Review of the Corporate Risks and Opportunities

Agreed Committee 2 papers

AI summaryJoint Strategic Committee to receive another corporate risk report in September 2026, with 18 risks currently tracked across housing, regeneration, reorganisation and the environment.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedCommittee agreed to receive a further update
Money£4.9m Worthing budget gapAdur balanced; Worthing seeking Exceptional Funding Support
What happens nextSeptember 2026Next corporate risk progress report to the Committee
Who it affectsAdur and Worthing CouncilsBoth councils jointly tracking 18 risks

What was decided

The Joint Strategic Committee agreed that a further progress report on the Corporate Risk Register be received in September 2026.

The call-in deadline for the decision was set at 5.00pm on 13 March 2026.

Why

The Committee reviewed a Corporate Risk Register of 18 risks (C1 to C18) aligned to Fair, Green and Local missions, with each risk showing its owner, likelihood, impact, score and current mitigations. Report P1, P3, P4, P6, P7, P9, P11, P13, P14, P16, P17, P19, P20, P21, P22, P24, P25, P27

Several risks were flagged as moving in a particular direction: housing compliance (C1), business support (C3), Building Control (C6), emergency response (C20), data protection (C13), Equality Act duties (C14) and climate (C16) improved; the Worthing Integrated Care Centre development (C4), land charges migration (C7), and corporate income and debt (C9) worsened. Report P3, P6, P7, P11, P13, P16, P20, P21, P22, P25

What happens next

A further progress report on the Corporate Risk Register is to come back to the Joint Strategic Committee in September 2026.

Food waste collections are anticipated to start being rolled out in September 2026, subject to vehicle delivery, with a separate report to come to JSC in February 2026. Report P25

The next phase of Worthing Heat Network construction is due to commence in March 2026, using less disruptive directional drilling. Report P25

The money

  • £4.9m Worthing budget gap for 2026/27 to be closed by Exceptional Funding Support Scheme Report P17
  • £4.75m Increased EFS principal submitted for 2025/26 to manage Worthing overspend Report P17
  • up to £500m Private investment figure cited as the potential scale of growth for the Worthing Heat Network Report P25
  • £1.2m Total grant funding secured for the Sussex Bay marine project to sustain the programme to 2028/2029 Report P25
  • £1m project Hydrogen trial at Worthing crematorium, the first of its kind in the UK, completed May/June 2024 Report P25

Implications

  • Financial: Both councils' finances remain under severe pressure. Adur's 2026/27 budget is balanced; Worthing has requested Exceptional Funding Support to close a £4.9m gap and submitted an increased EFS principal of £4.75m for 2025/26. Report P17
  • Risk: The Strategic Property Investment Fund (SPIF) is rated High risk: Reading Beta Building has been disposed of, and Eskan Court in Milton Keynes is expected to become fully vacant in January 2027 when the remaining tenant's lease expires. Report P9
  • Risk: The Worthing Integrated Care Centre development (C4) is rated High and has worsened. Two key NHS tenants entered lease agreements from July 2025, but water system defects, a re-commissioning process and liquidated damages claims against developer WSWL remain live issues. Report P7
  • Risk: Land charges migration to HM Land Registry (C7) is a new High risk: 3,000 of 40,000 records had been transferred as of the report, against a deadline of December 2025, putting the transition grant at risk. Report P13
  • Legal: Equality Act and Public Sector Equality Duty compliance (C14) is rated Medium but improved; the Inclusion Lead role is not funded after March 2026 and ongoing delivery is being reviewed. Report P22
  • Staffing: Risks around leaders and managers (C11) and emergency response capability (C12) remain live; Strategic Duty Officer training is being rolled out and a L&D Delivery Plan is due to launch by April 2026. Report P19, P20
  • Climate: Climate emergency risk (C16) remains High but improved: the first phase of Worthing Heat Network construction is complete, the corporate fleet has transitioned to HVO, and Sussex Bay has secured further grant funding. Report P25
  • Risk: Local Government Reorganisation (C8) and a related new risk on neighbourhood governance creating a democratic deficit (C15) are being managed through the West Sussex Leaders Group, a cross party Neighbourhood Governance Working Group, and a small transformation budget secured in 2026/27 subject to final approval. Report P14, P24

Who and where

  • Adur District Council and Worthing Borough Council, as joint owners of the register Report P1
  • Households at risk of homelessness, given high demand and limited affordable supply Report P4
  • Council tenants in Adur Homes, given the housing compliance improvement plan Report P3
  • Local businesses that depend on council-coordinated business support Report P6
  • Council staff facing Local Government Reorganisation and management capacity pressures Report P14, P19
  • Residents in the Worthing and Adur area affected by the climate, environment and waste collection risks Report P25

Timeline

  • March 2026: Next phase of Worthing Heat Network construction due to commence Report P25
  • Q1 2026: Emergency Assistance Centre training to be delivered Report P20
  • Q2 2026: Rest Centre training delivery expected Report P20
  • 13 March 2026: Call-in deadline for the decision at 5.00pm
  • September 2026: Next Corporate Risk Register progress report to be received by the Committee
  • September 2026: Food waste collections anticipated to begin rolling out, subject to vehicle delivery Report P25
  • January 2027: Remaining tenant at Eskan Court, Milton Keynes, likely to leave, leaving the building fully vacant Report P9

Plain English for the jargon

  • EFS: Exceptional Funding Support Scheme, a form of government financial support for councils in difficulty
  • LGR: Local Government Reorganisation, the move towards larger unitary councils in place of the existing district and county structure
  • HRRB: High Risk Residential Building, in this context defined as buildings over 18m in height or with seven or more storeys and two or more residential units
  • RBCA: Registered Building Control Approver, the new class of approver introduced by the Building Safety Act
  • SPIF: Strategic Property Investment Fund, the councils' property portfolio held to generate income
  • WICC: Worthing Integrated Care Centre, the major NHS-related development at risk C4
  • CLT: Corporate Leadership Team, the senior officer group running the two councils jointly
  • PSED: Public Sector Equality Duty, the equality duty placed on public bodies by the Equality Act 2010
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemJSC/112/25-26

Resolved

That it be agreed that a further progress report be received in September 2026 Call In: The call-in deadline for decisions will be 5.00pm on 13 March 2026.
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

NEW Fair/Green/Local Missions aligned Risk and Opportunities Registers Corporate Risk register

Change in Date added to Corporate Risks and Opportunities Mission Type Authority Owner Lead Officer Likelihood L Score Impact I Score Score Rating overall Risk Last reviewed Latest update report Mitigations in place risk register status

C1 Risk that Adur Council will fail to comply with statutory Housing & Prevention Adur CLT Rob Jarvis Moderate 3 Moderate 3 9 Medium Improved 09/02/2026 01/11/2022 February 2026 February 2026 - health and safety obligations as a social landlord (Adur The Council is awaiting the outcomes from the recent - Improvement plan review being Homes) Audit. There was an improvement to the risk in undertaken to incorporate the original September 2025 with it reducing from High to areas of focus, audit recommendations Medium because we have significantly improved our and subsequent discoveries. awareness of the compliance gaps, eradicated a -Recommendations for an updated number of them, fire risk assessments and high risk improvement plan have been presented actions (having none outstanding) being a prime to the Adur Homes Improvement Board example but there is progress across all of the big for consideration. six. Our governance process is also significantly - Officers continue to meet with the improved with monthly compliance meetings and Regulator of Social Housing monthly to challenges/blockers raised and escalated to the monitor progress. improvement board where necessary. The primary - CLT monthly reporting continues focus has continued to be compliance and H&S and alngside periodic updates provided to the data is now showing good progress in all areas Joint Audit and Governance Committee with a firm grip on the data supporting the reported and the Joint Strategic Committee. figures.

C2 Risk that due to the limited supply of affordable Housing & Prevention Joint CLT Tina Favier Very likely 5 Major 4 20 High No change 16/02/2026 01/05/2022 February 2026 February 2026 accommodation to meet the demand for households in Following a joint review of the pressures facing the Work to secure TA is focused on as part housing need there is an increase demand from housing advice service with representatives of the of the Housing and Prevention Mission households at risk of homelessness and our ability to Ministry Housing Communites and Local Board to ensure greater assurance. meet our statutory duties. There is an increased use of Governement (MHCLG), a transformation plan has As part of the Homelessness Strategy temporary accommodation and demand for homeless been created to ensure we can continue to meet the work will ensure that TA supply is services which is placing extreme pressure on the needs of households facing homelessness. Of the managed in line with need and future Council's financial position actions within the transformation plan, additional projected need. resource have been identified, a review of a number New Affordable Homes Group has been of processes and procedures put in place in addition established to drive the data and to an audit of Temporary Accommodation use and activities around the concils as an placements. An updated data tracker has been enabler of affordable housing, working created and informs monthly oversight updates to the with registered providers and developers. Housing and Prevention mission board. In Adur - prioritised focused on the delivery of key sites that have been Additional temporary accommodation is being started. developed to improve the options for households facing homelessness in addition to a continued drive to complete permanent affordable development sites in Adur District. We continue to explore and implement long term leased accommodation, where appropriate to bring households facing homelessness as close to their support networks as possible. NEW Fair/Green/Local Missions aligned Risk and Opportunities Registers Corporate Risk register

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
NEW Fair_Green_Local Missions aligned Risk and Opportunities Registers: Corporate Risk register (9) /112/25-26Report 118 KB DownloadRead as text
PDF
Review of the Corporate Risks and OpportunitiesAgenda 187 KB Download

At this meeting

Whole meeting

Who was there

11 of 12 attended
SC
Councillor Sophie CoxChair, present
RG
Councillor Rita GarnerVice-Chair, present
ÖB
Councillor Ödül BozkurtWorthing Member, present
DF
Councillor Dom FordWorthing Member, absent
JT
Councillor John TurleyWorthing Member, present
VW
Councillor Vicki WellsWorthing Member, present
RW
Councillor Rosey WhorlowWorthing Member, present
JG
Councillor Jeremy GardnerAdur Member, present
LC
Councillor Lee CowenAdur Member, present
BA
Councillor Becky AllinsonAdur Member, present
SJ
Councillor Saffa JanAdur Member, present
AH
Councillor Andrew HarveyAdur Member, present

On this subject at Adur & Worthing

Search all
  1. Review of the Corporate Risks and OpportunitiesThis decision
  2. Review of the Corporate Risks and OpportunitiesAgreed
  3. Review of Corporate Risks and OpportunitiesAgreed
  4. Annual Review of Corporate Complaints and Customer Feedback ReportNoted
  5. Review of Joint Overview and Scrutiny Committee Work Programme for 2024/25 including review of the Corporate Risks and OpportunitiesDecided
  6. Annual Review of Corporate Complaints and Customer Feedback Report 23/24Noted

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open