i. Noted the 2023/24 revised budget of £148.745m as set out in paragraph 6 and Table 1 of the report. ii. Noted the restated capital programme for 2023/24 – 2027/28 as set. Reason: to enable the effective management and monitoring of the Council’s capital programme. i. Noted the 2023/24 revised budget of £148.745m as set out in paragraph 6 and Table 1 of the report. ii. Noted the restated capital programme for 2023/24 – 2027/28 as set. Reason: to enable the effective management and monitoring of the Council’s capital programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Meeting: Executive Meeting date: 14/09/2023 Report of: Chief Finance Officer – Debbie Mitchell Portfolio of: Cllr Katie Lomas – Executive Member for Finance, Performance, Major Projects, Human Rights, Equalities and Inclusion
Decision Report: Capital Programme – Monitor 1 2023/24
Subject of Report 1. The purpose of this report is to set out the projected outturn position for 2023/24 including any under/over spends and adjustments, along with requests to re-profile budgets to/from current and future years.
2. A decrease of £135.903m is detailed in this monitor resulting in a revised capital programme for 2023/24 of £148.745m. There is a decrease of £10.404m and a re-profiling of budgets to future years totalling £125.499m. This is mainly due to a thorough review of the timings of the capital programme to reflect latest timescales. Key schemes that have been re-profiled within this figure are York Central Infrastructure (£35m), York Outer Ring Road Dualling (£23m), LA Homes – New Build & Burnholme (£27m). Details of these schemes can be found in the body of the report below.
3. Table 1 outlines the variances reported against each portfolio area and a summary of the key exceptions and implications on the capital programme are highlighted in the paragraphs that follow. Department Current Projected Adjustment Reprofile Total Paragraph Approved Outturn Variance Budget £m £m Ref £m £m £m
Total 284.648 148.745 (10.404) (125.499) (135.903)
Table 1 Capital Programme Forecast Outturn 2023/24
4. As a result of the changes highlighted above the revised 5 year capital programme is summarised in Table 2. Gross Capital 2023/24 2024/25 2025/26 2026/27 2027/28 Total Programme
Table 2 Revised 5 Year Capital Programme Funding the 2023/24 – 2027/28 Capital Programme
5. The revised 2023/24 capital programme of £521.617 m is funded from £184.044m of external funding and £337.533m of internal funding. Table 3 shows the projected call on resources going forward. 2023/24 2024/25 2025/26 2026/27 2027/28 Total
£m £m £m £m £m £m
Gross Capital Programme 148.745 172.461 86.477 77.551 36.383 521.617
Council Controlled Resources 81.687 118.607 45.083 62.308 29.888 337.533
Total Funding 148.745 172.461 86.477 77.551 36.383 521.617
Table 3 – 2023/24 –2027/28 Capital Programme Financing
6. The Council controlled figure is comprised of a number of resources that the Council has ultimate control over. These include Right to Buy receipts, revenue contributions, supported (government awarded) borrowing, prudential (Council funded) borrowing, reserves (including Venture Fund) and capital receipts
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.