Decision The Joint Strategic Committee:- (a) With respect to the Capital Investment Programme of Adur District Council i) noted the reprofiling of the Adur District Council capital schemes as advised in paragraphs 7.2.1 and Appendix 3; ii) approved the funding of the overspend incurred in the replacement of the HR / Payroll system as detailed in paragraph 7.1.1; iii) approved the increase in the Disabled Facilities Budget in line with the forecast expenditure funded from Better Care Fund Grant as detailed in paragraph 7.2.2; and iv) approved the transfer of Disability Discrimination Adaptations Budget to fund Adur District Council’s contribution to the Adur and Worthing Workspaces Project as detailed in paragraph 7.2.3. b) With respect to the Capital Investment Programme of Worthing Borough Council i) noted the reprofiling of the Worthing Borough Council capital schemes as advised in paragraphs 7.3.1 and Appendix 4; ii) approved the funding of the overspend incurred in the replacement of the HR / Payroll system as detailed in paragraph 7.1.1; iii) approved the addition of the Worthing Public Realm Project to the 2021/22 Capital Investment Programme as detailed in paragraph 7.3.3; iv) approved the transfer of Disability Discrimination Adaptations Budget to the Adur and Worthing Workspaces Project as detailed in paragraph 7.3.4; and v) noted the receipt of the Pocket Parks Grant funding of £24,030 to support communities to provide new or renovated parks and approve the ... view the full minutes text for item JSC/95/21-22
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1. PURPOSE 1.1 This report updates the Joint Strategic Committee on the progress made on the 2021/22 Capital Investment Programmes for Adur District Council, Worthing Borough Council. The programmes include schemes which support the delivery of services by the Joint Services Committee.
1.2The following appendices have been attached to this report: Appendix 1: Adur District Council Capital Monitoring Summary Appendix 2: Worthing Borough Council Capital Monitoring Summary Appendix 3: Adur District Council Reprofiled Budgets Appendix 4: Worthing Borough Council Reprofiled Budgets
2. RECOMMENDATIONS 2.1 The Joint Strategic Committee is asked: (a) With respect to the Capital Investment Programme of Adur District Council. i) To note the reprofiling of the Adur District Council capital schemes as advised in paragraphs 7.2.1 and Appendix 3.
ii) To approve the funding of the overspend incurred in the replacement of the HR / Payroll system as detailed in paragraph 7.1.1. iii) To approve the increase in the Disabled Facilities Budget in line with the forecast expenditure funded from Better Care Fund Grant as detailed in paragraph 7.2.2.
iv) To approve the transfer of Disability Discrimination Adaptations Budget to fund Adur District Council’s contribution to the Adur and Worthing Workspaces Project as detailed in paragraph 7.2.3.
b) With respect to the Capital Investment Programme of Worthing Borough Council.
i) To note the reprofiling of the Worthing Borough Council capital schemes as advised in paragraphs 7.3.1 and Appendix 4.
ii) To approve the funding of the overspend incurred in the replacement of the HR / Payroll system as detailed in paragraph 7.1.1.
iii) To approve the addition of the Worthing Public Realm Project to the 2021/22 Capital Investment Programme as detailed in paragraph 7.3.3.
iv) To approve the transfer of Disability Discrimination Adaptations Budget to the Adur and Worthing Workspaces Project as detailed in paragraph 7.3.4.
v) To note the receipt of the Pocket Parks Grant funding of £24,030 to support communities to provide new or renovated parks and approve the use of the funding to create a community garden in Beach House Park as detailed in paragraph 7.3.5.
3. CONTEXT
3.1In accordance with the Councils’ Capital Strategy, the Capital Working Group oversees the implementation and progress of both Councils’ Capital Investment Programmes.
3.2The Capital Working Group meets quarterly and monitors the programmes’ progress and finance, seeking to address any problems at an early stage in order for schemes to be completed within budget and timescales. Where problems are highlighted the Group considers possible remedies including virements between schemes, reprofiling of budgets between years and the withdrawal of schemes from the programme when schemes are unable to proceed. This could be due to resourcing problems, time delays or other factors beyond the Councils’ control.
3.3Full summaries of the progress of all the schemes in the 2021/22 Capital Investment Programmes are prepared each quarter highlighting: Schemes with significant challenges Red
Schemes where progress is being closely monitored Amber
Schemes progressing well Green
Schemes where progress is beyond officers’ control ◘
Schemes with financial issues £
Schemes where progress has improved ⇧
Schemes where progress has deteriorated ⇩
3.4The Capital Working Group also ensures that capital schemes are approved within financial regulations.
3.5Financial Regulations require officers to report each project on completion.
4. SUCCESSES AND CHALLENGES IN THE 2021/22 CAPITAL INVESTMENT PROGRAMMES
4.1The following schemes are progressing well:
4.1.1 Adur Homes Capital Investment Programme
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.