City of York Council

York Outer Ring Road Improvements - Proposed A1237 Monks Cross Junction Upgrade - Report on Public Engagement

Approved Executive 6 papers

Decision Session - Executive Member for Transport - Expired approved this item on Thursday 13 September 2018. Below is the council's own wording, with the papers it was decided on.

Item28

Resolved

That the Executive Member ( i ) confirms that the results of the public engagement process have been considered and incorporated in the design where possible. Reason: To enable the detailed final design of the Monks Cross junction upgrades to proceed and be completed. (ii) notes the general arrangement design for the junction upgrade and give approval for preparations and implementation of construction (Annex 1 of the report). Reason: To enable arrangements to be made to commence construction of the Monks Cross junction upgrade. (iii) notes the ongoing acquisition of land and negotiation of terms and conditions by the Assistant Director Transport Highways & Environment. Reason: To enable the acquisition of land in a timely manner in order to adhere to the York Outer Ring Road (YORR) programme. (iv) endorses the appointment of the City of York Council’s Delivery Team for the civil engineering and associated works to undertake the Monks Cross junction upgrade. Reason: To enable a timely appointment of a contractor which eliminates the need to go through lengthy and costly tendering processes. That the Executive Member: ( i ) confirms that the results of the public engagement process have been considered and incorporated in the design where possible. Reason: To enable the detailed final design of the Monks Cross junction upgrades to proceed and be completed. (ii) notes the general arrangement design for the junction upgrade and give approval for preparations and implementation of construction (Annex 1 of the report). Reason: To enable arrangements to be made to commence construction of the Monks Cross junction upgrade. (iii) notes the ongoing acquisition of land and negotiation of terms and conditions by the Assistant Director Transport Highways & Environment. Reason: To enable the acquisition of land in a timely manner in order to adhere to the York Outer Ring Road (YORR) programme. (iv) endorses the appointment of the City of York Council’s Delivery Team for the civil engineering and associated works to undertake the Monks Cross junction upgrade. Reason: To enable a timely appointment of a contractor which eliminates the need to go through lengthy and costly tendering processes.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for Transport - Expired, 14 pages

Summary

1. This report is about the design and public engagement of the proposed upgrade of the A1237 / Monks Cross Link junction (the “Monks Cross junction”). The report is seeking the Executive Member for Transport and Planning’s approval to proceed with the detailed design and construction stages of the scheme.

2. Preliminary design and public engagement processes have recently been completed and it is now time to conclude the detailed design and move to the construction stage. This report sets out what has been achieved over the last few months and asks approval to progress to the delivery stage.

Recommendations

3. The Executive Member is asked to:

1) Confirm that the results of the public engagement process have been considered and incorporated in the design where possible.

Reason: To enable the detailed final design of the Monks Cross junction upgrades to proceed and be completed.

2) Note the general arrangement design for the junction upgrade and give approval for preparations and implementation of construction (See Annex 1).

Reason: To enable arrangements to be made to commence construction of the Monks Cross junction upgrade. 3) Note the ongoing acquisition of land and negotiation of terms and conditions by the Assistant Director Transport Highways & Environment.

Reason: To enable the acquisition of land in a timely manner in order to adhere to the York Outer Ring Road (YORR) programme.

4) Endorse the appointment of the City of York Council’s Delivery Team for the civil engineering and associated works to undertake the Monks Cross junction upgrade.

Reason: To enable a timely appointment of a contractor which eliminates the need to go through lengthy and costly tendering processes.

Background

4. In July 2017 City of York Council Executive approved a report setting out the proposed approach and management of the YORR Improvement Project. Specifically, the report gave delegation of operational and detailed decision making for the design and delivery of the scheme to the Executive Member for Transport and Planning. Progress has been made over recent months on the scheme with work commencing on Phase 1 at the A1237/Wetherby Road junction. Design and development work has also been in progress on the Phase 2 A1237/Monks Cross Link junction and it is now time to move to the next stage on this junction. The decisions to be made by the Executive Member which are relevant at this stage are:

a. Accept that a satisfactory public engagement process has been held and note the results.

b. Accept the final layout of the Monks Cross junction upgrade and note that the results of the public engagement process have been considered and incorporated in the design where possible.

c. Note the continuing phasing of the programme.

d. Endorse the appointment of the City of York Council’s Delivery Team to undertake the works at Monks Cross junction. 5. Running in parallel to the endorsement by City of York Council Executive, the scheme is being funded through the West Yorkshire Plus Transport Fund. The fund is administered by the West Yorkshire Combined Authority (WYCA) and is governed through a programme management process, see Annex 4. A Final Business Case for the overall improvement programme was submitted in late 2017. This was accepted by WYCA with a condition that each individual phase must be submitted separately to secure funding for the delivery stage. The estimated cost of the proposed upgrade at Monks Cross at that time was £3.3m.

6. The project team are currently making preparations to submit a Final Business Case + to WYCA in September 2018 in order to secure the estimated £3.3m funding for upgrading the Monks Cross junction.

Consultation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Proposed General Arrangement for Monks Cross JunctionAppendix 1 1 pages Download
PDF
Layout presented for public consultationAppendix 2 1 pages Download
PDF
Sample consultation packageAppendix 3 3 pages Download
PDF
WYCA Project Assurance Process.Appendix 4 1 pages Download
PDF
Press Release for public engagement processAppendix 5 2 pages Download
PDF
York Outer Ring Road Improvements: Proposed A1237 Monks Cross Junction Upgrade: Report on Public EngagementReport 14 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at York

Search all
  1. York Outer Ring Road Improvements - Proposed A1237 Monks Cross Junction Upgrade - Report on Public EngagementThis decision
  2. Major Projects (Station Gateway and York Outer Ring Road Business Case)Approved
  3. York Outer Ring Road (YORR) - Proposed A1237 (Rawcliffe to Little Hopgrove) Dualling - Update on Progress and Proposed Utility Diversions (6:32 pm)Noted
  4. York Outer Ring Road (YORR) – Phase 1 Dualling – Evaluation of the Consultation Process and Resolution to Submit a Planning ApplicationNoted
  5. York Outer Ring Road Phase 1 Dualling - Resolution in principle to promote a Compulsory Purchase Order and associated Side Roads Order.Noted
  6. York Outer Ring Road Phase 1 Dualling - Procurement Strategy, Approach to Public Engagement and LandscapingApproved

More from York Decision Session - Executive Member for Transport - Expired

All decisions
MeetingDecisionOutcome
21 Mar 2023 Acomb Road Safety Updatei. That the council promote and relaunch the existing campaign to recruit a school crossing patroller on Acomb Road; ... Noted Open
21 Mar 2023 Active Travel Programme Updatei. Noted the update on the progress of the Active Travel Programme contained within this report; Reason: To provide i... Noted Open
21 Mar 2023 Active Travel Programme – Hospital Fields Road Schemei. Approved the advertisement of amendments to the Traffic Regulation Order (TRO) to implement the parking restrictio... Approved Open
21 Mar 2023 Resident Parking (Recommendations from Scrutiny)i. Noted the response to the scrutiny recommendations detailed within paragraph 25 of this report; ii. Noted that the... Noted Open
14 Mar 2023 Exclusion of Press and PublicThat the press and public be excluded from the meeting during the consideration of annexes D and E for Agenda Items 5... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies