City of York Council
Executive, Tuesday 4 November 2025 at 4.30pm

Capital Programme - Monitor Two 2025/26

Approved Executive 3 papers

AI summaryCity of York Council Executive unanimously recommends a £17.865m reduction to the 2025/26 capital budget, notes a revised £162.466m budget, and approves a £1.3m budget transfer for Lendal Bridge. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFull Council will consider the recommended budget adjustments. [D]
Money£17.865m [D]Revised budget: £162.466m [D][P2]. Transfer: £1.3m [D][P65].
What happens nextFull Council consideration [D]The recommended adjustments would reduce the 2025/26 budget. [D]
Who it affectsAll wards affected [P98]Reductions could affect staff and resident wellbeing. [P96]

What was decided

Executive recommends adjustments that reduce the 2025/26 budget by £17.865m. [D][P2] Report P2

Executive notes the revised 2025/26 capital budget of £162.466m and the restated five year capital programme. [D][P2][P5] Report P2, P5

Executive approves the £1.3m virement from Integrated Transport to Lendal Bridge for additional works. [D][P65] Report P65

Why

The aim is effective management and monitoring of the Council's capital programme. [D]

The changes include £3.992m of additional funding and £21.857m re-profiled to future years. [P2] Report P2

A review of transport project commitments mainly caused the budget changes. [P2] Report P2

What happens next

Full Council will consider the recommended £17.865m budget decrease. [D]

Lendal Bridge construction is programmed for April next year. The additional scope includes repainting metalwork and coating troughing, parapets and elevations. [D][P64][P65][P99] Report P64, P65, P99

A full update of Children and Education Services summer works will be provided at Monitor 3. [P10] Report P10

The money

  • £17.865m Decrease in the 2025/26 capital budget Report P2
  • £162.466m Revised 2025/26 capital budget Report P2
  • £1.3m Virement from Integrated Transport to Lendal Bridge Report P65
  • £3.992m Increase from additional funding and adjustments Report P2
  • £21.857m Budgets re-profiled to future years Report P2
  • £442.153m Revised 2025/26 to 2029/30 capital programme Report P6
  • £169.147m External funding for the five year programme Report P6
  • £273.006m Internal funding for the five year programme Report P6

Options considered

  • Chosen: Transfer £1.3m from Integrated Transport to Lendal Bridge. It funds additional works above essential maintenance. [D][P65][P99] Report P65, P99
  • Chosen: Include £1.795m of City Centre Sustainable Corridor reprofiling to 2026/27. This supports delivery alongside other city centre projects and avoids traffic flow conflict. [D][P43] Report P43
  • Chosen: Include £2.5m of P & R Interchange Upgrades reprofiling to 2026/27. Two remaining sites require planning applications, extending delivery into next year. [D][P47] Report P47
  • Chosen: Include £1.1m of Riverside Path Improvements reprofiling to 2026/27. Delivery depends on the Riverbank stability impact assessment. [D][P54] Report P54
  • Chosen: Include £1.9m of Askham Bar P & R reprofiling to 2026/27. Land ownership issues remain while design work continues. [D][P54] Report P54
  • Chosen: Add the £421k Carbon Negative Challenge Fund bid to the programme. The successful bid will enter the programme once final documentation is accepted. [P24] Report P24

Implications

  • Financial: A capital programme review will identify ways to reduce capital expenditure. [P96] Report P96
  • Other: Reductions in some areas could affect staff and residents' health and wellbeing. The Council will monitor impacts and mitigate them where possible. [P96] Report P96
  • Legal: The report has no further legal implications, but individual schemes will receive legal advice where necessary. [P96] Report P96
  • Staffing: There are no direct HR implications. Variations with staffing implications will follow consultation, HR policies and procedures. [P96] Report P96
  • Equalities: There are no direct equalities and human rights implications. Individual schemes will have impact assessments in the usual way. [P96] Report P96
  • Climate: There are no direct environment and climate action implications from the report. [P96] Report P96
  • Other: The report has no direct procurement, affordability, communications or economy implications. It processes no personal data, so no data protection impact assessment is required. [P96] Report P96
  • Risk: Capital programme risks are managed through regular monitoring, project management, and internal and external audit reviews. [P97] Report P97

Who and where

  • All wards Report P98
  • Council staff and residents affected by spend reductions Report P96
  • Vulnerable people using telecare and disability equipment Report P14, P15, P16
  • Council tenants receiving housing adaptations Report P19
  • Homeowners and tenants in private properties receiving adaptations Report P19
  • Private sector households receiving Warm Homes retrofits Report P20, P21
  • Library users in Haxby, Clifton and Acomb Report P34
  • People using transport and active travel schemes Report P43, P49

Timeline

  • 27 February 2025: The 2025/26 capital programme was approved with a budget of £180.743m. [P1] Report P1
  • 2nd September 2025: Monitor 1 reduced the budget by £0.412m to £180.331m. [P2][P102] Report P2, P102
  • 23/10/2025: The report was approved. [P101] Report P101
  • January 2026: Warm Homes retrofit delivery is expected to commence. [P21] Report P21
  • March 2026: The Future Libraries Investment Programme is expected to be complete. [P35] Report P35
  • 31 March 2026: Completion is set for the Bell Farm refurbishment and retrofit. [P31] Report P31
  • Spring 2026: York Station Gateway work is expected to continue. [P42] Report P42
  • April next year: Lendal Bridge construction is programmed to commence. [P64] Report P64

Plain English for the jargon

  • Capital programme: The Council's planned capital spending over five years. [P5][P6]
  • Monitor: A review of the capital programme and proposed budget changes. [P1][P2]
  • Virement: A transfer of budget between spending areas. [P65]
  • Reprofile: Move planned spending into another financial year. [P2][P43]
  • BSIP: Bus Service Improvement Plan. [P43]
  • P & R: Park and Ride. [P46]
  • DFG: Disabled Facilities Grant. [P16]
  • TSAR: Traffic Signal Asset Renewal Programme. [P49]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item163

Resolved

Resolved (unanimously): That Executive a) Recommends to Full Council the adjustments resulting in a decrease in the 2025/26 budget of £17.865m as detailed in the report. b) Notes the 2025/26 revised budget of £162.466m as set out in paragraph 10 and Table 1 of the report. c) Approves the virement of £1.3m between the Integrated Transport budget and Lendal Bridge budget to fund the additional works set out in the report. d) Notes the restated capital programme for 2025/26 – 2029/30 as set out in Annex 1. Reason: To enable the effective management and monitoring of the Council’s capital programme.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 26 pages

Background

8. The 2025/26 capital programme was approved by Council on 27 February 2025 and updated for amendments reported to Executive in the 2024/25 outturn report, which resulted in an approved capital budget for 2025/26 of £180.743m.

9. At Monitor 1 report (September 2nd, 2025) there was a decrease of £0.412m resulting in a revised capital programme of £180.331m. 10. A decrease of £17.865m is detailed in this monitor resulting in a revised capital programme for 2025/26 of £162.466m. There is an increase of £3.992m due to additional funding being awarded / approved and a re- profiling of budgets to future years totalling £21.857m. This is mainly due to a review of Transport project commitments.

11. Table 1 outlines the variances reported against each Directorate area and a summary of the key exceptions and implications on the capital programme are highlighted in the paragraphs that follow.

Current Projected Adjust Reprofile Total Paragraph Department Approved Outturn £m £m Variance Ref Budget £m £m £m Children’s services 15.849 15.849 - - - 17-20 Adult Social Care 1.197 1.039 (0.158) - (0.158) 21-24 Housing Services 48.682 48.682 - - - 25-45 Communities 5.831 4.017 (1.814) - (1.814) 46-53 Transport, Highways 73.652 58.062 3.956 (19.546) (15.590) 54-111 & Environment City Development 27.594 27.691 2.311 (2.214) 0.097 112-124 Property Services 1.671 1.701 0.127 (0.097) 0.030 125-128 ICT 4.109 3.929 (0.180) - (0.180) 129-131 Corporate Services 1.746 1.496 (0.250) - (0.250) - Total 180.331 162.466 3.992 (21.857) (17.865) Table 1 Capital Programme Monitor 2 2025/26

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme: Monitor Two 2025/26Report 26 pages DownloadRead as text
PDF
Item 9: Capital Programme: Monitor 2 2025-26: Annex 1Appendix 3 pages Download
PDF
View item 163. as HTML 217 KBReport 217 KB Copy on its way

At this meeting

Whole meeting

Who was there

7 of 8 attended
CD
Councillor Claire DouglasChair, present
PK
Councillor Peter KilbaneVice-Chair, present
JK
Councillor Jenny KentCommittee Member, present
KL
Councillor Katie LomasCommittee Member, present
MP
Councillor Michael PavlovicCommittee Member, present
KR
Councillor Kate RaviliousCommittee Member, apologies
LS
Councillor Lucy Steels-WalshawCommittee Member, present
RW
Councillor Robert WebbCommittee Member, present

On this subject at York

Search all
  1. Capital Programme - Monitor Two 2025/26This decision
  2. Capital Programme Monitor Update 2 Report (4:47pm)Noted
  3. Capital Programme - Monitor 1 2026/27 (4:46pm)Noted
  4. Capital Programme Outturn 2025/26 and Revisions to the 2026/27 - 2029/30 ProgrammeApproved
  5. Recommendations of Executive in relation to the Capital Programme - Monitor 3 2025/26Approved
  6. Capital Programme - Monitor 3 2025/26Approved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies