Joint 3rd Quarter Capital Investment Programme & Projects Monitoring 2025/26
NotedCommittee1 paper
AI summaryAdur and Worthing Joint Strategic Committee noted progress on 2025/26 capital schemes and approved virements and reprofiling totalling several million pounds across both councils.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCapital programme progress, virements and budget reprofiling approved for both councils
MoneyNot stated
What happens nextCall-in deadline 5pm on 13 March 2026Decisions can be called in until that date
Who it affectsAdur and Worthing councils' capital programmesMultiple housing, leisure, IT, flood defence and community schemes
What was decided
The committee noted the capital schemes update and approved virements to partnership schemes, Adur District Council schemes and Worthing Borough Council schemes, as detailed in paragraphs 8.1, 8.2 and 8.3. Report P4, P5, P6
The committee noted the reprofiling of Adur District Council and Worthing Borough Council capital budgets to 2026/27, with the full scheme lists in Appendix 2. Report P7, P8, P62, P67
Specific approvals included accepting a £36,019 contribution from South Downs Leisure for Lancing Manor Leisure Centre and adding new funding lines for West Park MUGA, tree replacement and Victoria Park improvements. Report P36, P59, P63, P64, P66
Why
The Capital Working Group monitors capital programme progress and finance, considering remedies including virements, reprofiling and scheme withdrawal where projects cannot proceed as planned. Report P10, P11
Reprofiling moves budgets into 2026/27 where project schedules have changed and schemes will not be completed within the 2025/26 period, ensuring the programme reflects realistic delivery timescales. Report P62, P67
What happens next
A new JSC report on the Worthing Integrated Care Centre is expected in the coming months as complex project issues continue to be addressed before occupation. Report P54
Procurement is underway to select a rescue contractor for the Daniel Close and Gravelly Crescent housing sites after the main contractor entered administration, with a claim to be submitted to the Bondsman. Report P49
The money
£70,000 Virement from Ultrafast Fibre Network Project budget to secure IT back-up system in 2025/26, to be reversed in 2026/27 Report P56
£54k Virement back to contingency from Lancing Manor Leisure Centre boiler budget no longer needed Report P58
£36,019 Contribution from South Downs Leisure to Lancing Manor Leisure Centre project, final cost £534,683, £1.3k under budget Report P36, P59
£73k Virement from Contingency to Community Alarm Digitalisation for new base units ahead of digital switchover Report P60
£10k Virement from Lancing Manor Leisure Centre to cover predicted shortfall on Southwick Community Centre Window Replacement Report P61
£854,105 Adur District Council capital budgets reprofiled to 2026/27 Report P62
£4,486,481 Worthing Borough Council capital budgets reprofiled to 2026/27 Report P67
£20,907 S106 funding added to West Park MUGA project Report P63
£15,000 CIL funding added to West Park MUGA project Report P63
£42,000 Two virements to create new budget line for tree replacement (Ash Dieback and Dutch Elm Disease), comprising £22,000 from Beach Hut Project and £20,000 from Building and Pavilion Improvements Report P64, P65
£17,447 S106 funding added to Victoria Park safety surfaces, equipment and perimeter fencing Report P66
£816,000 Environment Agency gap funding secured for Shoreham Flood Defences / Sussex Yacht Club wall Report P34
£500,000 Original budget for Lancing Manor Leisure Centre Reception refurbishment Report P36
Options considered
Chosen: Note and approve virements to partnership schemes (paragraph 8.1). Required to fund immediate IT back-up system purchase in 2025/26 Report P5, P56
Chosen: Note and approve virements to Adur District Council schemes (paragraph 8.2). Reallocations between schemes to reflect updated project requirements Report P6, P58, P59, P60, P61
Chosen: Note and approve virements to Worthing Borough Council schemes (paragraph 8.3). New funding additions for West Park MUGA, tree replacement and Victoria Park Report P6, P63, P64, P65, P66
Chosen: Note reprofiling of Adur and Worthing capital schemes to 2026/27. Project schedules updated; schemes will complete after 2025/26 Report P7, P8, P62, P67
Implications
Financial: Budgets totalling £854,105 (Adur) and £4,486,481 (Worthing) reprofiled to 2026/27 to reflect updated delivery schedules. Report P62, P67
Financial: Several virements made between schemes, including £70,000 from the Ultrafast Fibre Network to the IT back-up system and £54k returned to contingency from Lancing Manor Leisure Centre. Report P56, P58
Financial: New external funding added: £20,907 S106 and £15,000 CIL for West Park MUGA, £17,447 S106 for Victoria Park, and £816,000 Environment Agency gap funding for Shoreham flood defences. Report P34, P63, P66
