Adur District Council / Worthing Borough Council
Joint Strategic Committee, Tuesday 3 March 2026 at 6.30pm

Joint 3rd Quarter Capital Investment Programme & Projects Monitoring 2025/26

Noted Committee 1 paper

AI summaryAdur and Worthing Joint Strategic Committee noted progress on 2025/26 capital schemes and approved virements and reprofiling totalling several million pounds across both councils.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCapital programme progress, virements and budget reprofiling approved for both councils
MoneyNot stated
What happens nextCall-in deadline 5pm on 13 March 2026Decisions can be called in until that date
Who it affectsAdur and Worthing councils' capital programmesMultiple housing, leisure, IT, flood defence and community schemes

What was decided

The committee noted the capital schemes update and approved virements to partnership schemes, Adur District Council schemes and Worthing Borough Council schemes, as detailed in paragraphs 8.1, 8.2 and 8.3. Report P4, P5, P6

The committee noted the reprofiling of Adur District Council and Worthing Borough Council capital budgets to 2026/27, with the full scheme lists in Appendix 2. Report P7, P8, P62, P67

Specific approvals included accepting a £36,019 contribution from South Downs Leisure for Lancing Manor Leisure Centre and adding new funding lines for West Park MUGA, tree replacement and Victoria Park improvements. Report P36, P59, P63, P64, P66

Why

The Capital Working Group monitors capital programme progress and finance, considering remedies including virements, reprofiling and scheme withdrawal where projects cannot proceed as planned. Report P10, P11

Reprofiling moves budgets into 2026/27 where project schedules have changed and schemes will not be completed within the 2025/26 period, ensuring the programme reflects realistic delivery timescales. Report P62, P67

What happens next

A new JSC report on the Worthing Integrated Care Centre is expected in the coming months as complex project issues continue to be addressed before occupation. Report P54

Procurement is underway to select a rescue contractor for the Daniel Close and Gravelly Crescent housing sites after the main contractor entered administration, with a claim to be submitted to the Bondsman. Report P49

The money

  • £70,000 Virement from Ultrafast Fibre Network Project budget to secure IT back-up system in 2025/26, to be reversed in 2026/27 Report P56
  • £54k Virement back to contingency from Lancing Manor Leisure Centre boiler budget no longer needed Report P58
  • £36,019 Contribution from South Downs Leisure to Lancing Manor Leisure Centre project, final cost £534,683, £1.3k under budget Report P36, P59
  • £73k Virement from Contingency to Community Alarm Digitalisation for new base units ahead of digital switchover Report P60
  • £10k Virement from Lancing Manor Leisure Centre to cover predicted shortfall on Southwick Community Centre Window Replacement Report P61
  • £854,105 Adur District Council capital budgets reprofiled to 2026/27 Report P62
  • £4,486,481 Worthing Borough Council capital budgets reprofiled to 2026/27 Report P67
  • £20,907 S106 funding added to West Park MUGA project Report P63
  • £15,000 CIL funding added to West Park MUGA project Report P63
  • £42,000 Two virements to create new budget line for tree replacement (Ash Dieback and Dutch Elm Disease), comprising £22,000 from Beach Hut Project and £20,000 from Building and Pavilion Improvements Report P64, P65
  • £17,447 S106 funding added to Victoria Park safety surfaces, equipment and perimeter fencing Report P66
  • £816,000 Environment Agency gap funding secured for Shoreham Flood Defences / Sussex Yacht Club wall Report P34
  • £500,000 Original budget for Lancing Manor Leisure Centre Reception refurbishment Report P36

Options considered

  • Chosen: Note and approve virements to partnership schemes (paragraph 8.1). Required to fund immediate IT back-up system purchase in 2025/26 Report P5, P56
  • Chosen: Note and approve virements to Adur District Council schemes (paragraph 8.2). Reallocations between schemes to reflect updated project requirements Report P6, P58, P59, P60, P61
  • Chosen: Note and approve virements to Worthing Borough Council schemes (paragraph 8.3). New funding additions for West Park MUGA, tree replacement and Victoria Park Report P6, P63, P64, P65, P66
  • Chosen: Note reprofiling of Adur and Worthing capital schemes to 2026/27. Project schedules updated; schemes will complete after 2025/26 Report P7, P8, P62, P67

Implications

  • Financial: Budgets totalling £854,105 (Adur) and £4,486,481 (Worthing) reprofiled to 2026/27 to reflect updated delivery schedules. Report P62, P67
  • Financial: Several virements made between schemes, including £70,000 from the Ultrafast Fibre Network to the IT back-up system and £54k returned to contingency from Lancing Manor Leisure Centre. Report P56, P58
  • Financial: New external funding added: £20,907 S106 and £15,000 CIL for West Park MUGA, £17,447 S106 for Victoria Park, and £816,000 Environment Agency gap funding for Shoreham flood defences. Report P34, P63, P66
  • Legal: Section 28 Local Government Act 2003 and Section 151 of the Local Government Act 1972 cited as requiring proper financial administration and review of financial position during the year. Report P73, P74
  • Risk: Main contractor Boutique Modern Limited entered administration on 27 October 2025 affecting Daniel Close and Gravelly Crescent sites; Adur DC issued Notice of Termination in December 2025 and is procuring a rescue contractor. Report P49
  • Risk: Water ingress and weather damage to balconies identified at Albion Street shortly before Christmas 2025, with further investigations and re-tests required before handover; new estimated completion April 2026. Report P51
  • Risk: Cyber Security capital expenditure held back due to capacity constraints; investment scheduled for 2026/27 financial year. Report P48
  • Equalities: Disabled Facilities Grants continue to fund home adaptations such as stairlifts, level-access showers and widened doorways to support independent living, in both Adur and Worthing. Report P33, P41
  • Climate: Victoria Road housing development of 11 homes built to Passivhaus standard for low energy use; Lancing Manor Leisure Centre upgraded to lower carbon emissions through new low-energy lighting. Report P36, P42, P43
  • Staffing: Vacancies across the housing projects team and HRA surveying team have limited progress on some projects, with prior year scheme challenges also constraining capacity. Report P16

Who and where

  • Adur District Council residents and council taxpayers Report P2, P18, P62
  • Worthing Borough Council residents and council taxpayers Report P2, P19, P67
  • Households receiving Disabled Facilities Grants in Adur and Worthing Report P33, P41
  • Local families housed at the completed Victoria Road development in Worthing Report P42, P43
  • Sussex Yacht Club (negotiations ongoing on Shoreham flood defence scheme) Report P34

Timeline

  • August 2025: Water system at Worthing Integrated Care Centre handed back to building contractor GT Report P54
  • September 2025: Vehicular incursion prevention measures completed at Elm Grove, Lancing Report P32
  • 9 October 2025: Albion Street project budget extended at Joint Strategic Committee Report P51
  • 27 October 2025: Boutique Modern Limited (Daniel Close and Gravelly Crescent contractor) entered administration Report P49
  • December 2025: Joint Strategic Committee approved key recommendations on Shoreham Flood Defences; £816,000 Environment Agency gap funding secured Report P34
  • December 2025: Adur DC issued Notice of Termination to Boutique Modern Limited for Daniel Close and Gravelly Crescent Report P49
  • 13 March 2026: Call-in deadline for decisions at 5.00pm
  • 2026/27: Cyber Security capital investment scheduled; IT back-up system funding to be reversed back to Ultrafast Fibre Network Report P48, P56
  • April 2026: New estimated completion date for Albion Street development Report P51
  • Spring '26: Engagement work on the new WORTHING starts (Montague Gardens) Report P40
  • Early Summer '26: Targeted delivery of Montague Gardens development Report P40
  • Before end of December 2026: Targeted completion of Shoreham flood defence wall works Report P34

Plain English for the jargon

  • Virement: Transfer of budget from one scheme or line to another within the capital programme
  • Reprofiling: Moving budgeted capital spend from one financial year to a later one to match updated project schedules
  • S106 funding: Section 106 planning obligation contributions from developers toward local infrastructure
  • CIL funding: Community Infrastructure Levy receipts collected from developers for local infrastructure
  • MUGA: Multi-Use Games Area, a surfaced outdoor area for sport and recreation
  • Passivhaus: A rigorous energy-efficient building standard resulting in very low energy demand for heating and cooling
  • HRA: Housing Revenue Account, the ring-fenced account for council housing income and expenditure
  • SDL: South Downs Leisure, the operator contributing to Lancing Manor Leisure Centre works
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemJSC/110/25-26

Resolved

The Joint Strategic Committee note the update on capital schemes and: 2. That the virement to partnership schemes as detailed in 8.1. be noted and approved; 3. That the virements in relation to Adur District Council, detailed in 8.2 be noted and approved; 4. That the virements to Worthing Borough Council Schemes as detailed in 8.3 be noted and approved; 5. That the reprofiling of the Adur District Council capital schemes be noted as advised in paragraph 8.2.5 and appendix 2. 6. That the reprofiling of the Worthing Borough Council capital schemes be noted as advised in paragraph 8.3.4 and appendix 2. Call In: The call-in deadline for decisions will be 5.00pm on 13 March 2026.March 2026.
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

1.​ Purpose

1.1.​ This report updates the Committee on the progress made on the delivery of the 2025/26 Capital Investment Programme for Adur District Council and Worthing Borough Council. The programme includes schemes which support the delivery of services across the councils.

1.2.​ The following appendices have been attached to this report: Appendix 1: Capital Monitoring Summary for Both Councils Appendix 2: Reprofiled Budgets for Adur District Council and Worthing Borough Council

2.​ Recommendations 2.1.​ The Joint Strategic Committee is asked note the update on capital schemes and:

i) To note and approve the virement to partnership schemes as detailed in 8.1.

ii) To note and approve the virements in relation to Adur District Council, detailed in 8.2. iii) To note and approve the virements to Worthing Borough Council Schemes as detailed in 8.3.

iv) To note the reprofiling of the Adur District Council capital schemes as advised in paragraph 8.2.5 and appendix 2.

v) To note the reprofiling of the Worthing Borough Council capital schemes as advised in paragraph 8.3.4 and appendix 2.

3.​ Context​

3.1.​ In accordance with the Council’s Capital Strategy, the Capital Working Group oversees the implementation and progress of the Council’s capital investment programmes. The Capital Working Group also ensures that capital schemes are approved within financial regulations.

3.2.​ The Capital Working Group monitors the programme’s progress and finance, seeking to address any problems at an early stage in order for schemes to be completed within budget and timescales. Where problems are highlighted the Group considers possible remedies including virements between schemes, reprofiling of budgets between years and the withdrawal of schemes from the programme when schemes are unable to proceed. This could be due to resourcing problems, time delays or other factors beyond the Council’s control. The Major Programmes Board now has oversight of the capital programme and a new budget management group for assets has been established to review capital expenditure requests before commitment to spend.

3.3.​ Full summaries of the progress of all the schemes in the 2025/26 Capital Investment Programmes are prepared each quarter.

3.4.​ Financial Regulations require officers to report each project on completion.

4.​ Progression of the 2025/26 Capital Programme’s - Quarter 3

4.1.​ This section of the report looks into the progression of the programme and highlights the current overview of the projects currently underway. By tracking this trajectory we can highlight issues with projects and be aware of schemes which require further support and monitoring. This information is supplied by project managers monthly, following updates on their expenditure from finance colleagues.

4.2.​ Appendix 1 includes summaries of progress on budget spend. Some expenditure has been delayed due to limitations of internal resourcing, significantly a number of vacancies across the housing projects team and the HRA’s surveying team have limited progress in the latter half of last year and the earlier part of this year. Additionally, challenges with prior year schemes continue to constrict the capacity available to dedicate to new schemes.

4.3.​ A change in scheme categorisation was introduced at Q1 now more clearly identifies projects with risks related to resourcing, timeliness of commencement, or interdependency. While these schemes were previously monitored, they weren't highlighted in the same way. This new approach has significantly increased the population of the section "Schemes where progress is being closely monitored" for both councils. Though this could be seen as negative, it in fact more accurately reflects the extensive work underlying the delivery of both capital programmes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Joint 3rd Quarter Capital Investment Programme & Projects Monitoring 2025/26Agenda 650 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 12 attended
SC
Councillor Sophie CoxChair, present
RG
Councillor Rita GarnerVice-Chair, present
ÖB
Councillor Ödül BozkurtWorthing Member, present
DF
Councillor Dom FordWorthing Member, absent
JT
Councillor John TurleyWorthing Member, present
VW
Councillor Vicki WellsWorthing Member, present
RW
Councillor Rosey WhorlowWorthing Member, present
JG
Councillor Jeremy GardnerAdur Member, present
LC
Councillor Lee CowenAdur Member, present
BA
Councillor Becky AllinsonAdur Member, present
SJ
Councillor Saffa JanAdur Member, present
AH
Councillor Andrew HarveyAdur Member, present

On this subject at Adur & Worthing

Search all
  1. Joint 3rd Quarter Capital Investment Programme & Projects Monitoring 2025/26This decision
  2. Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27Approved
  3. Joint 2nd Quarter Capital Investment Programme & Projects Monitoring 2025/26Noted
  4. Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2025/26Approved
  5. Joint 3rd Quarter Capital Investment Programme & Projects Monitoring 2024/25Noted
  6. Joint 2nd Quarter Capital Investment Programme & Projects Monitoring 2024/25Noted

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies