1) That the reprofiling of the Adur District Council capital schemes as advised in paragraph 7.1.2 and appendix 2 be noted. 2) That the reprofiling of the Worthing Borough Council capital schemes as advised in paragraph 7.2.1 and appendix 2 be noted. 3) That the application of UKSPF funding and creation of a capital budget for Pier Decking Works in the 2024/25 programme as detailed in 6.3.1 be approved. 4) That the virement of £5k underspend from the Roof Replacement project to the Splashpoint fire dampers replacement project as requested in 5.2.1 be approved Call In: The call-in deadline for decisions will be 5.00pm on 18 March 2025
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1 This report updates the Committee on the progress made on the delivery of the 2024/25 Capital Investment Programme for Adur District Council and Worthing Borough Council. The programme includes schemes which support the delivery of services by the Joint Services Committee.
1.2 The following appendices have been attached to this report:
Appendix 1: Capital Monitoring Summary for Both Councils Appendix 2: Reprofiled Budgets for Adur District Council and Worthing Borough Council
2. RECOMMENDATIONS
2.1The Joint Strategic Committee is asked to:
i) To note the reprofiling of the Adur District Council capital schemes as advised in paragraph 7.1.2 and appendix 2.
i) To note the reprofiling of the Worthing Borough Council capital schemes as advised in paragraph 7.2.1 and appendix 2.
ii) To approve the application of UKSPF funding and creation of a capital budget for Pier Decking Works in the 2024/25 programme as detailed in 6.3.1.
IV) To approve the virement of £5k underspend from the Roof Replacement project to the Splashpoint fire dampers replacement project as requested in 5.2.1
3. CONTEXT
3.1 Previously in accordance with the Council’s Capital Strategy, the Capital Working Group would oversee the implementation and progress of the Council’s capital investment programmes. With the implementation of a new governance structure the Major Programmes Board will now fulfil this role.
3.2 The progress and financial position of the capital programme are monitored to ensure schemes are delivered on time and within budget. Any emerging issues are identified early, allowing for appropriate interventions such as virements between schemes, reprofiling of budgets across financial years, or, where necessary, withdrawing schemes that cannot proceed due to resourcing challenges, delays, or external factors. This oversight will be provided by The Major Programmes Board, while a newly established budget management group for assets will review capital expenditure requests before financial commitments are made.
3.3 Full summaries of the progress of all the schemes in the 2024/25 Capital Investment Programmes are prepared each quarter. Financial Regulations require officers to report each project on completion.
4. Progression of the 2024/25 Capital Programme’s - Quarter 3
4.1 This section of the report looks into the progression of the programme and highlights the current overview of the projects currently underway. Tracking this trajectory helps identify issues with projects and highlight schemes needing further support and monitoring. This information is supplied by project managers monthly, following updates on their expenditure from finance colleagues.
Number of Percentage Adur District Council schemes % Schemes which have completed 5 9.3% Schemes which are progressing satisfactorily 36 66.7% Schemes where progress is being closely monitored 12 22.2% Schemes with significant challenges or financial issues 1 1.9%
Number of Percentage Worthing Borough Council schemes % Schemes which have completed 7 9.6% Schemes which are progressing satisfactorily 62 84.9% Schemes where progress is being closely monitored 3 4.1% Schemes with significant challenges or financial issues 1 1.4%
A summary of the financial movements of the 2024/25 Capital Investment Programme is attached as Appendix 1 to this report.
4.2 Capital Programme Review
The development of the capital programme is guided by the Capital Strategy, which outlines available resources and establishes the framework for approval and delivery. The Joint Capital Strategy 2024-27 was last updated and agreed by the Joint Strategic Committee (JSC) on 11th July 2023.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.