Worthing Heat Network Densification Phase Property Rights
AgreedCommittee1 paper
AI summaryWorthing and Adur Joint Strategic Committee delegates authority to officers to sign property, connection and supply agreements for the Worthing Heat Network's Densification Phase 1, covering Splashpoint Leisure Centre and Pavilion Theatre.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedOfficers can sign heat network contracts
Money£5.5k legal costs to dateFurther legal fees expected, figures not given
What happens nextCall-in by 13 March 2026Decision can be challenged until deadline
Who it affectsTwo council venues, public landSplashpoint Leisure, Pavilion Theatre, seafront users
What was decided
Authority delegated to the Service Director, Place & Economy, in consultation with the Cabinet Member for Regeneration and the Cabinet Member for Resources, to enter into and complete the legal agreements needed to add Densification Phase 1 of land and buildings to the heat network. Report P4, P5
Authority delegated to enter into Connection Agreements and Heat Supply Agreements for Splashpoint Leisure Centre and Pavilion Theatre, setting out connection rights, obligations and the ongoing heat supply transaction. Report P6, P7, P34, P35
Authority delegated to enter into either a Main Pipeline Lease of 99 years or a Connection Pipeline Lease of 20 years, following connection of the buildings to the network. Report P8, P23, P36
Why
Planning permission for Densification Phase 1 was granted on 15 October 2025, and the scheme was considered by the Joint Overview and Scrutiny Committee on 27 January 2026. The council now needs formal property rights and contractual arrangements to allow the work to proceed. Report P11, P2, P33
The agreements will sit alongside the Corporate Concession Agreement entered into on 28 March 2024 between the council and Worthing Energy Supply Company Limited (the ESCo) and will formalise the addition of new sites to the network. Report P10, P31
Officers recommend the same agreement structure used for the pioneer phase, which connected the Energy Centre at the High Street Multi-Storey Car Park and five council buildings including the Town Hall and Portland House. Report P24, P25
What happens next
The call-in deadline is 5.00pm on 13 March 2026, after which officers will negotiate and complete the legal agreements subject to the delegated authority. Report P5, P28
Where access is needed to a council-owned building occupied by an existing tenant, the council will seek third party consents and agree access protocols under the Corporate Concession Agreement. Report P28
Disposal notices for public open space land have already been advertised in the Worthing Herald and on the council website for two consecutive weeks under Section 123(2a) of the Local Government Act 1972. Report P27, P39
The money
£5.5k Estimated legal advice costs to date for property rights and variation to technical agreements, met from existing heat network project budgets Report P41
Options considered
Chosen: Main Pipeline Lease of 99 years for land forming part of the main pipeline route. Used for the main pipeline route that does not connect a council building, matching the pioneer phase structure Report P23, P24, P36
Chosen: Connection Pipeline Lease of 20 years for land linking council buildings to the main pipeline. Used for areas connecting council buildings to the main route, matching the pioneer phase structure Report P23, P24, P36
Chosen: Bespoke Deed of Easement for the Pavilion Theatre. Grants access rights only, in favour of land owned by Worthing Borough Council, rather than a lease to the ESCo Report P26, P20
Implications
Legal: Section 123(2a) of the Local Government Act 1972 has been complied with through public advertising of public open space disposals; Section 111 of the 1972 Act, Section 3(1) of the Local Government Act 1999 and Section 1 of the Local Government (Contracts) Act 1997 support the council's powers to enter the agreements. Report P27, P44, P45, P46
Financial: Further legal costs are anticipated to formalise the variation to the Corporate Concession Agreement for Densification Phase 1, with the exact amount contingent on legal advice conclusions. Report P42
Climate: The works will provide low carbon heating infrastructure for Worthing, with Horizontal Directional Drilling chosen over open trench construction to reduce disruption and environmental impact. Report P56, P62
Equalities: Accessibility requirements during construction are considered as part of traffic management plans; no equality, community safety or human rights issues have been identified. Report 2.2, P60, P61
Worthing Energy Supply Company Limited (the ESCo) Report P10
Users of public open space along Steyne Gardens and Marine Parade Report P16, P22
Hemiko, which operates the social value and community engagement programme for the heat network Report 2.1
Timeline
28 March 2024: Corporate Concession Agreement for the Worthing Heat Network entered into between the council and the ESCo Report P10
15 October 2025: Planning permission granted for Densification Phase 1 connecting Splashpoint Leisure Centre and Pavilion Theatre Report P11
27 January 2026: Joint Overview and Scrutiny Committee considered the next phase of the heat network Report P11, P38
3 March 2026: Joint Strategic Committee decision to delegate authority for property rights and agreements
5.00pm on 13 March 2026: Call-in deadline for the decision
Plain English for the jargon