Legal: Section 28 Local Government Act 2003 and Section 151 of the Local Government Act 1972 cited as requiring proper financial administration and review of financial position during the year. Report P73, P74
Risk: Main contractor Boutique Modern Limited entered administration on 27 October 2025 affecting Daniel Close and Gravelly Crescent sites; Adur DC issued Notice of Termination in December 2025 and is procuring a rescue contractor. Report P49
Risk: Water ingress and weather damage to balconies identified at Albion Street shortly before Christmas 2025, with further investigations and re-tests required before handover; new estimated completion April 2026. Report P51
Risk: Cyber Security capital expenditure held back due to capacity constraints; investment scheduled for 2026/27 financial year. Report P48
Equalities: Disabled Facilities Grants continue to fund home adaptations such as stairlifts, level-access showers and widened doorways to support independent living, in both Adur and Worthing. Report P33, P41
Climate: Victoria Road housing development of 11 homes built to Passivhaus standard for low energy use; Lancing Manor Leisure Centre upgraded to lower carbon emissions through new low-energy lighting. Report P36, P42, P43
Staffing: Vacancies across the housing projects team and HRA surveying team have limited progress on some projects, with prior year scheme challenges also constraining capacity. Report P16
Who and where
Adur District Council residents and council taxpayers Report P2, P18, P62
Worthing Borough Council residents and council taxpayers Report P2, P19, P67
Households receiving Disabled Facilities Grants in Adur and Worthing Report P33, P41
Local families housed at the completed Victoria Road development in Worthing Report P42, P43
Sussex Yacht Club (negotiations ongoing on Shoreham flood defence scheme) Report P34
Timeline
August 2025: Water system at Worthing Integrated Care Centre handed back to building contractor GT Report P54
September 2025: Vehicular incursion prevention measures completed at Elm Grove, Lancing Report P32
9 October 2025: Albion Street project budget extended at Joint Strategic Committee Report P51
27 October 2025: Boutique Modern Limited (Daniel Close and Gravelly Crescent contractor) entered administration Report P49
December 2025: Joint Strategic Committee approved key recommendations on Shoreham Flood Defences; £816,000 Environment Agency gap funding secured Report P34
December 2025: Adur DC issued Notice of Termination to Boutique Modern Limited for Daniel Close and Gravelly Crescent Report P49
13 March 2026: Call-in deadline for decisions at 5.00pm
2026/27: Cyber Security capital investment scheduled; IT back-up system funding to be reversed back to Ultrafast Fibre Network Report P48, P56
April 2026: New estimated completion date for Albion Street development Report P51
Spring '26: Engagement work on the new WORTHING starts (Montague Gardens) Report P40
Early Summer '26: Targeted delivery of Montague Gardens development Report P40
Before end of December 2026: Targeted completion of Shoreham flood defence wall works Report P34
Plain English for the jargon
Virement: Transfer of budget from one scheme or line to another within the capital programme
Reprofiling: Moving budgeted capital spend from one financial year to a later one to match updated project schedules
S106 funding: Section 106 planning obligation contributions from developers toward local infrastructure
CIL funding: Community Infrastructure Levy receipts collected from developers for local infrastructure
MUGA: Multi-Use Games Area, a surfaced outdoor area for sport and recreation
Passivhaus: A rigorous energy-efficient building standard resulting in very low energy demand for heating and cooling
HRA: Housing Revenue Account, the ring-fenced account for council housing income and expenditure
SDL: South Downs Leisure, the operator contributing to Lancing Manor Leisure Centre works
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemJSC/110/25-26
Resolved
The Joint Strategic Committee note the update on capital schemes and: 2. That the virement to partnership schemes as detailed in 8.1. be noted and approved; 3. That the virements in relation to Adur District Council, detailed in 8.2 be noted and approved; 4. That the virements to Worthing Borough Council Schemes as detailed in 8.3 be noted and approved; 5. That the reprofiling of the Adur District Council capital schemes be noted as advised in paragraph 8.2.5 and appendix 2. 6. That the reprofiling of the Worthing Borough Council capital schemes be noted as advised in paragraph 8.3.4 and appendix 2. Call In: The call-in deadline for decisions will be 5.00pm on 13 March 2026.March 2026.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1. This report updates the Committee on the progress made on the delivery of the 2025/26 Capital Investment Programme for Adur District Council and Worthing Borough Council. The programme includes schemes which support the delivery of services across the councils.
