The Joint Strategic Committee:- (a) with respect to the Capital Investment Programme of Adur District Council i. noted the reprofiling of the Adur District Council capital schemes as advised in paragraphs 7.2.1 and Appendix 3; ii. approved the use of ring-fenced capital receipts to fund the overspend of £23,134 on the Shoreham Air Crash Memorial Project as detailed in paragraph 7.2.3; iii. agreed to increase the budget for the Extended Ultrafast Network Fibre Network by £800,000 to £3.3m, funded by a combination of the Local Growth Fund Grant funding of £676,500 and a contribution from the WSCC Business Rate Pool of £1,250,000 as detailed in paragraph 7.1.3. The Adur District Council share of this scheme was £376,000; iv. approved the virement to fund the overspend on the purchase of wheeled bins for the new alternate weekly collection service and approve the funding as detailed in paragraph 7.1.2; v. approved the increase in the Disabled Facilities Grant Budget by £64,790 funded by Better Care Fund Grant as detailed in paragraph 7.2.4. (b) with respect to the Capital Investment Programme of Worthing Borough Council i. noted the reprofiling of the Worthing Borough Council capital schemes as advised in paragraphs 7.3.1 and Appendix 4; ii. approved the virement to fund the overspend on the purchase of wheeled bins for the new alternate weekly collection service and approve the funding as detailed in paragraph 7.1.2; iii. agreed to increase the budget for the Extended Ultrafast Network Fibre Network by £800,000 to £3.3m funded by a combination of the Local Growth Fund Grant funding of £676,500 and a contribution from the WSCC Business Rate Pool of £1,250,000 as detailed in paragraph 7.1.3. The Worthing Borough Council share of this scheme was £424,000; iv. approved the increase in the Disabled Facilities Grant Budget by £204,240 funded by Better Care Fund Grant as detailed in paragraph 7.3.2.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1This report updates the Joint Strategic Committee on the progress made on the 2019/20 Capital Investment Programmes for Adur District Council, Worthing Borough Council. The programmes include schemes which support the delivery of services by the Joint Services Committee.
1.2The following appendices have been attached to this report:
Appendix 1: Adur District Council Capital Monitoring Summary Appendix 2: Worthing Borough Council Capital Monitoring Summary Appendix 3: Adur District Council Reprofiled Budgets Appendix 4: Worthing Borough Council Reprofiled Budgets
Recommendations
2.1The Joint Strategic Committee is asked: (a) With respect to the Capital Investment Programme of Adur District Council. i) To note the reprofiling of the Adur District Council capital schemes as advised in paragraphs 7.2.1 and Appendix 3.
ii) To approve the use of ring-fenced capital receipts to fund the overspend of £23,134 on the Shoreham Air Crash Memorial Project as detailed in paragraph 7.2.3. iii) Agree to increase the budget for the Extended Ultrafast Network Fibre Network by £800,000 to £3.3m funded by a combination of the Local Growth Fund Grant funding of £676,500 and a contribution from the WSCC Business Rate Pool of £1,250,000 as detailed in paragraph 7.1.3. The Adur District Council share of this scheme is £376,000.
iv) To approve the virement to fund the overspend on the purchase of wheeled bins for the new alternate weekly collection service and approve the funding as detailed in paragraph 7.1.2.
v) To approve the increase in the Disabled Facilities Grant Budget by £64,790 funded by Better Care Fund Grant as detailed in paragraph 7.2.4.
b) With respect to the Capital Investment Programme of Worthing Borough Council.
i) To note the reprofiling of the Worthing Borough Council capital schemes as advised in paragraphs 7.3.1 and Appendix 4.
ii) To approve the virement to fund the overspend on the purchase of wheeled bins for the new alternate weekly collection service and approve the funding as detailed in paragraph 7.1.2.
iii) Agree to increase the budget for the Extended Ultrafast Network Fibre Network by £800,000 to £3.3m funded by a combination of the Local Growth Fund Grant funding of £676,500 and a contribution from the WSCC Business Rate Pool of £1,250,000 as detailed in paragraph 7.1.3. The Worthing Borough Council share of this scheme is £424,000.
v) To approve the increase in the Disabled Facilities Grant Budget by £204,240 funded by Better Care Fund Grant as detailed in paragraph 7.3.2.
3. CONTEXT
3.1In accordance with the Councils’ Capital Strategy, the Capital Working Group oversees the implementation and progress of both Councils’ Capital Investment Programmes.
3.2The Capital Working Group meets quarterly and monitors the programmes’ progress and finance, seeking to address any problems at an early stage in order for schemes to be completed within budget and timescales. Where problems are highlighted the Group considers possible remedies including virements between schemes, reprofiling of budgets between years and the withdrawal of schemes from the programme when schemes are unable to proceed. This could be due to resourcing problems, time delays or other factors beyond the Councils’ control. 3.3 Full summaries of the progress of all the schemes in the 2019/20 Capital Investment Programmes are prepared each quarter highlighting:
Schemes with significant challenges Red
Schemes where progress is being closely monitored Amber
Schemes progressing well Green
Schemes where progress is beyond officers’ control ◘
Schemes with financial issues £
Schemes where progress has improved ⇧
Schemes where progress has deteriorated ⇩
3.4The Capital Working Group also ensures that capital schemes are approved within financial regulations.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.