ESCo: Energy Supply Company; here, Worthing Energy Supply Company Limited, the operator of the heat network
Densification Phase 1: The next phase of the heat network connecting Splashpoint Leisure Centre and Pavilion Theatre to the Energy Centre
Heat network: A system of pipes that distributes heat from a central energy source to multiple buildings
Offtaker: A customer that buys or takes heat supplied from the network
Main Pipeline Lease: A 99 year lease of subsoil land for the main heat pipeline route, not connecting a specific council building
Connection Pipeline Lease: A 20 year lease of subsoil land linking a council building to the main pipeline
Deed of Easement: A legal agreement granting access rights over land without granting a lease, used here for the Pavilion Theatre
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemJSC/116/25-26
Resolved
That authority be delegated to the Service Director, Place & Economy, in consultation with the Cabinet Member for Regeneration and the Cabinet member for Resources to: 2. Enter into and complete all necessary legal agreements to formally add the next phase (Densification Phase 1) of land and buildings to Worthing’s heat network. 3. Enter into and complete Connection Agreements for Splashpoint Leisure and Pavilion Theatre which set out the rights and obligations of both parties when making a connection to the heat network. 4. Enter into and complete Heat Supply Agreements for Splashpoint Leisure and Pavilion Theatre which act as the ongoing transactional document between the offtaker and the heat network. 5. Following their connection to the heat network, agree to enter into and complete either a Main Pipeline Lease of 99 years or a Connection Pipeline Lease of 20 years Call In: The call-in deadline for decisions will be 5.00pm on 13 March 2026.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1. The Worthing Heat Network ESCo (Energy Supply Company) has been granted planning permission for the next phase of work to connect Splashpoint Leisure Centre and Pavillion Theatre to the Energy Centre (Densification Phase 1). In order for the works to proceed the council needs to issue property rights over council owned land and enter into agreements that govern the connection to the heat network and the contractual arrangements around the supply of heat via the network.
1.2. The purpose of this report is to set out the proposed property rights and agreements between the council and the ESCo to allow the works to commence and seek committee approval to delegate authority to the Service Director, Place & Economy, in consultation with the Cabinet Member for Regeneration and the Cabinet member for Resources, to enter into the relevant agreements. 2. Recommendations
2.1. The Committee is asked to delegate authority to the Service Director, Place & Economy, in consultation with the Cabinet Member for Regeneration and the Cabinet member for Resources to:
2.1.1. Enter into and complete all necessary legal agreements to formally add the next phase (Densification Phase 1) of land and buildings to Worthing’s heat network.
2.1.2. Enter into and complete Connection Agreements for Splashpoint Leisure and Pavilion Theatre which set out the rights and obligations of both parties when making a connection to the heat network.
2.1.3. Enter into and complete Heat Supply Agreements for Splashpoint Leisure and Pavilion Theatre which act as the ongoing transactional document between the offtaker and the heat network.
2.1.4. Following their connection to the heat network, agree to enter into and complete either a Main Pipeline Lease of 99 years or a Connection Pipeline Lease of 20 years
3. Context
3.1. The Council entered into the Corporate Concession Agreement for the Worthing Heat Network on 28 March 2024. This is an overarching agreement that sets out the arrangements between the Council and Worthing Energy Supply Company Limited (the ESCo), for the development and operation of the heat network. It includes, amongst other things, the arrangements for connection and supply to land and buildings that are to be added to the heat network. These are referred to as ‘future network projects’.
3.2. The next phase of work, referred to as Densification Phase 1, will connect Splashpoint Leisure Centre and Pavilion Theatre to the heat network. This phase of work was subject to planning permission which was granted on 15 October 2025. It has also been subject to extensive community engagement and has been considered by the Council’s Joint Overview and Scrutiny Committee on 27 January 2026. The proposed pipeline route is shown on the attached plan which may change slightly as a result of the design and delivery process.
3.3. The purpose of this report is to set out the recommended property rights to be granted to enable this phase of the heat network to be constructed and the associated heat connection and supply agreements.
3.4. The report seeks delegated authority from the committee for officers to enter into the technical agreements in consultation with the relevant members.
3.5. Pipeline Leases & Easements
3.5.1. The areas of land that are subject to the property rights are as follows:
(a) Steyne Gardens, 18 Marine Parade, Worthing, BN11 3PT (HM Land Registry Title WSX293906) (b) Marine Parade and area south of Splashpoint Leisure Centre, Worthing, BN11 2EJ (HM Land Registry Title WSX293905) (c) Marine Parade, Worthing, BN11 3PS (HM Land Registry Title WSX322462)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.