Economy & Place Capital Programme – 2020/21 Budget Report
ApprovedExecutive3 papers
Decision Session - Executive Member for Transport - Expired approved this item on Thursday 19 March 2020. Below is the council's own wording, with the papers it was decided on.
The Executive Member: (i) Approved the proposed programme of schemes for 2020/21; (ii) with the proviso that there would be further review and discussion regarding Holtby Lane, in due course. Officers will be reviewing the information received by Ward Member Cllr Waters and the Parish Council and providing a more detailed response in their consolidation report which would usually be received at this Decision Session in July (subject to change in the current climate). Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme. The Executive Member: (i) Approved the proposed programme of schemes for 2020/21; (ii) with the proviso that there would be further review and discussion regarding Holtby Lane, in due course. Officers will be reviewing the information received by Ward Member Cllr Waters and the Parish Council and providing a more detailed response in their consolidation report which would usually be received at this Decision Session in July (subject to change in the current climate). Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired, 8 pages
Recommendations
2. The Executive Member is asked to:
1) Approve the proposed programme of schemes for 2020/21. Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme.
Background
3. Following approval at Budget Council on 27 February 2020, the Transport Capital Budget for 2020/21 has been confirmed at £21,282k. The approved budget includes funding from the Local Transport Plan (LTP) grant and council resources.
4. The budget also includes significant funding from various external sources, including grant funding from the government’s Office of Low Emission Vehicles (OLEV) and the European Regional Development Fund (ERDF) for the Hyper Hubs project, the National Productivity Investment Fund, the West Yorkshire Transport Fund, and funding from the Department for Transport for the Outer Ring Road Dualling scheme. 5. Details of the budget are shown in Annex 1 to this report.
2020/21 Major Schemes
6. The allocations within the Major Schemes block will deliver a significant programme of improvements to the city’s transport infrastructure. Funding for these schemes has been secured from several external funding sources, with contributions from the council’s capital budgets as agreed at Budget Council in February 2020.
7. The City Centre Access & Security scheme will provide permanent measures to improve security in the city centre, following the decision in August 2019 to make the revised city centre traffic restrictions permanent. The proposed works to install physical measures (static and automated) to secure the Phase 1 area of the city centre were approved at the report to Executive in February 2020, and will be progressed in 2020/21. Work will also be carried out to install permanent measures at Racecourse Road/ Knavesmire Road, as agreed with York Racecourse.
8. York’s Clean Air Zone was launched on 31 January 2020, and requires every bus operating frequent services on or within the inner ring road to meet the Euro VI emission standard within 12 months. As previously reported to the Executive, the council has committed £1.4m funding (plus £0.2m grant funding from Defra) to bus operators to convert buses to the new standards. Following grant applications in autumn 2019, a total of 93 buses from five bus operators will be ‘retrofitted’ or replaced to meet the new emissions standard by the deadline of 31 January 2021.
9. Following the approval of the planning applications for the new ‘Hyper Hub’ charging points at Monks Cross and Poppleton, a tender process was carried out to appoint a contractor to implement the scheme, and it is expected that construction will be completed by September 2020. This scheme is funded by grant funding from the Office of Low Emission Vehicles (OLEV) and the European Regional Development Fund (ERDF), and a contribution from the council’s capital budget.
10. The Smarter Travel Evolution Programme (STEP) is funded by the National Productivity Investment Fund, and aims to implement real- time monitoring and associated infrastructure to allow York to prepare for future transport measures such as connected and autonomous vehicles. The work planned for 2020/21 includes the development of the new transport model for York, and an upgrade of communications equipment across the city.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.