Executive, Thursday 13 February 2020 at 5.30pm

York Outer Ring Road Improvements – Dualling from A19 Rawcliffe to A64 Hopgrove

Noted Executive 1 paper

Executive noted this item on Thursday 13 February 2020. Below is the council's own wording, with the papers it was decided on.

Item94

Resolved

( i ) That the positive news that YORR has Programme Entry for the first phase of dualling , from A19 Rawcliffe to A64 Malton Road, be noted. Reason: Successive administrations have for many years sought funding to upgrade the YORR, and many residents and employers in the city will welcome and support the news of this proposal. (ii) That approval be given to merge the remaining Junction Scheme and the Dualling Scheme into a single programme of planning and delivery. (iii) That officers be requested to work with the funders of the two schemes to detail the impact of the two separate approvals and bring a single programme and revised timetable to a future meeting of Executive. (iv) That officers ensure that any positive impact on the city’s transport system of dualling the YORR is incorporated into the review of the Local Transport Plan so that policies can look at capturing any benefit. Reason: To develop a single project approach, providing benefits that will aid the management and co-ordination of the overall scheme, minimise the impact on the city of delivering such a significant infrastructure project and avoid abortive works, thus delivering the benefits and purchasing power of a single programme. (v) That approval be given to use the City of York match funding which has already been approved for the overall development specifically for the acquisition of land for the Dualling Scheme up to a value of £1m. Reason: To enable the match funding to be used for land purchase, where appropriate, at the earliest opportunity. (vi) That it be noted that the Assistant Director of Transport, Highways & Environment has delegated authority to purchase land by private agreement / private treaty up to and including a value of £250k in any one land interest in respect of the Junction Scheme and that such authority also be delegated to the Assistant Director in relation to the purchase of land by private agreement / private treaty in respect of the Dualling Scheme. Reasons: a) To ensure that land purchases for both schemes can be administered and acquired in an efficient manner. b) To ensure that the council can demonstrate it has attempted to avoid a future Compulsory Purchase Order by acquiring land through private agreement. ( i ) That the positive news that YORR had Programme Entry for the first phase of dualling , from A19 Rawcliffe to A64 Malton Road, be noted. Reason: Successive administrations have for many years sought funding to upgrade the YORR, and many residents and employers in the city will welcome and support the news of this proposal. (ii) That approval be given to merge the remaining Junction Scheme and the Dualling Scheme into a single programme of planning and delivery. (iii) That officers be requested to work with the funders of the two schemes to detail the impact of the two separate approvals and bring a single programme and revised timetable to a future meeting of Executive. (iv) That officers ensure that any positive impact on the city’s transport system of dualling the YORR is incorporated into the review of the Local Transport Plan so that policies can look at capturing any benefit. Reason: To develop a single project approach, providing benefits that will aid the management and co-ordination of the overall scheme, minimise the impact on the city of delivering such a significant infrastructure project and avoid abortive works, thus delivering the benefits and purchasing power of a single programme. (v) That approval be given to use the City of York match funding which has already been approved for the overall development specifically for the acquisition of land for the Dualling Scheme up to a value of £1m. Reason: To enable the match funding to be used for land purchase, where appropriate, at the earliest opportunity. (vi) That it be noted that the Assistant Director of Transport, Highways & Environment has delegated authority to purchase land by private agreement / private treaty up to and including a ... view the full minutes text for item 94.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

Summary

1. In October 2019, the Department for Transport (DfT) announced that a £26m funding package for dualling a section of the YORR (A19 Rawcliffe to A64 Malton Road) (‘Dualling Scheme’) had been approved (‘Programme Entry’). This is in addition to a programme to upgrade seven junctions along the YORR (‘Junction Scheme’) which has been underway since summer 2017.

2. The achievement of Programme Entry is good news for the region and provides further significant investment in the City’s transport network to add to the £38m already secured for the Junction Scheme. Officers have undertaken a review of the project and have taken advice regarding the implications of the increased funding. The project will now require a single process in terms of an Environmental Impact Assessment (EIA) meaning the current planning permitted development rights in respect of the Junction Scheme can no longer be relied upon. The Junction Scheme and the Dualling Scheme will need to be dealt with as one project.

3. The amalgamation of the remaining Junction Scheme with the Dualling Scheme presents opportunities to co-ordinate and manage the design and construction of both schemes. Early delivery of both schemes is important to the city and merging them delivers more efficiency and cost effectiveness which enables a quicker overall delivery programme.

4. Through the development of the new Local Transport Plan the council can capture the opportunity and benefits that dualling and decongestion of the YORR could deliver for the city centre. Recommendations

5. The Executive are requested to:

1) note the positive news that YORR has Programme Entry for the first phase of dualling the YORR, from A19 Rawcliffe to A64 Malton Road.

Reason: Successive administrations have strived for many years seeking funding to upgrade the YORR. Many residents and employers in the City will welcome and support the news of this proposal.

2) approve the merging of the remaining Junction Scheme and the Dualling Scheme into a single programme of planning and delivery.

3) request officers to work with the funders of the two schemes to detail the impact of the two separate approvals and bring forward a single programme and revised timetable to a future Executive.

4) ensure that any positive impact upon the city’s transport system of dualling the YORR is incorporated into the review of the Local Transport Plan so that policies can consider capturing any benefit.

Reason: To develop a single project approach to provide benefits which will aid management and co-ordination of the overall scheme and minimise the disruption impact upon the city of delivering such significant infrastructure project and avoid abortive works. By delivering as one scheme the benefits of a single programme and purchasing power are delivered.

5) approve the use of City of York match funding which has already been approved for the overall development specifically for the acquisition of land for the Dualling Scheme to a value of £1m.

Reason: To enable the match funding to be used for land purchase, where appropriate, at the earliest opportunity.

6) to note that the Assistant Director Transport, Highways and Environment has delegated authority to purchase land by private agreement / private treaty up to and including £250k in any one land interest in respect of the Junction Scheme and to authorise him to also have such delegated authority in relation to the purchase of land by private agreement / private treaty in respect of the Dualling Scheme.

Reason: a) To ensure that land purchases for both schemes can be administered and acquired in an efficient manner.

b) To ensure that the council can demonstrate it has attempted to avoid a future Compulsory Purchase Order (CPO) by acquiring land through private agreement.

Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
York Outer Ring Road Improvements: Dualling from A19 Rawcliffe to A64 HopgroveReport 291 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
KA
Councillor Keith AspdenChair, present
NA
Councillor Nigel AyreCommittee Member, present
DC
Councillor Denise CraghillCommittee Member, present
IC
Councillor Ian CuthbertsonCommittee Member, present
AD
Councillor Andy D'AgorneCommittee Member, present
CR
Councillor Carol RuncimanCommittee Member, present
DS
Councillor Darryl SmalleyCommittee Member, present
AW
Councillor Andrew WallerCommittee Member, present
PW
Councillor Paula WiddowsonCommittee Member, present

On this subject at York

Search all
  1. York Outer Ring Road Improvements – Dualling from A19 Rawcliffe to A64 HopgroveThis decision
  2. Major Projects (Station Gateway and York Outer Ring Road Business Case)Approved
  3. York Outer Ring Road (YORR) - Proposed A1237 (Rawcliffe to Little Hopgrove) Dualling - Update on Progress and Proposed Utility Diversions (6:32 pm)Noted
  4. York Outer Ring Road (YORR) – Phase 1 Dualling – Evaluation of the Consultation Process and Resolution to Submit a Planning ApplicationNoted
  5. York Outer Ring Road Phase 1 Dualling - Resolution in principle to promote a Compulsory Purchase Order and associated Side Roads Order.Noted
  6. York Outer Ring Road Phase 1 Dualling - Procurement Strategy, Approach to Public Engagement and LandscapingApproved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies