Crescent, as set out at table one of this report. This being Council financial support payable per YCK game played at Bootham Crescent up to a net cost of £45,000 per Rugby League season, paid from the existing Project budget. (ii) Note the financial position of the Project and the associated financial risks present until Financial Close can be met, as set out at paragraphs 57 to 60 of the report. (iii) Note the latest position of the Project’s Community Partners and Sport Clubs, as set out in the report. (iv) Note the current anticipated Project timetable for delivery of the New Stadium Leisure Complex, as set out at table two of the report. (v) Note the position of the ongoing Yearsley Swimming Pool Review and that a further recommendation report on this matter will be brought to Executive early in 2017. (vi) Note the highlighted Project risks that have changed since the March 2016 ... view the full minutes text for item 87.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 14 pages

Executive 7 December 2016.

Report of the Deputy Chief Executive/Director of Customer and Corporate Services

Portfolio of the Executive Member for Culture, Leisure and Tourism

Community Stadium & Leisure Facilities Report Report Summary 1. The purpose of this report is to update the Executive on the progress of the Community Stadium and Leisure Facilities Project (“Project”) since the last report brought to Executive in March 2016. 2. In doing so this progress report sets out an up to date position on the following:

 The latest position with regards the Judicial Review Claim (“JR Claim”) into the Project‟s planning permission.  Updates on the latest position with all Community Partners and Sport Clubs. Including a recommendation to provide further financial support to York City Knights RLFC (“YCK”) first team arrangements for the coming Rugby League seasons.

 A progress update on the position with our preferred bidder from the Procurement exercise, Greenwich Leisure Ltd (“GLL”). This prior to entering into the Design, Build, Operate and Maintain Contract (“DBOM Contract”).

 An update on the key Project risks where changes have occurred to those highlighted in the March 2016 Executive Report.

 The latest anticipated Project timetable.

Project Background 3. The March 2016 Executive and subsequent Council approval represented a significant milestone for the Project with approval given to proceed in entering into the DBOM Contract with GLL for the delivery of the New Stadium Leisure Complex (“NSLC”) scheme and long term operation of both the NSLC and the City‟s existing leisure facilities. 4. As the last key Council decision point on the Project, the March 2016 Executive Report should be referred to where applicable alongside this update progress report presented at December 2016.

Report Recommendations Executive is asked to:

I. Approve the proposed YCK financial support towards first team playing arrangements at Bootham Crescent, as set out at table one of this report. This being Council financial support payable per YCK game played at Bootham Crescent up to a net cost of £45,000 per Rugby League season, paid from the existing Project budget.

II. Note the financial position of the Project and the associated financial risks present until Financial Close can be met, as set out at paragraphs 57 to 60 of this report. III. Note the latest position of the Project‟s Community Partners and Sport Clubs, as set out in this report. IV. Note the current anticipated Project timetable for delivery of the NSLC, as set out at table two of this report. V. Note the position of the ongoing Yearsley Swimming Pool Review and that a further recommendation report on this matter will be brought to Executive early in 2017. VI. Note the highlighted Project risks that have changed since the March 2016 Executive Report, as summarised at table three of this report.

Reason for recommendations: To ensure continued progress of the Project.

Planning - Judicial Review Claim Background

5. Detailed planning permission for the NSLC was granted in March 2015 and the Judicial Review (“JR”) period for this permission expired without challenge in July 2015.

6. Through finalising the NSLC scheme to reach Financial Close it became necessary to seek changes to the original March 2015 planning permission. The Council as the Local Planning Authority (“LPA”) dealt with this through s73 planning amendment. This was approved on 8th June 2016.

7. The Secretary of State (“SoS”) confirmed on the 21st June 2016 that the decision would not be called in and the permission was therefore issued. 8. The s73 planning amendment approval then entered a statutory JR period of six weeks, which was due to expire on the 2nd August. This six week JR period allows for parties to challenge the lawfulness of the Council‟s decision in the High Court.

9. On the 1st August 2016 the LPA received notification that a claimant was planning to lodge a JR Claim to the High Court.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Community Stadium Update ReportReport 14 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at York

Search all
  1. Community Stadium Update ReportThis decision
  2. Community Stadium Project – Stadium Naming Rights SponsorshipAgreed
  3. Community Stadium Project UpdateNoted
  4. Community Stadium Project ReportNoted
  5. Community Stadium & Leisure Facilities ReportApproved
  6. Community Stadium and Leisure Facilities ReportAgreed

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies