Q1 Capital Programme Monitor

Noted Executive 2 papers

Executive noted this item on Thursday 31 August 2017. Below is the council's own wording, with the papers it was decided on.

Item50

Resolved

That the Executive; I. Recommend to Full Council the adjustments resulting in a decrease in the 2017/18 budget of £14.065m as detailed in the report and contained in Annex A; II. Note the 2017/18 revised budget of £111.638 as set out in paragraph 6 and Table 1; III. Note the restated capital programme for 2017/18 – 2021/22 as set out in paragraph 17, Table 2 and detailed in Annex A. Reason: To enable the effective management and monitoring of the Council’s capital programme. That the Executive; I. Note the 2017/18 revised budget of £111.638 as set out in paragraph 6 and Table 1; II. Note the restated capital programme for 2017/18 – 2021/22 as set out in paragraph 17, Table 2 and detailed in Annex A. Reason: To enable the effective management and monitoring of the Council’s capital programme.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 11 pages

Summary

1 The purpose of this report is to set out the projected outturn position for 2017/18 including any under/over spends and adjustments, along with requests to re-profile budgets to/from current and future years.

2 The 2017/18 capital programme approved by Council on 23 February 2017, updated for amendments reported to Executive and Council in the July Outturn Report resulted in an approved capital budget of £125.703m.

Recommendations

3 Executive is asked to:

 Recommend to Full Council the adjustments resulting in a decrease in the 2017/18 budget of £14.065m as detailed in the report and contained in Annex A.

 Note the 2017/18 revised budget of £111.638 as set out in paragraph 6 and Table 1.  Note the restated capital programme for 2017/18 – 2021/22 as set out in paragraph 17, Table 2 and detailed in Annex A.

Reason: to enable the effective management and monitoring of the Council’s capital programme. Consultation

4 The capital programme was developed under the Capital Budget Process and agreed by Council on 23 February 2017. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals and associated capital receipt sales do follow a consultation process with local Councillors and residents in the locality of the individual schemes.

Summary of Key Issues

5 An decrease of £14.065m is detailed in this monitor resulting in a revised capital programme of £111.638m. There is an increase of £13.741m in 2017/18 attributable to new schemes added to the programme agreed by members set out in the paragraphs below, funded by an increase in government grants available and departmental prudential borrowing. This is offset by a £27.806m decrease in 2017/18 due to re-profiling of budgets to future years.

6 Table 1 outlines the variances reported against each portfolio area.

Department Current Projected Variance Paragraph Approved Outturn Ref Budget £m £m £m Children, Education & Communities 28.463 9.618 (18.845) 8-10

Health, Housing & Adult Social Care – 5.825 5.922 (0.097) Adult Social Care Health, Housing & Adult Social Care – 33.399 25.718 (7.681) 11-18 Housing & Community Safety Economy & Place – Transport, 21.558 20.607 (0.951) 19-27 Highways & Environment

Economy & Place – Regeneration & 15.023 30.023 15.000 28 Asset Management Community Stadium 15.926 14.241 (1.685) 29

Customer & Corporate services 2.184 2.184 0.000

IT Development Plan 3.325 3.325 0.000

Total 125.703 111.638 (14.065)

Table 1 Capital Programme Forecast Outturn 2017/18 Analysis

7 A summary of the key exceptions and implications on the capital programme are highlighted below.

Children, Education & Communities

8 There have been a number of amendments as part of this report, including an overall increase to the programme of £3.5m (£655k 17/18, £2.8m 18/19) and a transferring of £19.5m of funds from 2017/18 into 2018/19. Key variances are summarised in the table below, referenced to further narrative.

Scheme Amendment Amount Amount Further 17/18 18/19 Details – £m Paragraph £m ref Basic Need Re-profile (19.500) 19.500 9 Basic Need Adjustment 2.250 2.800 9 South Bank Adjustment (1.250) - 10 Expansion

9 The Basic Need scheme requires funds of £19.5m to be transferred from 2017/18 into 2018/19. Pupil number projections and pressures continue to be monitored across the city and, when appropriate, additional schemes will be proposed which might require further changes to the profile in the later years of the programme. In 2018/19, the effect of the remainder of the DSG budget set aside for funding the revenue cost of capital expenditure on reorganisation of the school estate has been added to the programme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Mon 1 1718 Annex for report Final vAppendix 4 pages Download
PDF
Q1 Capital Programme MonitorReport 11 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 8 attended
DC
Councillor David CarrChair, present
IG
Councillor Ian GilliesCommittee Member, present
SL
Councillor Sam LisleCommittee Member, present
SR
Councillor Stuart RawlingsCommittee Member, present
CR
Councillor Carol RuncimanCommittee Member, present
AW
Councillor Andrew WallerCommittee Member, absent
RN
Rebecca NoonOfficer, expected
CT
Chris Twells (LD Political Asst)Officer, expected

On this subject at York

Search all
  1. Q1 Capital Programme MonitorThis decision
  2. Capital Programme Monitor Update 2 Report (4:47pm)Noted
  3. Capital Programme - Monitor 1 2026/27 (4:46pm)Noted
  4. Capital Programme Outturn 2025/26 and Revisions to the 2026/27 - 2029/30 ProgrammeApproved
  5. Recommendations of Executive in relation to the Capital Programme - Monitor 3 2025/26Approved
  6. Capital Programme - Monitor 3 2025/26Approved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies