Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2025/26

Approved Committee 1 paper

Joint Strategic Committee approved this item on Thursday 11 September 2025. Below is the council's own wording, with the papers it was decided on.

ItemJSC/37/25-26

Resolved

That the correction of the carry forward Adur Homes budget to 2025/26 as detailed in 7.1.1. be approved 2. That the reprofile of capital budget for Shadwells play area as detailed in 7.1.2 be approved 3. That the reprofile of capital budget for the Shoreham Centre air source heat pump as detailed in 7.1.3 be approved 4. That the first quarter treasury management update set out in appendix 3 be noted. Call In: The call-in deadline for decisions will be 5.00pm on 23 September 2025
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

1.​ PURPOSE 1.1​ This report updates the Committee on the progress made on the delivery of the 2025/26 Capital Investment Programme for Adur District Council and Worthing Borough Council. The programme includes schemes which support the delivery of services across the councils.

1.2Included within the report is information about the prudential indicators which provide a link between the Councils’ revenue budget and capital budget. Quarterly monitoring of these indicators is a requirement of the prudential code.

1.2​ The following appendices have been attached to this report: ​ Appendix 1: Capital Monitoring Summary for Both Councils Appendix 2: Joint 1st Quarter Treasury Management Update 2025/26

​ ​ ​ ​ 2.​ RECOMMENDATIONS

2.1The Joint Strategic Committee is asked to: i) To approve the correction of the carry forward Adur Homes budget to 2025/26 as detailed in 7.1.1.

ii) To approve the reprofile of capital budget for Shadwells play area as detailed in 7.1.2

iii) To approve the reprofile of capital budget for the Shoreham Centre air source heat pump as detailed in 7.1.3

iv) To note the first quarter treasury management update set out in appendix 3.

3.​ CONTEXT

3.1​ In accordance with the Council’s Capital Strategy, the Capital Working Group oversees the implementation and progress of the Council’s capital investment programmes. The Capital Working Group also ensures that capital schemes are approved within financial regulations.

3.2​ The Capital Working Group monitors the programme’s progress and finance, seeking to address any problems at an early stage in order for schemes to be completed within budget and timescales. Where problems are highlighted the Group considers possible remedies including virements between schemes, reprofiling of budgets between years and the withdrawal of schemes from the programme when schemes are unable to proceed. This could be due to resourcing problems, time delays or other factors beyond the Council’s control. The Major Programmes Board now has oversight of the capital programme and a new budget management group for assets has been established to review capital expenditure requests before commitment to spend.

3.3​ Full summaries of the progress of all the schemes in the 2025/26 Capital Investment Programmes are prepared each quarter.

3.4​ Financial Regulations require officers to report each project on completion.

4. ​ Progression of the 2025/26 Capital Programme’s - Quarter 1

4.1​ This section of the report looks into the progression of the programme and highlights the current overview of the projects currently underway. By tracking this trajectory we can highlight issues with projects and be aware of schemes which require further support and monitoring. This information is supplied by project managers monthly, following updates on their expenditure from finance colleagues.

4.2​ A change in scheme categorisation now more clearly identifies projects with risks related to resourcing, timeliness of commencement, or interdependency. While these schemes were previously monitored, they weren't highlighted in the same way. This new approach has significantly increased the population of ​ ​ ​ ​ the section "Schemes where progress is being closely monitored" for both councils. Though this could be seen as negative, it in fact more accurately reflects the extensive work underlying the delivery of both capital programmes.

Number of Percentage Adur District Council schemes % Schemes which have completed 1 1.4% Schemes which are progressing satisfactorily 49 69% Schemes where progress is being closely monitored 20 28.2% Schemes with significant challenges or financial issues 1 1.4%

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2025/26Report 547 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 13 attended
SC
Councillor Sophie CoxChair, present
RG
Councillor Rita GarnerVice-Chair, present
ÖB
Councillor Ödül BozkurtWorthing Member, present
DF
Councillor Dom FordWorthing Member, present
JT
Councillor John TurleyWorthing Member, present
VW
Councillor Vicki WellsWorthing Member, present
RW
Councillor Rosey WhorlowWorthing Member, present
JG
Councillor Jeremy GardnerAdur Member, present
LC
Councillor Lee CowenAdur Member, present
BA
Councillor Becky AllinsonAdur Member, present
SJ
Councillor Saffa JanAdur Member, present
AH
Councillor Andrew HarveyAdur Member, present

All 13 on the meeting page

On this subject at Adur & Worthing

Search all
  1. Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2025/26This decision
  2. Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27Approved
  3. Joint 3rd Quarter Capital Investment Programme & Projects Monitoring 2025/26Noted
  4. Joint 2nd Quarter Capital Investment Programme & Projects Monitoring 2025/26Noted
  5. Joint 3rd Quarter Capital Investment Programme & Projects Monitoring 2024/25Noted
  6. Joint 2nd Quarter Capital Investment Programme & Projects Monitoring 2024/25Noted

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies