York Railway Station Gateway – Funding and Delivery

Approved Executive 4 papers

Executive approved this item on Thursday 26 November 2020. Below is the council's own wording, with the papers it was decided on.

Item60

Resolved

(i) That the scope, budget, delivery and procurement strategy of the project be approved. Reason: To enable arrangements to be put in place to purchase land, place orders with utility companies and proceed with the detailed design and procurement of Packages 1, 2 and 4 of the scheme. (ii) That the Station Gateway budget be increased by £12.250m to reflect the WYCA Transforming Cities grant funding. Reason: To ensure that the capital programme reflects the latest funding position. (iii) That authority be delegated to the Corporate Director of Economy & Place, in consultation with the s151 Officer and the Director of Governance or her delegated officers, to draw down further funds from the West Yorkshire-Plus Transport Fund to complete the land purchase negotiations and take such steps as are necessary to enter into the resulting legal agreement(s). Reason: In order to acquire land from Canada Life (George Stephenson House) and Network Rail to enable the delivery of the scheme. (iv) That authority be delegated to the Corporate Director of Economy & Place, in consultation with the s151 Officer and the Director of Governance or her delegated officers, to draw down funds from West Yorkshire-Plus Transport fund to place orders with utility companies to fund Package 1: Enabling Works (package value £2.04m) to divert services from Queen Street Bridge through the station car park. Reason: To enable delivery of Package 1: Enabling Works. (v) That authority be delegated to the Corporate Director of Economy & Place, in consultation with the s151 Officer and the Director of Governance or her delegated officers, to draw down funds from West Yorkshire-Plus Transport fund to issue a task order to commence detailed design of the scheme. Reason: To enable the production of detailed cost plans and to progress the scheme to procurement. (i) That the scope, budget, delivery and procurement strategy of the project be approved. Reason: To enable arrangements to be put in place to purchase land, place orders with utility companies and proceed with the detailed design and procurement of Packages 1, 2 and 4 of the scheme. (ii) That the Station Gateway budget be increased by £12.250m to reflect the WYCA Transforming Cities grant funding. Reason: To ensure that the capital programme reflects the latest funding position. (iii) That authority be delegated to the Corporate Director of Economy & Place, in consultation with the s151 Officer and the Director of Governance or her delegated officers, to draw down further funds from the West Yorkshire-Plus Transport Fund to complete the land purchase negotiations and take such steps as are necessary to enter into the resulting legal agreement(s). Reason: In order to acquire land from Canada Life (George Stephenson House) and Network Rail to enable the delivery of the scheme. (iv) That authority be delegated to the Corporate Director of Economy & Place, in consultation with the s151 Officer and the Director of Governance or her delegated officers, to draw down funds from West Yorkshire-Plus Transport fund to place orders with utility companies to fund Package 1: Enabling Works (package value £2.04m) to divert services from Queen Street Bridge through the station car park. Reason: To enable delivery of Package 1: Enabling Works. (v) That authority be delegated to the Corporate Director of Economy & Place, in consultation with the s151 Officer and the Director of Governance or her delegated officers, to draw down funds from West Yorkshire-Plus Transport fund to issue a task order to commence detailed design of the scheme. Reason: To enable the production of detailed cost plans and to progress the scheme to procurement.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 17 pages

Summary

1. The purpose of this report is to update the Executive on the current status of the Station Frontage project, to seek Members approval for a phased delivery approach and to seek approval for a series of recommendations that allows progress whilst mitigating the Council’s risks.

Recommendations 2. The Executive is asked to:

i) Approve the project scope, budget, delivery and procurement strategy of the scheme.

Reason: To enable arrangements to be put in place to purchase land, place orders with utility companies and to proceed with the detailed design and procurement of Packages 1, 2 and 4 of the scheme. ii) Increase the Station Gateway budget by £12.250m to reflect the WYCA Transforming Cities grant funding.

Reason: To ensure the capital programme reflects the latest funding position

iii) Delegate authority to the Corporate Director for Economy and Place (in consultation with the s151 Officer and the Director of Governance or her delegated officers) to draw down further funds from West Yorkshire-Plus Transport Fund to complete land purchase negotiations and take such steps as are necessary to enter into the resulting legal agreement(s). Reason: To acquire land from Canada Life (George Stephenson House) and Network Rail to enable the delivery of the scheme.

iv) Delegate authority to the Corporate Director for Economy and Place (in consultation with the s151 Officer and the Director of Governance or her delegated officers) to draw down funds from West Yorkshire- Plus Transport Fund to place orders with utility companies to fund Package 1: Enabling Works (package value of £2.04m) to divert services from Queen Street Bridge through the station car park.

Reason: To enable the delivery of Package 1: Enabling Works

v) Delegate authority to the Corporate Director for Economy and Place (in consultation with the s151 Officer and the Director of Governance or her delegated officers) to draw down funds from West Yorkshire- Plus Transport Fund to issue a task order to commence detailed design of the scheme.

Reason: To enable the production of detailed cost plans and to progress the scheme to procurement.

Future Reports 3. Future reports will be brought to Executive to seek approval for further works packages with procured prices, detailed scheme design and confirmation of appropriate mitigation of delivery risk of subsequent packages.

Background 4. The York Railway Station Gateway scheme comprises a coordinated, multi-modal package of interventions in and around York Railway Station. The scheme complements and connects the proposals being progressed to the west and east of the station and will transform the Station Gateway to York; significantly improving access, addressing carbon and air quality issues, and directly supporting delivery of housing and commercial uses on the York Central development site. Therefore, City of York Council (CYC), in collaboration with Network Rail (NR) and London North East Railway (LNER), has developed a masterplan that proposes to reorganise highway and public realm areas to the front of York Station through:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Delivery StrategyAppendix 1 15 pages Download
PDF
Delivery Strategy DrawingsAppendix 1a 4 pages Download
PDF
York Station Front: Better Decision Making Tool: CopyAppendix 2 7 pages Download
PDF
York Railway Station Gateway: Funding and DeliveryReport 17 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at York

Search all
  1. York Railway Station Gateway – Funding and DeliveryThis decision
  2. York Railway Station Gateway - Project Update and LNER Funding & Development AgreementNoted
  3. Station Building, Railway Station, Station Road, York YO24 1AY [19/00542/LBC]Approved
  4. National Railway Museum, Leeman Road, York YO26 4XD (14/02862/FULM)Approved
  5. Traffic Arrangements at York Railway StationAgreed
  6. Reports on Traffic Management at York Railway Station and York North WestNoted

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies