York Outer Ring Road Improvements - Proposed A1237/B1224 Wetherby Road Junction Upgrade – Approval of Layout
NotedExecutive6 papers
Decision Session - Executive Member for Transport - Expired noted this item on Thursday 15 March 2018. Below is the council's own wording, with the papers it was decided on.
( i ) To confirm that the results of the consultation process have been considered and incorporated in the design where possible. (ii) To note the general arrangement design for the junction upgrade and give approval for preparations and implementation of construction as shown in Annex 1 of the report. Reason: ( i ) To enable the detailed final design of the Wetherby Road junction upgrade. (ii) To enable arrangements to be made to commence construction of the Wetherby Road junction upgrade. ( i ) To confirm that the results of the consultation process have been considered and incorporated in the design where possible. (ii) To note the general arrangement design for the junction upgrade and give approval for preparations and implementation of construction as shown in Annex 1 of the report. Reason: ( i ) To enable the detailed final design of the Wetherby Road junction upgrade. (ii) To enable arrangements to be made to commence construction of the Wetherby Road junction upgrade.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired, 13 pages
Summary
1. This report is about the design and consultation of the proposed upgrade of the A1237/B1224 junction (‘The Wetherby Road junction’). The report is seeking the Executive Member for Transport and Planning’s approval to proceed with the detailed design and construction stages of the scheme.
2. Consultation and business case processes have recently been completed and it is now time to conclude the detailed design and move to the construction stage. This report sets out what has been achieved over the last few months and asks approval to progress to the delivery stage.
Recommendations
3. The Executive Member is asked to:
1) Confirm that the results of the consultation process have been considered and incorporated in the design where possible.
Reason: To enable the detailed final design of the Wetherby Road junction upgrade.
2) Note the general arrangement design for the junction upgrade and give approval for preparations and implementation of construction (See Annex 1). Reason: To enable arrangements to be made to commence construction of the Wetherby Road junction upgrade.
Background
4. In July 2017 City of York Council Executive approved a report setting out the proposed approach and management of the York Outer Ring Road (YORR) Improvement Project. Specifically, the report gave delegation of operational and detailed decision making for the design and delivery of the scheme to the Executive Member for Transport and Planning. Progress has been made over recent months on the scheme and it is now time to move to the next stage. The decisions which are relevant at this stage are:
a. Note the consultation results.
b. Note the final layout of the Wetherby Road junction upgrade.
c. Note the phasing of the programme.
5. Running in parallel to the endorsement by City of York Council Executive, the scheme is being funded through the West Yorkshire Plus Transport Fund. The fund is administered by the West Yorkshire Combined Authority (WYCA) and is governed through a programme management process, see Annex 2. A Final Business Case for the improvement programme was submitted in late 2017 (Decision Point 4) and WYCA have subsequently approved £3.6m funding for the Wetherby Road junction upgrade.
6. The project team are currently making preparations for a final sign off process (Decision Point 5) which will secure the £3.6m funding for this upgrade scheme.
Consultation
7. A public consultation process has been held during January and early February 2018.
8. Before the consultation process commenced, an opportunity was taken to present proposals on the principles of the YORR improvement programme to the Westfield Ward meeting at Acomb Explore library on the 1st November 2017 and also at Working Together - the Annual Parish Council liaison forum – at the Rock on the 29th November 2017.
9. Early in 2018, a formal public consultation process relating specifically to the Wetherby Road junction proposals was arranged, see Annex 3. The proposals were discussed at the following events:
Wednesday 10th January 2018 at Lidgett Grove Church coffee morning. Thursday 11th January 2018, at Sanderson House Community Hub. Monday 15th January 2018 at Knapton with Rufforth Parish Council meeting. Thursday 18th January 2018 and Monday 22nd January 2018, Acomb Explore Library. Exhibition Boards and leaflets have also been available at West Offices reception throughout the period.
10. A leaflet was produced and circulated to approximately 1200 properties in the Wetherby Road and Chapelfields area, see Annex 4.
11. In addition a dedicated e-mail address and on-line consultation has taken place from Monday 8th January to Friday 2nd February 2018. A copy of all the comments received are attached as Annex 5.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.