City of York Council
Executive, Tuesday 8 May 2018 at 5.30pm

The Development of the Guildhall Complex (formerly 'Guildhall Procurement Update')

Approved Executive 2 papers

Executive approved this item on Tuesday 8 May 2018. Below is the council's own wording, with the papers it was decided on.

Item167

Resolved

( i ) That the scope for the regeneration of the Guildhall, as set out in the ‘Future Options’ section of the report, be confirmed. (ii) That approval be given to procure a construction contractor for the Guildhall project, based upon Option 2 in paragraphs 29 to 31 of the report. Reason: To minimise delay and ensure that the value of the Early Contractor Involvement (ECI) phase work is realised for the project in re-tendering the delivery of the works in the most effective way, at less cost to the council than the other options and without committing the future budget. (iii) That, in view of the complexity of the project, a further report with proposals for the appointment of a contractor and determination of the final budget be brought to Executive in the Autumn; that report to include an updated business case, a risk assessment, and details of how the preferred supplier will promote economic growth. (iv) That the council enter into further discussions with Leeds City Region Local Enterprise Partnership, to seek to increase the level of grant funding to deliver the Guildhall scheme. Reason: To ensure the future viability and effective re-use of the Guildhall, as one of the city’s most significant buildings. ( i ) That the scope for the regeneration of the Guildhall, as set out in the ‘Future Options’ section of the report, be confirmed. (ii) That approval be given to procure a construction contractor for the Guildhall project, based upon Option 2 in paragraphs 29 to 31 of the report. Reason: To minimise delay and ensure that the value of the Early Contractor Involvement (ECI) phase work is realised for the project in re-tendering the delivery of the works in the most effective way, at less cost to the council than the other options and without committing the future budget. (iii) That, in view of the complexity of the project, a further report with proposals for the appointment of a contractor and determination of the final budget be brought to Executive in the Autumn; that report to include an updated business case, a risk assessment, and details of how the preferred supplier will promote economic growth. (iv) That the council enter into further discussions with Leeds City Region Local Enterprise Partnership, to seek to increase the level of grant funding to deliver the Guildhall scheme. Reason: To ensure the future viability and effective re-use of the Guildhall, as one of the city’s most significant buildings.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 12 pages

Recommendations

3. Executive are asked to : I. Confirm the scope for the regeneration of the Guildhall as set out in the options section of the report. II. Approve the procurement of a construction contractor for the Guildhall project based upon the option determined under recommendation 1 III. Due to the complexity of the Guildhall project to bring a further report back to Executive for Contractor appointment and determination of the final budget in the Autumn. IV. Enter into further discussions with Leeds City Region Local Enterprise Partnership (LCR LEP) to seek to increase the level of grant funding to deliver the Guildhall scheme

Reason:-to ensure the future viability and effective re-use of the Guildhall as one of the City’s most significant historic buildings.

Background

4. The council vacated the Guildhall complex in March 2013, when they moved to West Offices. The complex has been largely vacant and underused over the interim period at a cost of c£125k pa.

5. A condition survey undertaken in August 2013 highlighted a backlog of repair and maintenance items, the generally poor condition of the complex, life expired services and poor accessibility. The costs of remedial action were estimated at c£2.5m at 2013 prices, before the full extent of the structural problems with the north annex tower were known.

6. The complex has continued to deteriorate since that time, although timely remedial action in 2014 to repair roofs / gutters prevented further unecessary damage as a result of water ingress. There are, however, a number of significant structural problems identified by subsequent site surveys, which need to be addressed to stabilise the complex. In particular there are issues with notable movement in the north annex tower and south range. The scheme has been designed with underpinning to these areas to prevent further structural movement.

7. The Guildhall complex spans six centuries of development on a riverside site that contains evidence of two millennia of urban development. The buildings are listed at Grade I, II* and II – making the site hugely significant. The main elements of the complex are :

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
GH site planAppendix 1 1 pages Download
PDF
The Development of the Guildhall Complex (formerly 'Guildhall Procurement Update')Report 12 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
IG
Councillor Ian GilliesChair, present
KA
Councillor Keith AspdenCommittee Member, present
NA
Councillor Nigel AyreCommittee Member, present
PD
Councillor Peter DewCommittee Member, present
HD
Councillor Helen DouglasCommittee Member, present
KM
Councillor Keith MyersCommittee Member, present
CR
Councillor Carol RuncimanCommittee Member, present
AW
Councillor Andrew WallerCommittee Member, present

On this subject at York

Search all
  1. The Development of the Guildhall Complex (formerly 'Guildhall Procurement Update')This decision
  2. The Guildhall Redevelopment Tender Evaluation & Project Business Plan AppraisalNoted
  3. The Development of the Guildhall ComplexAgreed
  4. Guildhall Development Review Introductory ReportNoted
  5. Hungate Development Site Hungate York (07/01901/REMM) [Guildhall Ward]Approved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open