CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
City of York Council

Junction Alterations - Monkgate Bar

Approved Executive 5 papers

Decision Session - Executive Member for Transport - Expired approved this item on Thursday 24 October 2019. Below is the council's own wording, with the papers it was decided on.

Item33

Resolved

(i) That O ption 1 – the proposed junction layout shown in drawing Annex A be approved. (ii) That further consideration and consultation be undertaken with ward councillors particularly in relation to the central refuge point and the impact of a right turn ban and further to this, that decisions on adjustments be delegated to the Assistant Director Transport, Highways and Environment in consultation with the Executive Member. Reasons: · This option achieves the core aim of replacing the life-expired traffic signal asset such that it can continue be operated and repaired economically. · This option has no negative impact on junction capacity. Any option which reduces junction capacity would have a cumulative effect on congestion in this area if the proposed experimental Traffic Regulation Order in The Groves is implemented. (i) That O ption 1 – the proposed junction layout shown in drawing Annex A be approved. (ii) That further consideration and consultation be undertaken with ward councillors particularly in relation to the central refuge point and the impact of a right turn ban ... view the full minutes text for item 33.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for Transport - Expired, 10 pages

Summary

1. The traffic signalling equipment at this junction is life expired and has become difficult and costly to maintain, it needs to be replaced.

2. The TSAR (Traffic Signal Asset Renewal) programme is the means by which life expired traffic signal assets across the city are refurbished.

3. Although the programme is primarily about asset renewal, there is scope to take advantage of ‘easy wins’ whilst refurbishing the equipment. To that end, junction alterations have been proposed that offer an improvement.

A decision is required to approve the proposed junction alterations.

Recommendations

1. The Executive Member is asked to:

Approve Option 1

Reason:  This option achieves the core aim of replacing the life-expired traffic signal asset such that it can continue be operated and repaired economically.  This option has no negative impact on junction capacity. Any option which reduces junction capacity would have a cumulative effect on congestion in this area if the proposed experimental Traffic Regulation Order in The Groves is implemented. Background

2. A report was brought to the Executive Member for Transport and Planning on 12th November 2015 to seek approval to undertake the 5- year ‘TSAR’ (Traffic Signal Asset Renewal) programme.

3. This programme entails a replacement of life expired traffic signal assets around York. The focus is on replacing equipment that is liable to imminent failure, rather than seeking to improve congestion or achieve a similar transport improvement goal. However, where ‘easy wins’ can be achieved at the same time as replacing obsolete equipment, these will be taken advantage of.

4. To date, 26 sets of signals have been refurbished and a further 4 are programmed in for the 19/20 financial year.

Consultation

5. The scope of the works included within this proposal are relatively minor and in normal circumstances would not require an executive decision for approval, or an external consultation.

6. However, due to the sensitivity of the location a consultation has been carried out to offer key user groups an opportunity to have their say on the proposed scheme.

7. A summary of the consultation feedback can be found in Annex C.

Options

8. The following options are available:

9. Option 1 – Approve the proposed junction layout shown in drawing Annex A.

10. Option 2 – Approve the proposed junction layout as shown in drawing Annex B.

11. Option 3 – Do not approve the presented option. Analysis

Option 1

Description of changes

12. A full replacement of all traffic signalling technology, including signal heads, poles, cabling, cabinets, detectors, communications and ducting.

13. Increased size of pedestrian staggered island in Lord Mayor’s Walk to 3.0m and increased crossing width and tactile paving to meet design guidance.

14. Removal of the ahead flare lane on the northern Monkgate arm. This will reduce the approach to 1 lane, allowing for the provision of a 1.5m cycle lane and an enlarged pedestrian island at the informal crossing point.

15. Increased width of signal controlled crossing and tactile paving over St Maurice’s Road to meet design guidance.

16. Provision of an uncontrolled crossing point over the southern arm of Monkgate, in front of the Bar.

17. Resurfacing and line marking across the whole junction.

18. The estimated cost of the work is £280,000.

Reasoning

19. Replacement of the traffic signal technology is the fundamental purpose of this project, as per Section 2.

20. Widening of the pedestrian crossings is necessary to bring the pedestrian facilities in line with current guidance and standards. The increased size of the pedestrian island on Lord Mayors Walk will improve safety during the busiest times.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ANNEX_A_YK2215-MONK BAR LORD MAYORS WALK OPTION AAppendix 1 pages Download
PDF
ANNEX_B_YK2215-MONK BAR LORD MAYORS WALK OPTION BAppendix 1 pages Download
PDF
ANNEX_C-Consultation_SummaryAppendix 2 pages Download
PDF
ANNEX_D-Monkgate_Modelling_SummaryAppendix 2 pages Download
PDF
Junction Alterations: Monkgate BarReport 10 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at York

Search all
  1. Junction Alterations - Monkgate BarThis decision
  2. TSAR Junction Alterations – Gillygate/Bootham/St Leonards PlaceDeferred
  3. Junction Alterations – Bishopthorpe Road / Scarcroft RoadApproved
  4. Junction Alterations – Lendal Arch GyratoryApproved
  5. Traffic Signal Asset Renewal (TSAR) - Junction AlterationsApproved

More from York Decision Session - Executive Member for Transport - Expired

All decisions
MeetingDecisionOutcome
21 Mar 2023 Acomb Road Safety Updatei. That the council promote and relaunch the existing campaign to recruit a school crossing patroller on Acomb Road; ... Noted Open
21 Mar 2023 Active Travel Programme Updatei. Noted the update on the progress of the Active Travel Programme contained within this report; Reason: To provide i... Noted Open
21 Mar 2023 Active Travel Programme – Hospital Fields Road Schemei. Approved the advertisement of amendments to the Traffic Regulation Order (TRO) to implement the parking restrictio... Approved Open
21 Mar 2023 Resident Parking (Recommendations from Scrutiny)i. Noted the response to the scrutiny recommendations detailed within paragraph 25 of this report; ii. Noted that the... Noted Open
14 Mar 2023 Exclusion of Press and PublicThat the press and public be excluded from the meeting during the consideration of annexes D and E for Agenda Items 5... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies