Economy & Place Transport Capital Programme – 2020/21 Monitor 1
ApprovedExecutive4 papers
Decision Session - Executive Member for Transport - Expired approved this item on Tuesday 3 November 2020. Below is the council's own wording, with the papers it was decided on.
i. The amendments to the 2020/21 Economy & Place Transport Capital Programme were approved. ii. The Executive Member noted the progress of schemes in the Transport Capital Programme and the Emergency Active Travel Fund programme. Reason: To implement the Council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme. i. The amendments to the 2020/21 Economy & Place Transport Capital Programme were approved. ii. The Executive Member noted the progress of schemes in the Transport Capital Programme and the Emergency Active Travel Fund programme. Reason: To implement the Council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired, 10 pages
Recommendations
3. The Executive Member is asked to: 1) Approve the amendments to the 2020/21 Economy & Place Transport Capital Programme. 2) Note the progress of schemes in the Transport Capital Programme and the Emergency Active Travel Fund programme.
Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme.
Background
4. The COVID-19 lockdown significantly affected the capacity of the Transport and Highways teams to deliver the schemes in the Transport Capital Programme. Although progress has been maintained on many of the schemes resources had to be redirected to deliver additional urgent items, such as the Emergency Active Travel Fund schemes, in direct response to the outbreak. At the same time delivery capacity continues to be affected by social distancing and self isolation requirements. This has placed a significant amount of pressure on the Transport team who have worked at speed to deliver multiple schemes which under normal circumstances would have taken many months. These works, such as the delivery of footstreet extensions, have been broadly welcomed by businesses as supporting the York economy that faired particularly well over the summer compared to other Cities. To get the programme back on schedule it is proposed to commission additional resources to deliver the schemes which were delayed by the COVID 19 outbreak and the new schemes being brought into the programme.
5. Following approval at Budget Council on 27 February 2020, the Transport Capital Budget for 2020/21 was confirmed at £21,282k. The budget was then increased to £28,538k in August 2020 when the Executive Member was presented with the Consolidated Transport Capital Programme, which included all schemes and funding that had carried over from 2019/20.
6. The approved budget includes funding from the Local Transport Plan (LTP) grant and council resources, and significant funding from various external sources, including grant funding from the government’s Office of Low Emission Vehicles (OLEV) and the European Regional Development Fund (ERDF) for the Hyper Hubs project, the National Productivity Investment Fund, the West Yorkshire Transport Fund, and funding from the Department for Transport for the Outer Ring Road Dualling scheme.
2020/21 Major Schemes 7. Due to the impact of the COVID-19 lockdown measures, progress on the major schemes in the capital programme has been slower than anticipated due to the lockdown restrictions preventing works from going ahead, and staff resources being focused on COVID-19 measures and the Emergency Active Travel Fund programme.
8. The City Centre Access scheme has been affected by the expansion of the city centre Footstreets area as part of the council’s COVID-19 measures to provide additional space for pedestrians to accommodate social distancing measures. The scope of the scheme has been reviewed to assess the impact of these changes, and the outcome will be reported to the Executive. The design of the Racecourse security measures is ongoing, and the scheme will be implemented later in the year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.