(i) That the 2020/21 revised budget of £144.683m, as set out in Table 1 at paragraph 6 of the report, be noted. (ii) That the re-stated capital programme for 2020/21-2024/25, as set out in Table 2 at paragraph 43, be noted. Reason: To enable the effective management and monitoring of the council’s capital programme. (i) That the 2020/21 revised budget of £144.683m, as set out in Table 1 at paragraph 11 of the report, be noted. (ii) That the re-stated capital programme for 2020/21-2024/25, as set out in Table 2 at paragraph 43, be noted. Reason: To enable the effective management and monitoring of the council’s capital programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1 The purpose of this report is to set out the projected outturn position for 2020/21including any under/over spends and adjustments, along with requests to re-profile budgets to/from current and future years.
2 The 2020/21 capital programme approved by Council on 27 February 2020 and updated for amendments reported to Executive in the 2019/20 outturn report resulted in an approved capital budget of £181.221m.
3 Whilst the content of this report focuses on reporting amendments to budgets in year and re-profiling to future years, as reported previously to Executive, there has been a significant impact on the Council’s financial position as a result of the COVID-19 pandemic.
4 The Monitor 1 report resented to Executive on 1st October outlined the work that has been done to review the capital programme in light of the pandemic to ensure that planned capital investment is consistent with the recovery plan, that it delivers the required outcomes and that, where necessary, ongoing schemes are reviewed to ensure they are compliant with any new regulations relating to COVID-19. The Council is facing a significant financial challenge as a result of the pandemic and therefore any expenditure that doesn’t clearly contribute to the delivery of the Council Plan needs to be challenged so that resources can be directed at areas where they will have the most impact.
5 Careful and close monitoring of the financial assumptions will continue for all schemes included in the programme. In most cases schemes are already subject to the agreement of detailed business cases so will progress as planned. These detailed business cases will take account of the current climate and therefore will incorporate any specific financial or COVID-19 issues.
6 Whilst capital investment has been disrupted due to the pandemic, progress has still been made in a number of areas including: Purchase of land for the Northern Forest Effective rollout of ICT to enable continued remote working Continued delivery of shared ownership homes Lowfield Green new build site has had reservations for 20 of the 24 properties that are available for market sale or shared ownership. These properties are due to be completed in March 2021
7 It should be noted that the Asset Strategy Review report also on this Agenda contains information on capital schemes which are not reflected in this report. If approved by Members any changes agreed will be incorporated into the capital programme at Monitor 3.
Recommendations
8 Executive is asked to:
Recommend to Full Council the adjustments resulting in a decrease in the 2020/21 budget of £36.538m as detailed in the report and contained in Annex A. Note the 2020/21 revised budget of £144.683m as set out in paragraph 6 and Table 1. Note the restated capital programme for 2020/21 – 2024/25 as set Reason: to enable the effective management and monitoring of the Council’s capital programme.
Consultation
9 The capital programme was developed under the capital budget process and agreed by Council on 27 February 2020. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals and associated capital receipt sales do follow a consultation process with local Councillors and residents in the locality of the individual schemes. Summary of Key Issues
10 A decrease of £36.538m is detailed in this monitor resulting in a revised capital programme for 2020/21 of £144.683m. There is an increase of £1.141m in 2020/21 and a re-profiling of budgets to future years totalling £37.679m. The majority of this re-profiling is due to delays in schemes such as York Central, The Guildhall and WYTF Station Frontage.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.