City of York Council
Executive, Thursday 29 November 2018 at 5.30pm

York Station Front Proposed Improvements - Report on Public Engagements

Approved Executive 6 papers

Executive approved this item on Thursday 29 November 2018. Below is the council's own wording, with the papers it was decided on.

Item67

Resolved

( i ) That it be confirmed that the public and stakeholder process has been carried out appropriately and that the Statement of Community Involvement (SOCI) be endorsed. Reason: To enable the submission of a full planning application and to proceed to detailed design. (ii) That approval be given to instruct the design team to incorporate design changes informed by responses received in the public consultation. Reason: To enable the design team to submit a full planning application and proceed to detailed scheme design. (iii) That the submission of a full planning application based on the amended masterplan informed by the SOCI be approved. Reason: In order to gain planning permission for the scheme. (iv) That approval be given for the project team to pursue land acquisition negotiations with partners, stakeholders and third party landowners and that authority for land purchase be delegated to the Corporate Director of Economy & Place, in consultation with the Leader and Deputy Leader. Reason: To enable Queen Street Bridge to be demolished and the scheme to be constructed as designed. (v) That engagement with statutory undertakers to design and deliver a detailed scheme of utility diversionary work be continued, using existing budget allocations. Reason: To enable the removal of Queen Street Bridge and the construction of the scheme. ( i ) That it be confirmed that the public and stakeholder process has been carried out appropriately and that the Statement of Community Involvement (SOCI) be endorsed. Reason: To enable the submission of a full planning application and to proceed to detailed design. (ii) That approval be given to instruct the design team to incorporate design changes informed by responses received in the public consultation. Reason: To enable the design team to submit a full planning application and proceed to detailed scheme design. (iii) That the submission of a full planning application based on the amended masterplan informed by the SOCI be approved. Reason: In order to gain planning permission for the scheme. (iv) That approval be given for the project team to pursue land acquisition negotiations with partners, stakeholders and third party landowners and that authority for land purchase be delegated to the Corporate Director of Economy & Place, in consultation with the Leader and Deputy Leader. Reason: To enable Queen Street Bridge to be demolished and the scheme to be constructed as designed. (v) That engagement with statutory undertakers to design and deliver a detailed scheme of utility diversionary work be continued, using existing budget allocations. Reason: To enable the removal of Queen Street Bridge and the construction of the scheme.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 21 pages

Summary

1. This report sets out scheme progress to date and seeks the approval to submit a full planning application and proceed to work with partners on the detailed scheme design in spring 2019. This report also seeks permission for the following:  to enter into land acquisition negotiations with stakeholders and third party landowners;  approval to incorporate design changes to the Masterplan informed by public and stakeholder consultation;  approval to proceed with the relocation of statutory undertakers’ apparatus affected by the proposed scheme.

Recommendations

2. The Executive will be asked to:

1) Confirm that the public and stakeholder engagement process has been carried out appropriately and endorse the Statement of Community Involvement (SOCI).

Reason: To enable the submission of a full planning application and to proceed to detailed design.

2) Approve an instruction to the design team to incorporate design changes informed by responses received in the public consultation. Reason: To enable the design team to submit a full planning application and proceed to detailed scheme design.

3) Approve the submission of a full planning application based on the amended masterplan informed by the SOCI.

Reason: Gain planning permission.

4) Approve the project team to pursue land acquisition negotiations with partners, stakeholder and third party landowners.

Reason: To enable Queen Street Bridge to be demolished and the scheme to be constructed as designed.

5) Approve funds to continue engagement with statutory undertakers to design and deliver a detailed scheme of utility diversionary work.

Reason: To enable the removal of Queen Street Bridge and the construction of the scheme.

Background

3. York Rail Station is one of the principal gateways into York and currently accommodates over 12m people per year using it with forecasted growth to 38m by 2050. However, the existing transport interchange is fraught with vehicular and pedestrian conflict and the station environment aesthetically poor. Therefore, City of York Council (CYC), in collaboration with Network Rail (NR) and London North East Railway (LNER), has developed a masterplan that proposes to reorganise highway and public realm areas to the front of York Station through:

 the removal of the Queen Street Road Bridge and rebuilding the Inner Ring Road at grade;  the removal of the Parcel Square buildings to create space to re- locate the proposed taxi rank, passenger drop-off and short stay car park. The buildings currently comprise Cycle Heaven and train operating company accommodation;  the removal of the York RI band room to provide space for a gyratory road around the York RI gymnasium;  the separation of pedestrian, bicycles and motorised transport to provide a safer and more efficient station transport interchange;  The removal of taxis and passenger pick-up and drop-off from the station porte-cochere to a dedicated area in order to take most traffic out of Tea Room Square and improve air quality in the station;  the redevelopment of the areas to the front of the station to diffuse the current congestion and create a new bus interchange, relocated vehicle parking, drop-off and taxi rank and a more attractive public realm arrival experience; and  the redevelopment of Tea Room Square to create a safer and more attractive shared space.

4. In November 2016, City of York Council Executive was asked to decide whether to formally join the West Yorkshire Transport Fund in order to fund the major investment required to deliver the York Central and York Station Front Improvements. The Council’s decision was to formally join the West Yorkshire Transport Fund to ensure the delivery of the York Central Access Road and Station Gateway scheme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 1 pages Download
PDF
A4 leaflet York StationAppendix 2 2 pages Download
PDF
coverAppendix 2 2 pages Download
PDF
York Station Boards REDUCEDAppendix 3 6 pages Download
PDF
coverAppendix 3 2 pages Download
PDF
York Station Front Proposed Improvements: Report on Public EngagementsReport 21 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at York

Search all
  1. York Station Front Proposed Improvements - Report on Public EngagementsThis decision
  2. Major Projects (Station Gateway and York Outer Ring Road Business Case)Approved
  3. 7 Station Road, Haxby, York, YO32 3LS [24/01047/FUL] (4.37 pm)Approved
  4. Principal York, Station Road, York, YO24 1AY [22/02629 FULM] (4.55 pm)Approved
  5. York Railway Station Gateway - Project Update and LNER Funding & Development AgreementNoted
  6. York Central and York Station Gateway UpdateNoted

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies