Green Dykes Lane – Proposed Puffin Pedestrian Crossing
ApprovedExecutive3 papers
Decision Session - Executive Member for Transport - Expired approved this item on Tuesday 3 November 2020. Below is the council's own wording, with the papers it was decided on.
i. The Executive Member approved the scheme as shown in Annex A to provide a crossing point on Green Dykes Lane. Reason: To provide a safe and formal crossing point on Green Dykes Lane, which is in close proximity to the University of York and a local primary school. i. The Executive Member approved the scheme as shown in Annex A to provide a crossing point on Green Dykes Lane. Reason: To provide a safe and formal crossing point on Green Dykes Lane, which is in close proximity to the University of York and a local primary school.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired, 12 pages
Decision Session – Executive Member for 03 November 2020 Transport
Report of the Corporate Director – Economy and Place
Ward Committee scheme FS-19-05 / HR-19-06:
Green Dykes Lane – Proposed Puffin Pedestrian Crossing Summary
1. This report presents the outcome of the feasibility study, likely cost, and impact of providing a pedestrian puffin crossing on Green Dykes Lane, near its junction with Thief Lane.
Recommendations 2. The Executive Member is asked to approve Option 1 detailed below and the design shown in Annex A. Reason: to provide a safe and formal crossing point on Green Dykes Lane, which is in close proximity to the University of York and a local primary school. Background
3. Over the years, City of York Council have received several requests for formal crossing facilities or a school crossing patrol (or both) to be provided on Green Dykes Lane, in the vicinity of the Thief Lane junction, to cater mostly for children being taken to St Lawrence’s CE Primary School by their parents. Several changes have been made at the Green Dykes Lane / Thief Lane / University Road junction over the years.
4. Prior to 2002 alterations were made to the Green Dykes Lane kerb-line to build it out and reduce the crossing distance. Red anti- skid surfacing was also applied across the crossing to highlight its presence. 5. Between 2012 and 2014 an extended Keep Clear area was put in on the downhill side of Green Dykes Lane to stop queuing traffic which had backed up from the Hull Road junction from blocking the left and right turning traffic emerging from the western side of Thief Lane.
6. The junction has been investigated as a potential site for a school crossing patrol but was deemed to be too difficult to patrol as there are too many traffic movements for the patroller to take into consideration, so they would have to be located further down Green Dykes Lane away from the crossing desire line.
7. In November 2018 local ward members (Hull Road and Fishergate) commissioned a crossing assessment for the junction. Surveys were then undertaken and these are outlined in the ‘Traffic Surveys’ section. Feasibility Assessment
8. As part of the feasibility study the following key pieces of work have been undertaken
Developing an outline design
Detailed traffic and pedestrian surveys
A Statutory undertakers utility search (to assess the extent and likely cost of protecting or diverting underground services affected by the scheme)
Undertaking a Road Safety Audit, to assess the road safety implications of the proposals
Producing a cost estimate for delivering the project
Initial consultation with local Ward Councillors (to gauge support and identify concerns) Outline Design
9. The outline design developed from the feasibility study is shown on the plan in Annex A. This provides a puffin pedestrian crossing situated near numbers 22 and 27 Green Dykes Lane. This location offered the only suitable area to install a crossing facility taking into consideration the existence of significant utility apparatus in the verges and footways, access driveways to properties, and the location of mature trees. It is also as close to the natural desire line for pedestrians to cross as is feasible. The existing tactile crossing points on the north side of Thief Lane will be removed to further facilitate the use of this proposed crossing point. Unfortunately the zig-zag markings, which are a requirement for formal crossings to keep sight-lines clear, will remove on-street parking between the Kexby Avenue and Thief Lane junctions. 10. The carriageway surface across the proposed crossing and over the junction of Thief Lane, will be resurfaced and relined, thereby providing a new improved surface with enhanced skid resistance to make the area safer.
Traffic Surveys
11. In order to assess the traffic and pedestrian movements at and near the junction the following surveys were commissioned:
Full classified vehicle count over a 12 hour period (7am to 7pm)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.