That the Executive: i. Notes the plan for the York Central Partnership to undertake public consultation on access options and the master plan which will lead to the submission of outline and detailed planning applications; ii. Agrees to receive a further report in October setting out the York Central Partnership proposed master plan including a recommended access option and presenting the formal YCP partnership agreement for Executive to consider; and iii. Recommends to Council that a budget of £37.4m be approved for the York Central Transport improvements funded from the West Yorkshire Plus Transport Fund grant. Reason: To ensure the delivery of York Central and to ensure that a range of access options have been considered. That the Executive: i. Notes the plan for the York Central Partnership to undertake public consultation on access options and the master plan which will lead to the submission of outline and detailed planning applications; and ii. Agrees to receive a further report in October setting out the York Central Partnership proposed master plan including a recommended access option and presenting the formal YCP partnership agreement for Executive to consider. Reason: To ensure the delivery of York Central and to ensure that a range of access options have been considered.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Portfolio of the Executive Member for Finance and Performance and Executive Member for Economic Development & Community Engagement
York Central – Update - Partnership Agreement
Summary 1. York Central is a 72 hectare (ha) area of land adjacent to the railway station and is one of the largest brownfield sites in northern England. It provides a huge opportunity for regeneration providing new homes and Grade A commercial office space. The site is identified in the Local Plan for residential development of up to 1,500 dwellings and 100,000 sqm of commercial floor space including B1 Office. 2. The scheme is being promoted by the York Central Partnership (YCP) which is made up of the City of York Council (CYC), Network Rail (NR) the Homes and Communities Agency (HCA) and the National Railway Museum (NRM). The YCP are developing a comprehensive master plan for the regeneration of York Central. 3. The project is at a crucial stage as the master planning and viability assessment approach completion and YCP prepare both for consultation leading on to planning and for the formalisation of the YCP and the agreement of a financial model.
4. This report outlines the considerable progress to date and sets out the council’s commitment to developing a formal partnership agreement and the programme of work to take the scheme through to the submission of Planning Applications. This includes public consultation and outlines two consultations to be undertaken by the YCP over the summer and autumn that will seek views on the access options and then on the comprehensive master plan. The report also outlines the required finance to deliver the next phase of the project. Recommendations
5. Executive is asked : i. To note the plan for the York Central Partnership to undertake public consultation on access options and the master plan which will lead to the submission of outline and detailed planning applications ii. Agree to receive a further report in October setting out the York Central Partnership proposed master plan including a recommended access option and presenting the formal YCP partnership agreement for Executive to consider.
iii. To recommend to Council that a budget of £37.4m be approved for the York Central Transport improvements funded from the West Yorkshire Plus Transport Fund grant. Reason: - To ensure the delivery of York Central and to ensure that a range of access options have been considered.
Background 6. The delivery of York Central is essential to the growth of York and the regional economy and will contribute significantly to meeting housing demand in the city. Though the site has been earmarked for regeneration for many years previous attempts to deliver the scheme have not come to fruition and we are now poised to bring together the landholdings and the investment to deliver the once in a lifetime opportunity to shape the missing third of our city centre.
7. The site however has significant infrastructure challenges. It is entirely circumscribed by rail lines, with the rail station at the bottom of the teardrop of land, the East Coast Main Line (ECML) forming a barrier to the north and east, and the Freight Avoiding Lines (FAL) to the south and west. Current access roads onto the site already run through minor residential streets in the Salisbury Terrace area, or under the Marble Arch Rail Bridge and have limited capacity and low bridges, limiting access for high vehicles. They are not suitable to serve a comprehensive re-development of York Central. It is therefore necessary for a new route to be constructed.
8. There have been a number of developments which have finally enabled the scheme to be brought forward :-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.