1.2. The following appendices have been attached to this report: Appendix 1: Capital Monitoring Summary for Both Councils Appendix 2: Reprofiled Budgets for Adur District Council and Worthing Borough Council
2. Recommendations 2.1. The Joint Strategic Committee is asked note the update on capital schemes and:
i) To note and approve the virement to partnership schemes as detailed in 8.1.
ii) To note and approve the virements in relation to Adur District Council, detailed in 8.2. iii) To note and approve the virements to Worthing Borough Council Schemes as detailed in 8.3.
iv) To note the reprofiling of the Adur District Council capital schemes as advised in paragraph 8.2.5 and appendix 2.
v) To note the reprofiling of the Worthing Borough Council capital schemes as advised in paragraph 8.3.4 and appendix 2.
3. Context
3.1. In accordance with the Council’s Capital Strategy, the Capital Working Group oversees the implementation and progress of the Council’s capital investment programmes. The Capital Working Group also ensures that capital schemes are approved within financial regulations.
3.2. The Capital Working Group monitors the programme’s progress and finance, seeking to address any problems at an early stage in order for schemes to be completed within budget and timescales. Where problems are highlighted the Group considers possible remedies including virements between schemes, reprofiling of budgets between years and the withdrawal of schemes from the programme when schemes are unable to proceed. This could be due to resourcing problems, time delays or other factors beyond the Council’s control. The Major Programmes Board now has oversight of the capital programme and a new budget management group for assets has been established to review capital expenditure requests before commitment to spend.
3.3. Full summaries of the progress of all the schemes in the 2025/26 Capital Investment Programmes are prepared each quarter.
3.4. Financial Regulations require officers to report each project on completion.
4. Progression of the 2025/26 Capital Programme’s - Quarter 3
4.1. This section of the report looks into the progression of the programme and highlights the current overview of the projects currently underway. By tracking this trajectory we can highlight issues with projects and be aware of schemes which require further support and monitoring. This information is supplied by project managers monthly, following updates on their expenditure from finance colleagues.
4.2. Appendix 1 includes summaries of progress on budget spend. Some expenditure has been delayed due to limitations of internal resourcing, significantly a number of vacancies across the housing projects team and the HRA’s surveying team have limited progress in the latter half of last year and the earlier part of this year. Additionally, challenges with prior year schemes continue to constrict the capacity available to dedicate to new schemes.
4.3. A change in scheme categorisation was introduced at Q1 now more clearly identifies projects with risks related to resourcing, timeliness of commencement, or interdependency. While these schemes were previously monitored, they weren't highlighted in the same way. This new approach has significantly increased the population of the section "Schemes where progress is being closely monitored" for both councils. Though this could be seen as negative, it in fact more accurately reflects the extensive work underlying the delivery of both capital programmes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.