Executive, Thursday 15 March 2018 at 5.30pm

York Central - York Central Access Construction

Agreed Executive 2 papers

Executive agreed this item on Thursday 15 March 2018. Below is the council's own wording, with the papers it was decided on.

Item145

Resolved

( i ) That a contract be procured and awarded to a construction partner to deliver the key site infrastructure outlined in the report, including the access bridge, the spine road, and the NRM rail link, with the potential to novate the contract over to the York Central Partnership, a single partner or a successor body for development of the site. (ii) That a report on the proposal to dispose of the freehold of the Fermatol site and the Carlisle St private car park to Homes England for the best consideration, and to use this capital receipt to fund the York Central project costs, be brought to a joint Decision Session of the Leader and the Deputy Leader for a decision to be made. Reason: To ensure that the concerns around this proposal are properly considered. (iii) That authority be delegated to the Deputy Chief Executive, in consultation with the Council Leader, to: a) consider responses to the public consultation on the disposal of open space land and b) subject to that consideration, confirm the sale price of the land and agree the disposal of the Fermatol site and the Carlisle St private car park to Homes England. (iv) That a further £907k from the £10m EIF be committed to take the project through to planning determination. (v) That a further report be received in June 2018 setting out: a) a preferred masterplan prior to submission of an outline planning application and a detailed bridge and spine road planning application; b) a partnership agreement with the York Central Partnership to formalise the relationship and the financial agreement between the partners; c) a detailed financial plan for the delivery of York Central, including analysis of potential council borrowing, and funding from the Enterprise Zone. Reason: To ensure the early delivery of a new access route to York Central within the timescale of available grant funding. ( i ) That a contract be procured and awarded to a construction partner to deliver the key site infrastructure outlined in the report, including the access bridge, the spine road, and the NRM rail link, with the potential to novate the contract over to the York Central Partnership, a single partner or a successor body for development of the site. (ii) That a report on the proposal to dispose of the freehold of the Fermatol site and the Carlisle St private car park to Homes England for the best consideration, and to use this capital receipt to fund the York Central project costs, be brought to a joint Decision Session of the Leader and the Deputy Leader for a decision to be made. Reason: To ensure that the concerns around this proposal are properly considered. (iii) That a further £907k from the £10m EIF be committed to take the project through to planning determination. (iv) That a further report be received in June 2018 setting out: a) a preferred masterplan prior to submission of an outline planning application and a detailed bridge and spine road planning application; b) a partnership agreement with the York Central Partnership to formalise the relationship and the financial agreement between the partners; c) a detailed financial plan for the delivery of York Central, including analysis of potential council borrowing, and funding from the Enterprise Zone. Reason: To ensure the early delivery of a new access route to York Central within the timescale of available grant funding.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 16 pages

Recommendations

6. Executive is asked :-

I. To agree to procure and award a contract to a construction partner to deliver the key site infrastructure outlined in this report including the access bridge and the spine road, and the NRM rail link with the potential to novate the contract over to the York Central Partnership, a single partner or a successor body for the development of the site. II. To agree, in principle, the disposal of the freehold of the Fermatol site and the Carlisle St private car park to Homes England for best consideration and to use this capital receipt to fund the York Central project costs. III. To delegate to the Deputy Chief Executive in consultation with the Leader the power to: a) Consider responses to the public consultation on the disposal of open space land b) Subject to that consideration to confirm the sale price of the land and to agree the disposal of the Fermatol site and the Carlisle St private car park to Homes England IV. To commit £907k further funding from the £10m EIF to take the project through to planning determination. V. To receive a further report in June 2018 setting out :- a. a preferred masterplan prior to submission of outline planning application and a detailed bridge and spine road planning application b. a partnership agreement with the York Central Partnership to formalise the relationship and the financial agreement between the partners c. a detailed financial plan for the delivery of York Central including analysis of potential Council borrowing, and funding from the Enterprise Zone

Reason: - To ensure the early delivery of a new access route to York Central within the timescale of available grant funding

Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 2Appendix 2 1 pages Download
PDF
York Central: York Central Access ConstructionReport 16 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
IG
Councillor Ian GilliesChair, present
KA
Cllr Keith AspdenCommittee Member, present
NA
Councillor Nigel AyreCommittee Member, present
PD
Councillor Peter DewCommittee Member, present
HD
Councillor Helen DouglasCommittee Member, apologies
KM
Councillor Keith MyersCommittee Member, present
CR
Councillor Carol RuncimanCommittee Member, present
AW
Councillor Andrew WallerCommittee Member, present

On this subject at York

Search all
  1. York Central - York Central Access ConstructionThis decision
  2. York Central Mayoral Development Zone (5:02pm)Agreed
  3. York Central Land Disposal (5:20pm)Approved
  4. York Central Mayoral Development Zone (17:54)Decided
  5. York Central Update (5.38 pm)Noted
  6. York Central Update (5.38 pm)Decided

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies