Joint Strategic Committee, Tuesday 3 March 2026 at 6.30pm

Heat Network Investment Program (HNIP) Grant Application

Agreed Committee 1 paper

AI summaryWorthing councillors agree to seek £8.02 million government grant for the next phase of the Worthing Heat Network, to be passed to operator Hemiko subject to subsidy law checks.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedDelegated to Service Director for Operations and Environmental Services
Money£8.02 million grantAdditional HNIP funding for heat network construction
What happens nextApply and draw down by 31 March 2026Funds held in ring-fenced reserve pending legal checks
Who it affectsNot stated

What was decided

Authority delegated to the Service Director for Operations and Environmental Services to enter a grant funding agreement with Triple Point for £8.02 million of HNIP funding, to be on-granted to Hemiko for Densification Phase 1 of the Worthing Heat Network. Report P8

Authority delegated to on-grant the full amount to Hemiko under the existing On-Grant Agreement, subject to further legal advice on Subsidy Control Act 2022 compliance and on amendments to existing transactional documents. Report P9, P10

The on-grant is also subject to written consultation with the Chief Financial Officer and the Cabinet Members for Resources and for Regeneration, who must be satisfied that any additional implications are reasonable, proportionate and within the existing project scope. Report P10

Why

Construction costs have risen significantly above inflation, partly because the next phase will use Horizontal Directional Drilling rather than open trenching to reduce disruption in the town centre. Report P4, P29, P30

Delays to national Heat Network Zoning policy are slowing uptake of new connections, so grant funding is needed to maintain momentum and prepare for future expansion. Report P5, P21

A second air source heat pump is to be installed at the energy centre to provide enough low-carbon capacity for new customers, particularly developers of new build housing and commercial schemes. Report P19, P39

What happens next

The Service Director will enter the grant funding agreement with Triple Point, administer the draw down of the £8.02 million by 31 March 2026 and hold it in a ring-fenced reserve. Report P53, P58

Independent legal advice will be obtained on Subsidy Control Act 2022 compliance and on amendments needed to existing transactional documents before funds are passed to Hemiko. Report P10, P52, P59

Written consultation will take place with the Chief Financial Officer, the Cabinet Member for Resources and the Cabinet Member for Regeneration on the legal advice received. Report P10

The money

  • £8.02 million Additional HNIP grant funding to be received and on-granted to Hemiko Report P8
  • £8,023,000 Total value of the HNIP change request Report P26, P48
  • £4,498,644 Cost element for Horizontal Directional Drilling Report P26
  • £4,333,449 Cost element for increased low carbon capacity at the energy centre Report P26
  • £950,000 Previous HNIP commercialisation grant utilised by Worthing Borough Council Report P14
  • £5.058 million Previous HNIP construction grant on-granted to Hemiko Report P15
  • £1.275 million Previous HNIP loan on-loaned to Hemiko at 0.01% interest Report P16, P49
  • £15,561,000 Total HNIP allocation for Worthing Heat Network after the change request Report P50, P56

Options considered

  • Chosen: Apply for additional £8.02 million of HNIP grant funding and on-grant to Hemiko subject to legal and governance conditions. Needed to cover higher HDD construction costs, install a second air source heat pump and keep connection charges competitive while national policy delays slow uptake Report P7, P21, P38

Implications

  • Financial: Grant must be drawn down by 31 March 2026 or the £8.02 million allocation is lost. Funds are restricted to capital expenditure on the heat network and cannot be diverted to other council initiatives. Report P27, P58
  • Legal: Independent legal advice is required to confirm the on-grant does not create an unlawful subsidy under the Subsidy Control Act 2022, and to scope amendments to existing transactional documents. Report P10, P51, P59, P65
  • Risk: If subsidy control checks indicate an unmitigable risk, the council cannot pass the funds to Hemiko. Council costs of legal and governance work are expected to be met by Hemiko as ultimate beneficiary. Report P59, P60
  • Climate: The funding supports low-carbon heat network expansion and a second air source heat pump, contributing to Worthing's carbon reduction aims. Report P19, P39, P77

Who and where

  • Worthing Borough Council, as recipient and pass-through of the grant Report P8, P17
  • Hemiko, as concessionaire and ultimate recipient of the on-grant Report P3, P9, P57
  • Triple Point, administering HNIP on behalf of DESNZ Report P17, P54
  • Five potential heat network customers in progressed discussions, including four public sector off-takers across eight sites and one private sector off-taker Report P43
  • Town centre businesses and residents affected by construction works Report P29, P30
  • Existing connected buildings: Worthing Town Hall, Assembly Hall, Connaught Theatre, Worthing Museum, Portland House and Worthing Hospital Report P18

Timeline

  • Summer 2024: Construction of the Worthing Heat Network started Report P18
  • October 2025: First buildings connected to the network; Hemiko secured planning permission for Densification Phase 1 Report P18, P19
  • 5.00pm on 13 March 2026: Call-in deadline for the decision
  • 31 March 2026: Deadline for the council to draw down the additional £8.02 million HNIP funding Report P45, P53, P58
  • Early 2027: Indicative start of works to install the second air source heat pump at the energy centre Report P39, P40

Plain English for the jargon

  • HNIP: Heat Network Investment Programme, a government grant programme
  • DESNZ: Department for Energy Security and Net Zero, which now administers HNIP in place of BEIS
  • Triple Point: Administrator of HNIP funding on behalf of DESNZ
  • Hemiko: Concessionaire responsible for designing, building, operating and maintaining the Worthing Heat Network
  • HDD: Horizontal Directional Drilling, a less disruptive underground pipe installation method
  • ASHP: Air Source Heat Pump, low-carbon heating technology
  • ESCo: Energy Supply Company, the Hemiko vehicle supplying heat to customers
  • Densification Phase 1: Next phase of the heat network connecting the Pavillion Theatre and Splashpoint Leisure Centre to the Energy Centre
  • Subsidy Control Act 2022: UK law governing the giving of subsidies by public authorities to commercial undertakings
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemJSC/117/25-26

Resolved

That authority be delegated to the Service Director for Operations & Environmental Services to enter into a grant funding agreement with Triple Point for receipt into Worthing Borough Council’s budget the amount of £8.02 million grant funding for the purposes of on-granting to Hemiko for use as capital investment in the next agreed phase of construction of the Worthing Heat Network (Densification Phase 1). 2. That authority be delegated to the Service Director for Operations & Environmental Services to on-grant the full amount of grant funding to Hemiko pursuant to an existing On-Grant Agreement for the purpose of delivering out the next agreed phase of construction work but such delegation being subject to further legal advice and consultation as follows:- 3. That the proposed on-grant by Worthing Borough Council does not create an unlawful subsidy in accordance with the Subsidy Control Act 2022; 4. An advice on the scope of the amendments required to existing transactional documents to facilitate and implement the on-grant and associated construction work; 5. Written consultation with the Chief Financial Officer, the Cabinet Members for Resources, and the Cabinet Member for Regeneration on the legal advice obtained and their being satisfied that any additional implications for Worthing Borough Council are reasonable and proportionate and within the scope of the existing project. Call In: The call-in deadline for decisions will be 5.00pm on 13 March 2026.
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

1.​ Purpose

1.1.​ The Worthing Heat Network (WHN) project has benefited from government Heat Network Infrastructure Project (HNIP) funding during procurement, design and construction of Phase 1.

1.2.​ Hemiko, who are responsible for the design, build, operation, and maintenance of the network have been granted planning permission for the next phase of construction ‘Densification Phase 1’.

1.3.​ To minimise disruption associated with the next phase of work a new construction methodology is being adopted Horizontal Directional Drilling (HDD). HDD avoids the need for open trench construction but is more expensive than traditional open trench construction. Other project costs have also increased significantly beyond inflation.

1.4.​ In addition to cost increases, the delay to Heat Network Zoning is reducing the uptake of new connections to the heat network.

1.5.​ In response to these challenges this report seeks approval to apply for further HNIP funding to contribute to the capital costs of extending the heat network using HDD technology and bringing forward the installation of a second air source heat pump at the energy centre in readiness for future connections. 2.​ Recommendations

2.1.​ The Joint Strategic Committee is asked to:

2.1.1.​ Authorise the Service Director for Operations & Environmental Services to enter into a grant funding agreement with Triple Point for receipt into Worthing Borough Council’s budget the amount of £8.02 million grant funding for the purposes of on-granting to Hemiko for use as capital investment in the next agreed phase of construction of the Worthing Heat Network (Densification Phase 1).

2.1.2.​ To delegate authority to the Service Director for Operations & Environmental Services to on-grant the full amount of grant funding to Hemiko pursuant to an existing On-Grant Agreement for the purpose of delivering out the next agreed phase of construction work but such delegation being subject to further legal advice and consultation as follows:-

●​ That the proposed on-grant by Worthing Borough Council does not create an unlawful subsidy in accordance with the Subsidy Control Act 2022; ●​ An advice on the scope of the amendments required to existing transactional documents to facilitate and implement the on-grant and associated construction work; ●​ Written consultation with the Chief Financial Officer, the Cabinet Members for Resources, and the Cabinet Member for Regeneration on the legal advice obtained and their being satisfied that any additional implications for Worthing Borough Council are reasonable and proportionate and within the scope of the existing project.

3.​ Context

3.1.​ In October 2021 a report was presented to this committee providing an update on the Worthing Heat Network. The report confirmed that Worthing Borough Council had been successful in its application for grant funding from the Heat Network Investment Programme (HNIP). Additional grants were awarded during the project and the total allocation is summarised in the table below.The grant was awarded for the following amounts: Table 3.1 Previous HNIP Grant Funding

Amount Type Stage Notes

£950,000 Grant Commercialisation Utilised by Worthing Borough Council to bring WHN to market

£5.058 million Grant Construction On-granted to concessionaire partner (Hemiko)

£1.275 million Loan Construction On-loaned to concessionaire partner. The loan had a 0.01% interest rate attached to it.

3.2.​ The funding was awarded by BEIS (The Department for Business, Energy and Industrial Strategy), now replaced by DESNEZ (Department for Energy Security and Net Zero) and is administered by Triple Point on behalf of the Government.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Heat Network Investment Program (HNIP) Grant ApplicationAgenda 273 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 12 attended
SC
Councillor Sophie CoxChair, present
RG
Councillor Rita GarnerVice-Chair, present
ÖB
Councillor Ödül BozkurtWorthing Member, present
DF
Councillor Dom FordWorthing Member, absent
JT
Councillor John TurleyWorthing Member, present
VW
Councillor Vicki WellsWorthing Member, present
RW
Councillor Rosey WhorlowWorthing Member, present
JG
Councillor Jeremy GardnerAdur Member, present
LC
Councillor Lee CowenAdur Member, present
BA
Councillor Becky AllinsonAdur Member, present
SJ
Councillor Saffa JanAdur Member, present
AH
Councillor Andrew HarveyAdur Member, present

On this subject at Adur & Worthing

Search all
  1. Heat Network Investment Program (HNIP) Grant ApplicationThis decision
  2. Worthing Heat Network Densification Phase Property RightsAgreed
  3. Worthing Heat Network: Project Update and Entering into Heat Connection and Supply Agreements for Splashpoint Leisure Centre and Pavillion TheatreNoted
  4. Worthing Heat Network : Letting of contract to design, build, fund, operate and maintain a low carbon heat network for Worthing Town Centre and agreement to enter into heat supply and connection agreements for WBC estateNoted
  5. Carbon Neutral 2030: Worthing Heat Network Progress UpdateNoted
  6. Carbon Neutral 2030: Worthing Heat Network: progress updateNoted

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies