City of York Council
Executive, Thursday 17 January 2019 at 5.30pm

York Central Partnership Legal Agreement

Agreed Executive 4 papers

Executive agreed this item on Thursday 17 January 2019. Below is the council's own wording, with the papers it was decided on.

Item92

Resolved

( i ) That the Heads of Terms for the York Central Partnership (YCP) legal agreement be approved and that authority be delegated to the Director of Economy & Place and the Director of Corporate & Customer Services to take such steps as are necessary to enter into the legal agreement. (ii) That £1.2m of the £155m York Central capital budget, to be funded initially from City of York Council’s capital budget, be committed to undertake pre-construction site preparations, including telecommunications mast and rail line relocation and site segregation from the operational railway and bridge agreements with Network Rail, as set out in paragraph 40 of the report. (iii) That a further £5m of the £155m York Central capital budget, to be funded from the Housing Infrastructure Fund, be committed, subject to planning and external awards, to commence the enabling works, including site clearance, utility diversions and Millennium Green preparation, as set out in paragraphs 42-43. (iv) That it be acknowledged that a further report will be brought back to Executive to agree the submission of the reserved matters planning application and to commit the capital budget for delivery of the Phase 1 infrastructure, including: · bridge access onto the site · a new spine road · drainage · construction of an additional pedestrian and cycle deck onto Severus Bridge · construction of a new rail connection between the NRM and the East Coast Main Line subject to the award of outline planning permission for the scheme and the final agreement of the external grant funding from both the West Yorkshire Transport Fund and the Housing Infrastructure Fund. Reason: To ensure the delivery of York Central and to provide funding for enabling infrastructure, including a new access route to York Central, within the timescale of available grant funding. (v) That a further report be received, setting out proposals for economic development on York Central. (vi) That a business case be prepared for the council to acquire affordable housing on the York Central site as part of the first phase of residential development. (vii) That proposals be developed for the next phase of community engagement and a report be brought to Executive to seek financial support for community groups to develop capacity to engage effectively with YCP, with a view to active engagement to deliver social and economic benefits. Reason: To ensure that the social, environmental and economic benefits of York Central are delivered and are strongly influenced by community engagement. ( i ) That the Heads of Terms for the York Central Partnership (YCP) legal agreement be approved and that authority be delegated to the Director of Economy & Place and the Director of Corporate & Customer Services to take such steps as are necessary to enter into the legal agreement. (ii) That £1.2m of the £155m York Central capital budget, to be funded initially from City of York Council’s capital budget, be committed to undertake pre-construction site preparations, including telecommunications mast and rail line relocation and site segregation from the operational railway and bridge agreements with Network Rail, as set out in paragraph 40 of the report. (iii) That a further £5m of the £155m York Central capital budget, to be funded from the Housing Infrastructure Fund, be committed, subject to planning and external awards, to commence the enabling works, including site clearance, utility diversions and Millennium Green preparation, as set out in paragraphs 42-43. (iv) That it be ... view the full minutes text for item 92.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

Summary

1. York Central is a 72 hectare (ha) area of land adjacent to the railway station and is one of the largest brownfield sites in northern England, see plan at Annex 1. It provides a huge opportunity for regeneration providing new homes, Grade A commercial office space, an enhanced National Railway Museum and a range of new public spaces and facilities.

2. The scheme is being promoted by the York Central Partnership (YCP) which is made up of Network Rail (NR) Homes England (formerly the Homes and Communities Agency or HCA), the National Railway Museum (NRM) and the City of York Council (CYC). 3. The council has been instrumental in breaking the deadlock of decades and bringing forward York Central for development and the council has worked positively with partners to ensure that the development will deliver benefits to the people of York and will continue to be shaped by extensive public engagement. As the principal conduit for infrastructure funding and through its statutory roles as Local Planning Authority (LPA) and Highways Authority (HA) the council has significant influence and control over key future decisions and will continue to represent the views of the people of York in all partnership discussions.

4. This report sets out the proposed Heads of Terms for a formal agreement between the above partners, to be developed into a legal contract prior to the commencement of infrastructure construction. The report also requests the allocation of £6.25m to commence the first phase of site preparation works ahead of the construction of core infrastructure. £5m of this is subject to the award of planning permission and the award of external grant funding. 5. The report also sets out some early work being undertaken to ensure that York Central delivers significant social economic and environmental benefits for the whole city, including the development of business cases for housing delivery and economic development work with both universities. As part of the future delivery arrangements the report also proposes a revised approach to future community engagement.

Recommendations

6. Executive is asked :-

i. To agree the Heads of Terms for the York Central Partnership legal agreement and delegate to the Director of Economy and Place and the Director of Corporate and Customer Services to take such steps as are necessary to enter into the legal agreement. ii. To commit £1.25m of the £155m York central capital budget, funded initially from CYC capital budget to undertake pre-construction site preparations, including telecommunications mast and rail line relocation and site segregation from the operational railway and bridge agreements with Network Rail as set out in paragraph 40. iii. To commit a further £5m of the £155m York Central capital budget, to be funded from Housing Infrastructure Fund, subject to planning and external funding awards, to commence the enabling works including site clearance, utility diversions, Millennium Green preparation as set out in paragraph 42-43. iv. To acknowledge that a further report will be brought back to Executive to agree the submission of the reserved matters planning application and commit the capital budget for the delivery of the Phase 1 infrastructure, including bridge access onto the site, new spine road, drainage, construction of an additional pedestrian and cycle deck onto Severus Bridge and construction of a new rail connection between the NRM and the East Coast Main Line, subject to the award of Outline planning permission for the scheme and the final agreement of the external grant funding from both the West Yorkshire Transport Fund (WYTF) and the Housing Infrastructure Fund (HIF).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Site PlanAppendix 1 1.8 MB Download
PDF
Partnership Agreement HoTAppendix 2 300 KB Download
PDF
York Central Engagement FrameworkAppendix 3 510 KB Download
PDF
York Central Partnership Legal AgreementReport 566 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
IG
Councillor Ian GilliesChair, present
KA
Councillor Keith AspdenCommittee Member, present
NA
Councillor Nigel AyreCommittee Member, present
JB
Councillor Jenny BrooksCommittee Member, present
PD
Councillor Peter DewCommittee Member, present
KM
Councillor Keith MyersCommittee Member, present
CR
Councillor Carol RuncimanCommittee Member, present
AW
Councillor Andrew WallerCommittee Member, present

On this subject at York

Search all
  1. York Central Partnership Legal AgreementThis decision
  2. York Central Mayoral Development Zone (5:02pm)Agreed
  3. York Central Land Disposal (5:20pm)Approved
  4. York Central Mayoral Development Zone (17:54)Decided
  5. York Central Update (5.38 pm)Noted
  6. York Central Update (5.38 pm)Decided

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies