Capital Programme Monitor 2 (18:07)

Decided Executive 3 papers

Executive decided this item on Thursday 16 November 2023. Below is the council's own wording, with the papers it was decided on.

Item53

Resolved

Recommended: i. To Full Council the adjustments resulting in a decrease in the 2023/24 budget of £13.009m as detailed in the report and contained in Annex A.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 18 pages

Meeting: Executive Meeting date: 16/11/2023 Report of: Chief Finance Officer – Debbie Mitchell Portfolio of: Cllr Katie Lomas – Executive Member for Finance, Performance, Major Projects, Human Rights, Equalities and Inclusion

Decision Report: Capital Programme – Monitor 2 2023/24

Subject of Report 1. The purpose of this report is to set out the projected outturn position for 2023/24 including any under/over spends and adjustments, along with requests to re-profile budgets to/from current and future years.

2. A decrease of £13.009m is detailed in this monitor resulting in a revised capital programme for 2023/24 of £135.736m. There is an increase of £1.175m and a re-profiling of budgets to future years totalling £14.184m. This is mainly due to a thorough review of the phasing of the capital programme across Transport, Highways and Environment to reflect lates timescales.

3. Table 1 outlines the variances reported against each portfolio area and a summary of the key exceptions and implications on the capital programme are highlighted in the paragraphs that follow.

Page 1 of 18 Department Current Projected Adjustment Reprofile Total Paragraph Approved Outturn Variance Budget £m £m Ref £m £m £m

Children’s services 16.900 16.900 - - - 12 – 20

Adult Social Care 1.236 1.236 - - - -

Housing Services 41.697 42.519 1.530 (0.708) 0.822 21 – 35

Transport, Highways & 64.548 59.635 - (5.183) (5.183) 36 – 59 Environment

Regen, Economy & 12.909 4.995 (0.355) (7.559) (7.914) 60 - 62 Property Services Community Stadium 0.271 0.271 - - - -

ICT 3.722 3.722 - - - 65 - 66

Customer & Corporate 2.063 2.063 - - - 63 – 64 Services Communities & Culture 4.338 4.338 - - - 67 – 71

Climate Change 1.061 1.061 - (0.734) (0.734) 72

Total 148.745 135.736 (1.175) (14.184) (13.009)

Table 1 Capital Programme Forecast Outturn 2023/24

Page 2 of 18 4. As a result of the changes highlighted above the revised 5 year capital programme is summarised in Table 2.

Gross Capital 2023/24 2024/25 2025/26 2026/27 2027/28 Total Programme

£m £m £m £m £m £m

Children’s services 16.900 6.020 5.400 0.920 - 29.240

Adult Social Care 1.236 0.682 0.705 0.728 0.752 4.103

Housing Services 42.519 54.897 35.181 45.044 14.638 192.279

Transport, Highways & 59.365 74.520 41.296 27.564 17.698 220.443 Environment

Regen, Economy & 4.995 43.809 0.275 0.275 0.275 49.629 Property Services

Community Stadium 0.271 - - - - 0.271

ICT 3.722 2.820 3.170 2.820 2.820 15.352

Customer & Corporate 2.063 0.427 0.200 0.200 0.200 3.090 Services

Communities & Culture 4.338 2.026 - - - 6.364

Climate Change 0.327 1.384 0.250 - - 1.961

Revised Programme 135.736 185.685 86.477 77.551 36.383 522.732

Table 2 Revised 5 Year Capital Programme Funding the 2023/24 – 2027/28 Capital Programme

Page 3 of 18 5. The revised 2023/24 capital programme of £522.732m is funded from £184.172m of external funding and £338.560m of internal funding. Table 3 shows the projected call on resources going forward.

2023/24 2024/25 2025/26 2026/27 2027/28 Total

£m £m £m £m £m £m

Gross Capital Programme 135.736 186.585 86.477 77.551 36.383 522.732

Funded by:

External Funding 65.453 55.587 41.394 15.243 6.495 184.172

Council Controlled Resources 70.283 130.998 45.083 62.308 29.888 338.560

Total Funding 135.736 186.585 86.477 77.551 36.383 522.732

Table 3 – 2023/24 –2027/28 Capital Programme Financing

6. The Council controlled figure is comprised of a number of resources that the Council has ultimate control over. These include Right to Buy receipts, revenue contributions, supported (government awarded) borrowing, prudential (Council funded) borrowing, reserves (including Venture Fund) and capital receipts

7. In financing the overall capital programme the Chief Finance Officer will use the optimum mix of funding sources available to achieve the best financial position for the Council. Therefore an option for any new capital receipts would be to use these to replace assumed borrowing, thereby reducing the Councils’ borrowing levels and associated revenue costs.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Abbreviated Monitor 2 annexAppendix 2 pages Download
PDF
Capital Programme Monitor 2 (18:07)Report 18 pages DownloadRead as text
PDF
View item 53. as HTML 165 KBReport 165 KB Copy on its way

At this meeting

Whole meeting

On this subject at York

Search all
  1. Capital Programme Monitor 2 (18:07)This decision
  2. Capital Programme Monitor Update 2 Report (4:47pm)Noted
  3. Capital Programme - Monitor 1 2026/27 (4:46pm)Noted
  4. Capital Programme Outturn 2025/26 and Revisions to the 2026/27 - 2029/30 ProgrammeApproved
  5. Recommendations of Executive in relation to the Capital Programme - Monitor 3 2025/26Approved
  6. Capital Programme - Monitor 3 2025/26Approved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies