City of York Council
Executive, Tuesday 21 January 2020 at 5.30pm

Capital Programme - Monitor 2 2019/20

Noted Executive 2 papers

Executive noted this item on Tuesday 21 January 2020. Below is the council's own wording, with the papers it was decided on.

Item86

Resolved

( i ) That the 2019/20 revised budget of £136.870m, as set out in Table 1 at paragraph 6 of the report, be noted. (ii) That the re-stated capital programme for 2019/20-2023/24, as set out in Table 2 at paragraph 17 and detailed in Annex A, be noted. (iii) That the increase in the Shared Ownership Programme to reflect the sales receipts of £761k be approved. (iv) That the budget allocated to Askham Bar for detailed design work, and that planning submission is to be re-allocated to the Hospital Fields / Ordnance Lane site as per the Executive decision on 26 September 2019 (Minute 44), be noted. (v) That it be noted that the Modernisation and Major Repairs schemes have now been consolidated, as per the Monitor 1 report to Executive on 29 August 2019. (vi) That the appropriation of land from the general fund to the Housing Revenue Account for the building of dwellings at the Lowfield site, at a market value of £4m, be approved. (vii) That approval be given to continue the interim financial support arrangements for the York City Knights first team during the 2020 Rugby League season until YCK play their first game from the Stadium, on all the same principles as the financial support given in seasons 2017-2019. Reason: To enable the effective management and monitoring of the council’s capital programme. ( i ) That the 2019/20 revised budget of £136.870m, as set out in Table 1 at paragraph 6 of the report, be noted. (ii) That the re-stated capital programme for 2019/20-2023/24, as set out in Table 2 at paragraph 17 and detailed in Annex A, be noted. (iii) That the increase in the Shared Ownership Programme to reflect the sales receipts of £761k be approved. (iv) That the budget allocated to Askham Bar for detailed design work, and that planning submission is to be re-allocated to the Hospital Fields / Ordnance Lane site as per the Executive decision on 26 September 2019 (Minute 44), be noted. (v) That it be noted that the Modernisation and Major Repairs schemes have now been consolidated, as per the Monitor 1 report to Executive on 29 August 2019. (vi) That the appropriation of land from the general fund to the Housing Revenue Account for the building of dwellings at the Lowfield site, at a market value of £4m, be approved. (vii) That approval be given to continue the interim financial support arrangements for the York City Knights first team during the 2020 Rugby League season until YCK play their first game from the Stadium, on all the same principles as the financial support given in seasons 2017-2019. Reason: To enable the effective management and monitoring of the council’s capital programme.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

Summary

1 The purpose of this report is to set out the projected outturn position for 2019/20 including any under/over spends and adjustments, along with requests to re-profile budgets to/from current and future years.

2 The 2019/20 capital programme approved by Council on 28 February 2019, updated for amendments reported to Executive and Council in the 2018/19 outturn report resulted in an approved capital budget of £136.870m.

Recommendations

3 Executive is asked to:

 Recommend to Full Council the adjustments resulting in a decrease in the 2019/20 budget of £68.608m as detailed in the report and contained in Annex A.

 Note the 2019/20 revised budget of £136.870 as set out in paragraph 6 and Table 1.

 Note the restated capital programme for 2019/20 – 2023/24 as set out in paragraph 17, Table 2 and detailed in Annex A.

 Approve the increase in the Shared Ownership Programme to reflect the sales receipts of £761k

 Note the budget allocated to Askham Bar for detailed design work and planning submission is to be re-allocated to the Hospital Fields/ Ordnance Lane Site as per Executive 26th September 2019  Note the Modernisation and Major Repairs Schemes have now been consolidated as per Monitor 1 report, Executive 29th August 2019.  Approve the appropriation of land from the general fund to HRA for the building of dwellings at the Lowfield site at a market value of £4m

 Approve that the YCK interim first team arrangements financial support continues for the 2020 Rugby League season until YCK play their first game from the Stadium on all the same principles as the previous 2017 - 2019 Rugby League seasons financial support

Reason: to enable the effective management and monitoring of the Council’s capital programme.

Consultation

4 The capital programme was developed under the capital budget process and agreed by Council on 28 February 2019. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals and associated capital receipt sales do follow a consultation process with local Councillors and residents in the locality of the individual schemes.

Summary of Key Issues

5 A decrease of £68.608m is detailed in this monitor resulting in a revised capital programme of £136.870m. There is an increase of £113k in 2019/20 offset by a £68.721m decrease in 2019/20 due to re-profiling of budgets to future years. The majority of this re-profiling is due to a review of the York Central budget to reflect a more appropriate and accurate scheduling of when the costs are likely to be incurred. Progress has been made across a number of key areas of the capital programme, including work beginning on the restoration of the Guildhall and the appointment of a contractor build 140 new homes at Lowfield. 6 Table 1 outlines the variances reported against each portfolio area.

Department Current Projected Increase Reprofile Total Paragraph Approved Outturn (decrease) Variance Ref Budget £m £m £m £m £m Children, Education & 16.979 14.377 0.263 (2.865) (2.602) 8-17 Communities Health, Housing & Adult 6.670 5.254 (0.671) (0.745) (1.416) 20-23 Social Care – Adult Social Care Health, Housing & Adult 39.258 39.258 0.761 (0.761) - 24-29 Social Care – Housing & Community Safety Economy & Place – 41.468 41.268 - (0.200) (0.200) 30-33 Transport, Highways & Environment

Economy & Place – 82.876 18.606 (0.240) (64.030) (64.270) 34-37 Regeneration & Asset Management Community Stadium 10.143 10.143 - - - 38-46

Customer & Corporate 2.999 2.999 - - - 47 services IT Development Plan 5.085 4.965 - (0.120) (0.120) 48

Total 205.478 136.870 0.113 (68.721) (68.608)

Table 1 Capital Programme Forecast Outturn 2019/20

Analysis

7 A summary of the key exceptions and implications on the capital programme are highlighted below. Children, Education & Communities

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Bud Control 1920 Mon 2 Annex AAppendix 214 KB Download
PDF
Capital Programme: Monitor 2 2019/20Report 300 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
KA
Councillor Keith AspdenChair, present
NA
Councillor Nigel AyreCommittee Member, present
DC
Councillor Denise CraghillCommittee Member, present
IC
Councillor Ian CuthbertsonCommittee Member, present
AD
Councillor Andy D'AgorneCommittee Member, present
CR
Councillor Carol RuncimanCommittee Member, present
DS
Councillor Darryl SmalleyCommittee Member, present
AW
Councillor Andrew WallerCommittee Member, present
PW
Councillor Paula WiddowsonCommittee Member, present

On this subject at York

Search all
  1. Capital Programme - Monitor 2 2019/20This decision
  2. Capital Programme Monitor Update 2 Report (4:47pm)Noted
  3. Capital Programme - Monitor 1 2026/27 (4:46pm)Noted
  4. Capital Programme Outturn 2025/26 and Revisions to the 2026/27 - 2029/30 ProgrammeApproved
  5. Recommendations of Executive in relation to the Capital Programme - Monitor 3 2025/26Approved
  6. Capital Programme - Monitor 3 2025/26Approved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies