City of York Council
Executive, Thursday 13 July 2017 at 5.30pm

Proposed York Outer Ring Road Improvements – Approach to Delivery

Approved Executive 6 papers

Executive approved this item on Thursday 13 July 2017. Below is the council's own wording, with the papers it was decided on.

Item21

Resolved

That the Executive proposes to Full Council that a budget of £34.2m be approved for the York Outer Ring Road improvements funded from the West Yorkshire Plus Transport Fund grant. Reason: To confirm the detailed allocation within the budget for the delivery of the Outer Ring Road Upgrade scheme in accordance with the previous Council Decision taken in December 2016. That the Executive accepts the proposed approach and methodology for future development activity on the YORR Improvement programme, and approves the following scheme of delegation to enable effective management of the project: a. To approve the acquisition of land by agreement as required for the upgrade schemes, and to delegate approval of acquisition of land interests by agreement of up to £200,000 for any one interest to the Executive Member for Transport and Planning. b. To delegate to the Assistant Director of Transport, Highways and Environment the negotiation of the terms of purchase for individual land interests by private agreement. By definition, this delegation will also include negotiation of easements and temporary rights where freehold ownership is not required e.g. for drainage purposes, or temporary occupation for the construction works. This delegation will also include obtaining the release/extinguishment of, or variation of, any third part rights over affected land (for example a third party might have a right of way over land which needs to be acquired). c. To authorise the preparation of a draft Compulsory Purchase Order (CPO) in parallel to the purchase of land by private agreement in order to reduce the risk of the programme being prolonged if negotiations with some landowners become protracted. (Any decision to authorise the actual making of that CPO would be referred back to the Executive for determination in a subsequent further report). d. To delegate operational and detailed decision making to the Executive Member for Transport and Planning as the programme of design and delivery develops over the next 5 years. These decisions will include: i. Approval of proposed consultation with residents, businesses and stakeholders. ii. Approval of the final layout of each junction upgrade. iii. Approval of phasing of the scheme. iv. Approval of land acquisitions up to £200k (in any one interest as above) v. Acceptance of tenders for construction. e. To receive further update reports on progress through the Council’s monitoring regime. Further specific reports will be brought back to the Executive when decisions are needed on major changes to the scope of ... view the full minutes text for item 21.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 14 pages

Summary

1. The decision by City of York Council to join the West Yorkshire Plus Transport Fund was confirmed in December 2016. Funds will be drawn for the proposed York Outer Ring Road (YORR) Improvements. 2. This report sets out the proposed approach to the project and seeks approval of the delivery methodology for the development and construction of the seven targeted improvements to junctions on the north York Outer Ring Road over the next 5 years. Consideration is given to the principles about how the key issues and risks will be managed and the most effective way to make decisions over the coming months to develop the proposals. This report recommends that future decisions on the programme of improvements are taken by the Executive Member for Transport and Planning, for example over matters concerning the purchase of land, consultation and phasing of works.

Recommendations 3. The Executive is recommended to propose to Full Council that a budget of £34.2m be approved for the YORR improvements funded from the West Yorkshire Plus Transport Fund grant.

Reason: To confirm the detailed allocation within the budget for the delivery of the Outer Ring Road Upgrade scheme in accordance with the previous Council Decision taken in December 2016. 4. The Executive are recommended to accept the proposed approach and methodology for future development activity on the YORR Improvement programme, and to approve the following scheme of delegation to enable effective management of the project:

a. To approve the acquisition of land by agreement as required for the upgrade schemes, and to delegate approval of acquisition of land interests by agreement of up to £200,000 for any one interest to the Executive Member for Transport and Planning. b. To delegate to the Assistant Director of Transport, Highways and Environment the negotiation of the terms of purchase for individual land interests by private agreement. By definition, this delegation will also include negotiation of easements and temporary rights where freehold ownership is not required e.g. for drainage purposes, or temporary occupation for the construction works. This delegation will also include obtaining the release/extinguishment of, or variation of, any third part rights over affected land (for example a third party might have a right of way over land which needs to be acquired). c. To authorise the preparation of a draft Compulsory Purchase Order (CPO) in parallel to the purchase of land by private agreement in order to reduce the risk of the programme being prolonged if negotiations with some landowners become protracted. (Any decision to authorise the actual making of that CPO would be referred back to the Executive for determination in a subsequent further report). d. To delegate operational and detailed decision making to the Executive Member for Transport and Planning as the programme of design and delivery develops over the next 5 years. These decisions will include:

i. Approval of proposed consultation with residents, businesses and stakeholders.

ii. Approval of the final layout of each junction upgrade.

iii. Approval of phasing of the scheme. iv. Approval of land acquisitions up to £200k (in any one interest as above) v. Acceptance of tenders for construction. e. To receive further update reports on progress through the Council’s monitoring regime. Further specific reports will be brought back to the Executive when decisions are needed on major changes to the scope of the project or if there are significant financial implications to be considered.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Location PlanAppendix A 1 pages Download
PDF
WYCA Assurance ProcessAppendix B 1 pages Download
PDF
Indicative ProgrammeAppendix C 1 pages Download
PDF
OrganagramAppendix D 1 pages Download
PDF
BDMTAppendix E 6 pages Download
PDF
Proposed York Outer Ring Road Improvements: Approach to DeliveryReport 14 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
DC
Councillor David CarrChair, present
KA
Councillor Keith AspdenVice-Chair, present
NA
Councillor Nigel AyreCommittee Member, present
IG
Councillor Ian GilliesCommittee Member, present
SL
Councillor Sam LisleCommittee Member, present
SR
Councillor Stuart RawlingsCommittee Member, present
CR
Councillor Carol RuncimanCommittee Member, present
AW
Councillor Andrew WallerCommittee Member, present

On this subject at York

Search all
  1. Proposed York Outer Ring Road Improvements – Approach to DeliveryThis decision
  2. Consideration of representations received during the Statutory Consultation for the proposed amendments to the York Parking, Stopping and Waiting Traffic Regulation Order (TRO) (10:45am)Decided
  3. Public Footpath Copmanthorpe No 2 - Proposed closure of Level Crossing and Footpath Diversion - City of York Council Objection to Network Rail's Application under the Provisions of the Transport and Works Act 1992 (22:10)Approved
  4. York Outer Ring Road (YORR) - Proposed A1237 (Rawcliffe to Little Hopgrove) Dualling - Update on Progress and Proposed Utility Diversions (6:32 pm)Noted
  5. Proposed Telecommunications Equipment, Millfield Lane, Nether Poppleton, York [21/01067/TCMAS]Approved
  6. City of York Trading Limited - Proposed Amendments to Shareholders AgreementApproved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies