Deferred as updated recommendation. Clarify extend to highway at New Lane/A59 unction. Assess comments in pre-action letter and address in updated report. Reason: To allow for clarification and resolution of the above matters, for consideration at a future meeting.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Date: 17 August 2017 Ward: Rural West York Team: Major and Parish: Hessay Parish Council Commercial Team
Reference: 17/00670/FUL Application at: Land Adjacent Sewage Works At Hessay Industrial Estate New Road Hessay York For: Erection of asphalt plant with associated infrastructure By: Tynedale Roadstone Application Type: Full Application Target Date: 18 August 2017 Recommendation: Approve subject to Section 106 Agreement
1.0PROPOSAL
1.1Hessay Industrial Estate comprises a medium sized employment site of some long standing occupying a former MOD depot on land within the general extent of the York Green Belt to the north of Hessay village. Planning permission is sought for erection of a coated aggregates manufacturing plant situated within a building incorporating a mixing tower with associated chimney to be located at the western edge of the site. The site has a planning permission for erection of a fuel storage depot ref:- 10/00861/FUL dating to 2010 which was not implemented. A previous proposal incorporating an asphalt plant linked with the reinstatement of the rail head within a materially larger section of the site was submitted in 1999 but subsequently withdrawn. The total application site comprises some 7,200 sq metres in area which sets it within Schedule 2 of the 2017 Town and Country Planning (Environmental Impact Assessment) Regulations for which the application has been screened. The proposal does not require an Environmental Impact Assessment.
1.2Subsequent to the proposal being submitted amended details have been supplied to address concerns in respect of impacts of increased traffic flows on the adjacent highway network notably the junction of New Lane Hessay with the A59 directly to the north. Such off-site works would be secured by means of a Section 106 Agreement attaching to any permission.
2.0POLICY CONTEXT
See Section 4 below for full policy context.
3.0CONSULTATIONS
INTERNAL:-
Application Reference Number: 17/00670/FUL Item No: 4a Page 1 of 20 Public Protection:-
3.1Continues to raise concerns in respect of potential harm from activities at the site during the evening and night time hours but otherwise raise no objection in principle to the scheme as amended subject to the imposition of detailed conditions in respect of controlling noise from later working along with the potential for light pollution. It is also recommended that any permission be conditioned to secure remediation in the event of potential land contamination.
Highway Network Management:-
3.2Initially objected to the proposal on the grounds that it would give rise to significant harm to highway safety in respect to problems related to the capacity of the A59/New Lane junction to accommodate additional HGV traffic. The amended proposals are now supported on the basis that:- The junction alterations have been designed to allow vehicles to clear the A59 more readily. Auto track vehicular swept paths of HGV’S demonstrate that these vehicles can pass and re-pass each other at the junction mouth. Obviously smaller vehicles will greatly benefit from the improvements.
3.3The Highway Authority is satisfied in principle for the proposed off site works to be accepted as mitigation. This junction has been brought to our attention prior to the application but due to the limited personal injury accidents recorded, this has not attracted funding to alter the junction. Feels that the proposals maximise the manoeuvring space at the junction utilising land under highway authority control. The improvement scheme will benefit all highway users. This offer will be capped; to reduce the financial risk to the council of unforeseen costs. The works would be carried out by a section 278 agreement.
3.4With regard to the objections raised throughout the rest of the route leading to the industrial estate.
Access to Industrial Estate, New Road
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.