Adur District Council / Worthing Borough Council
Joint Strategic Committee, Wednesday 12 November 2025 at 6.30pm

Joint 2nd Quarter Capital Investment Programme & Projects Monitoring 2025/26

Noted Committee 1 paper

AI summaryAdur and Worthing Joint Strategic Committee approves virements across the 2025/26 capital programme, including £96k from Ultrafast Fibre to bereavement software and £54k from Adur contingency to Lancing Manor boilers.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedPartnership, Adur and Worthing schemes
MoneyMultiple virements detailed in reportLargest single: £96k bereavement software
What happens nextCall-in deadline 5pm, 24 November 2025Updates due at JSC on 9 December
Who it affectsCapital programme across both councilsPartner, Adur and Worthing schemes

What was decided

The Committee noted and approved virements to partnership schemes as set out in section 8.1, including reallocations from the Ultrafast Fibre Network budget to bereavement software, ICT Immutable Backups and the ICT network refresh. Report P6, P47, P48

The Committee noted and approved Adur District Council virements under section 8.2, including £54k from Adur contingency to replace boilers at Lancing Manor Leisure Centre and retention payments for Adur Homes developments. Report P7, P50, P51

The Committee noted and approved Worthing Borough Council virements under section 8.3, including £17k from Worthing contingency for Buckingham MSCP professional fees, £30k to Hillbarn Changing Rooms, and a £35,000 budget for the Crematorium Flue. Report P8, P53, P55, P56

Why

The Capital Working Group monitors capital schemes and uses virements, reprofiling or withdrawal to keep schemes within budget and timescales, with the Major Programmes Board now providing oversight. Report P10

Officers report that a new scheme categorisation at Q1 has more clearly identified projects with resourcing, timing or interdependency risks, which is reflected in the increased number of schemes now classified as closely monitored. Report P16

Expenditure has been delayed by internal resourcing limits, including housing projects and HRA surveying vacancies, and the carry-over of prior year scheme issues, which has constrained capacity for new schemes. Report P15

What happens next

A standalone project update on the Daniel Close and Gravelly Crescent sites will be presented to a future meeting of the Committee, with officers working to resume work after the contractor entered administration. Report P39, P40

Estimated final cost reports for the Sussex Yacht Club flood defences and an update on the Worthing Integrated Care Centre are expected at the JSC on 9 December. Report P43, P44

Finance Regulations require officers to report each project on completion, and the next quarterly capital monitoring report will follow. Report P12, P11

The money

  • £96k virement from Ultrafast Fibre Network budget to new bereavement software Report P27, P48
  • £80k virement from Ultrafast Fibre Network to ICT Immutable Backups Report P48
  • £50k virement from Ultrafast Fibre Network to top up ICT network refresh budget Report P48
  • £54k virement from Adur contingency to Lancing Manor Leisure Centre boiler replacement Report P50
  • £962 retention invoice for Ground Source Heat Pumps at Tollbridge House Report P51
  • £5,822 retention invoice for Ground Source Heat Pumps at Shadwell Court Report P51
  • £17k virement from Worthing contingency for Buckingham MSCP professional fees Report P53
  • £4,629 brought-forward 2024/25 Town Centre Improvements balance reallocated to UKSPF TLC revamp Report P54
  • £30k virement from parks and assets capital budget to Hillbarn Changing Rooms Report P55
  • £35,000 virement from Crematorium Walled Garden budget to fund crematorium flue replacement Report P56
  • £5k overspend on Commerce Way Male Showers refurbishment, part-funded by £2k from roof scheme underspend and £1.5k from each council's contingency Report P25, P26

Options considered

  • Chosen: Note and approve partnership scheme virements (section 8.1). Recommended by Interim Director for Core Services to reallocate underspend on the Joint Gigabit project Report P6, P47, P48
  • Chosen: Note and approve Adur District Council virements (section 8.2). Recommended to fund boiler replacement and Adur Homes retention payments within existing resources Report P7, P50, P51
  • Chosen: Note and approve Worthing Borough Council virements (section 8.3). Recommended to fund Buckingham MSCP, Hillbarn Changing Rooms, Crematorium Flue and the TLC revamp project Report P8, P53, P54, P55, P56

Implications

  • Financial: No unbudgeted financial implications: all virements are funded from existing resources or external funding within the 2025/26 capital programme approved in February 2025. Report P61
  • Legal: Section 28 Local Government Act 2003 and Section 151 of the Local Government Act 1972 require the councils to review their financial position during the year and maintain proper administration of financial affairs. Report P63, P64
  • Risk: Main contractor Boutique Modern Limited for Daniel Close and Gravelly Crescent has entered administration, delaying works while the Council protects its position under the performance bond. Report P39, P40
  • Risk: Flood Defences at Sussex Yacht Club face a material likelihood that the tender cost will exceed planned funding, though additional Environment Agency funding is being pursued. Report P43
  • Financial: An overspend is anticipated on the Worthing Integrated Care Centre, which is being reported separately to JSC. Report P44
  • Staffing: Vacancies in the housing projects team and HRA surveying team have limited progress on capital schemes in the latter half of last year and the earlier part of this year. Report P15
  • Equalities: The capital programme prioritisation model awards points for proposals that address Equalities Act requirements and reduce inequalities, including disabled adaptations via the Disabled Facilities Grant. Report 2.2, P30, P35
  • Climate: Schemes such as Connaught Theatre window replacement and the Lancing Manor roof and cladding works are designed to improve energy efficiency and reduce heat loss. Report P31, P33

Who and where

  • Adur District Council and Worthing Borough Council residents and service users, including park and leisure centre users Report P29, P31, P33, P34, P36
  • Households receiving Disabled Facilities Grants in both council areas Report P30, P35
  • Adur Homes tenants and applicants on the housing register, including those awaiting new properties at the Albion Street development Report P41
  • Contractors and suppliers working on the 2025/26 capital programme, including Pilbeam Construction Services Limited and Edburton Report P33, P34
  • Sussex Yacht Club and users of public rights of way at the site, following planning approval for a new flood wall Report P42
  • Officers in the housing projects and HRA surveying teams, with vacancies limiting progress Report P15

Timeline

  • April 2025: Shadwells Road playground in Adur opened following redesign funded by S106 from the Cala Homes New Monks Farm development. Report P29
  • August 2025: Commerce Way Roof scheme completed and £35,000 crematorium flue capital budget created by virement. Report P25, P56
  • September 2025: Commerce Way Male Showers refurbishment completed. Report P26
  • End of October 2025: Crematorium flue replacement scheduled to complete. Report P37
  • 9 October 2025: Albion Street development budget extension considered at the Joint Strategic Committee. Report P41
  • As at 27 October 2025: Main contractor Boutique Modern Limited for Daniel Close and Gravelly Crescent entered administration. Report P39
  • November 2025: Homefield Park playground works under way, with an estimated 14-week completion period. Report P36
  • 5.00pm on 24 November 2025: Call-in deadline for the decisions.
  • 9 December 2025: Estimated final reports on Sussex Yacht Club flood defences and Worthing Integrated Care Centre due at JSC. Report P43, P44
  • January 2026: Practical completion of the Albion Street development scheduled. Report P41
  • Early Summer '26: Montague Gardens development scheduled for delivery. Report P34

Plain English for the jargon

  • Virement: A reallocation of budget from one scheme or heading to another within the approved capital programme.
  • Capital Investment Programme: The councils' multi-year plan for spending on fixed assets such as land, buildings and equipment.
  • HRA: Housing Revenue Account, the ring-fenced account that funds council housing in England.
  • S106: Section 106 planning obligation payments from developers, used to fund local infrastructure or facilities.
  • UKSPF: UK Shared Prosperity Fund, central government funding supporting local growth and community projects.
  • MSCP: Multi-storey car park.
  • MHCLG: Ministry of Housing, Communities and Local Government.
  • TMSS: Treasury Management Strategy Statement, setting out how the council manages cash investments and borrowings.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemJSC/65/24-25

Resolved

That the the virement to partnership schemes as detailed in 8.1. be noted and approved; 2. That the virements in relation to Adur District Council, detailed in 8.2. be noted and approved; 3. That the virements to Worthing Borough Council Schemes as detailed in 8.3. Be noted and approved Call In: The call-in deadline for decisions will be 5.00pm on 24 November 2025.
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

1.​ Purpose

1.1.​ This report updates the Committee on the progress made on the delivery of the 2025/26 Capital Investment Programme for Adur District Council and Worthing Borough Council. The programme includes schemes which support the delivery of services across the councils.

1.2.​ The following appendices have been attached to this report: Appendix 1: Capital Monitoring Summary for Both Councils

2.​ Recommendations

2.1.​ The Joint Strategic Committee is asked note the update on capital schemes and:

i) To note and approve the virement to partnership schemes as detailed in 8.1.

ii) To note and approve the virements in relation to Adur District Council, detailed in 8.2.

iii) To note and approve the virements to Worthing Borough Council Schemes as detailed in 8.3. 3.​ Context

3.1.​ In accordance with the Council’s Capital Strategy, the Capital Working Group oversees the implementation and progress of the Council’s capital investment programmes. The Capital Working Group also ensures that capital schemes are approved within financial regulations.

3.2.​ The Capital Working Group monitors the programme’s progress and finance, seeking to address any problems at an early stage in order for schemes to be completed within budget and timescales. Where problems are highlighted the Group considers possible remedies including virements between schemes, reprofiling of budgets between years and the withdrawal of schemes from the programme when schemes are unable to proceed. This could be due to resourcing problems, time delays or other factors beyond the Council’s control. The Major Programmes Board now has oversight of the capital programme and a new budget management group for assets has been established to review capital expenditure requests before commitment to spend.

3.3.​ Full summaries of the progress of all the schemes in the 2025/26 Capital Investment Programmes are prepared each quarter.

3.4.​ Financial Regulations require officers to report each project on completion.

4.​ Progression of the 2025/26 Capital Programme’s - Quarter 2

4.1.​ This section of the report looks into the progression of the programme and highlights the current overview of the projects currently underway. By tracking this trajectory we can highlight issues with projects and be aware of schemes which require further support and monitoring. This information is supplied by project managers monthly, following updates on their expenditure from finance colleagues.

4.2.​ Appendix 1 includes summaries of progress on budget spend. Some expenditure has been delayed due to limitations of internal resourcing, significantly a number of vacancies across the housing projects team and the HRA’s surveying team have limited progress in the latter half of last year and the earlier part of this year. Additionally, challenges with prior year schemes continue to constrict the capacity available to dedicate to new schemes.

4.3.​ A change in scheme categorisation was introduced at Q1 now more clearly identifies projects with risks related to resourcing, timeliness of commencement, or interdependency. While these schemes were previously monitored, they weren't highlighted in the same way. This new approach has significantly increased the population of the section "Schemes where progress is being closely monitored" for both councils. Though this could be seen as negative, it in fact more accurately reflects the extensive work underlying the delivery of both capital programmes. ​ Number of Percentage Adur District Council schemes % Schemes which have completed 4 5.63% Schemes which are progressing satisfactorily 42 59.15% Schemes where progress is being closely monitored 22 30.99% Schemes with significant challenges or financial issues 3 4.23%

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Joint 2nd Quarter Capital Investment Programme & Projects Monitoring 2025/26Report 442 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 13 attended
SC
Councillor Sophie CoxChair, present
RG
Councillor Rita GarnerVice-Chair, present
ÖB
Councillor Ödül BozkurtWorthing Member, present
DF
Councillor Dom FordWorthing Member, absent
JT
Councillor John TurleyWorthing Member, present
VW
Councillor Vicki WellsWorthing Member, present
RW
Councillor Rosey WhorlowWorthing Member, present
JG
Councillor Jeremy GardnerAdur Member, present
LC
Councillor Lee CowenAdur Member, present
BA
Councillor Becky AllinsonAdur Member, present
SJ
Councillor Saffa JanAdur Member, present
AH
Councillor Andrew HarveyAdur Member, present

All 13 on the meeting page

On this subject at Adur & Worthing

Search all
  1. Joint 2nd Quarter Capital Investment Programme & Projects Monitoring 2025/26This decision
  2. Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27Approved
  3. Joint 3rd Quarter Capital Investment Programme & Projects Monitoring 2025/26Noted
  4. Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2025/26Approved
  5. Joint 3rd Quarter Capital Investment Programme & Projects Monitoring 2024/25Noted
  6. Joint 2nd Quarter Capital Investment Programme & Projects Monitoring 2024/25Noted

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies