TSAR Traffic Signal Refurbishment – Hull Road/Lilac Avenue
ApprovedExecutive3 papers
Decision Session - Executive Member for Transport - Expired approved this item on Thursday 19 March 2020. Below is the council's own wording, with the papers it was decided on.
To approve Option 1, the proposed crossing refurbishment shown in drawing Annex B. Reason: This option achieves the core aim of replacing the life- expired traffic signal asset such that it can continue be operated and repaired economically. It also provides improvements to cycling and walking infrastructure. To approve Option 1, the proposed crossing refurbishment shown in drawing Annex B. Reason: This option achieves the core aim of replacing the life-expired traffic signal asset such that it can continue be operated and repaired economically. It also provides improvements to cycling and walking infrastructure.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired, 6 pages
Summary
1. The traffic signalling equipment at this site is life expired, has become difficult and costly to maintain and needs to be replaced.
2. The TSAR (Traffic Signal Asset Renewal) programme is the means by which life expired traffic signal assets across the city are refurbished.
3. Although the programme is primarily about asset renewal, there is scope to take advantage of ‘easy wins’ whilst refurbishing the equipment. To that end, cycling facility alterations have been proposed that offer an improvement.
A decision is required to approve the proposed alterations.
Recommendations
4. The Executive Member is asked to:
Approve Option 1
Reason: This option achieves the core aim of replacing the life-expired traffic signal asset such that it can continue be operated and repaired economically. It also provides improvements to cycling and walking infrastructure.
Background
5. A report was brought to the Executive Member for Transport and Planning on 12th November 2015 to seek approval to undertake the 5- year ‘TSAR’ (Traffic Signal Asset Renewal) programme.
6. This programme entails a replacement of life expired traffic signal assets around York. The focus is on replacing equipment that is liable to imminent failure, rather than seeking to improve congestion or achieve a similar transport improvement goal. However, where ‘easy wins’ can be achieved at the same time as replacing obsolete equipment, these will be taken advantage of.
7. To date, 31 sets of signals have been refurbished and a further 6 are programmed in for the 20/21 financial year.
Consultation
8. The scope of the works included within this proposal are relatively minor and in normal circumstances would not require an executive decision for approval or an external consultation.
9. However, due to changes to the cycling facilities at the crossing and the surrounding area a consultation has been carried out to offer key user groups an opportunity to have their say on the proposed scheme.
10. A summary of the consultation feedback can be found in Annex A.
Options
11. The following options are available:
12. Option 1 – Approve the proposed crossing refurbishment shown in drawing Annex B
13. Option 2 – Do not approve the presented option Analysis
Option 1
Description of Changes
14. Refurbish the existing pedestrian / cyclist crossing into a standard Toucan crossing provided with all new equipment, including signal heads, poles, cabling, cabinets, detectors, communications and ducting.
15. The crossing width will be increased to accommodate cyclists and pedestrians and tactile paving replaced to bring these facilities in line with modern standards.
16. Formalisation of the shared cycleway/footway on the northern side of Hull Road east of the junction with Lilac Avenue.
17. This includes removing the small triangular area of grass to open the area up to users. The green space will be relocated to the back of the footway. Cyclist provision to join / leave the carriageway both on Hull Road and Lilac Avenue will be provided.
18. Formalise the pedestrian / cyclist areas into shared use footways on the southern side of the crossing including the pedestrian / cyclist link to Thief Lane. This will include brining all the footways to a single level and allow cyclists and pedestrians to formally mix rather than the current arrangement. Cyclist on / off slips to the Hull Road carriageway will be provided.
19. Appropriate signing, road markings and tactile paving will be installed to designate shared space at multiple sites across the site
20. Signal Controller to be relocated from within the verge south of the crossing to the footway/cycleway leading to Thief Lane to maximise footway width and ease of maintenance.
21. The estimated cost of the work to the Traffic Signal at Hull Road near Lilac Avenue detailed in Annex B is £80,000.00 Reasoning
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.