AI summaryJoint Strategic Committee approved a £3,790,500 capital budget for the Southwick FC community sports hub, with £500,000 from pooled business rates and a £150,000 virement from Buckingham Park.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSix-part decision with delegations to officer
Money£3,790,500 total capital budgetPlus £500,000 Growth Deal and £150,000 virement
What happens nextConstruction starts July 2026Facility operational Autumn 2027
Who it affectsSouthwick FC, Russell Martin FoundationLocal community and football partners
What was decided
Approved £500,000 of Pooled Business Rates from the Adur Growth Deal and allocated the full amount to the scheme, increasing the total budget by the same amount. Report P7
Approved a £150,000 capital virement from the Buckingham Park Pavilion allocation to provide a 10% project contingency, noting the Buckingham Park project is to be delivered through an Expression of Interest process seeking private investment. Report P8
Approved the overall £3,790,500 capital budget and delegated authority to the Service Director for Place & Economy, in consultation with the Cabinet Member for Regeneration and Economy, to sign grant funding agreements, award contracts and execute the agreement for lease and subsequent lease with the Russell Martin Foundation. Report P9, P10, P11, P12
Why
To deliver the Southwick FC upgrade of 3G pitch, infrastructure and a new clubhouse, in partnership with the Russell Martin Foundation since 2021, with Football Foundation and Premier League Stadium funding secured in September 2024. Report P2, P13
A 10% contingency is needed because the site is heavily restricted by size, subterranean utilities, media mast easements and the need for environmental mitigation for slow worms and a possible bat roost. Report P15, P21, P23, P75
The previous external design team was replaced in November 2025 after omitting key infrastructure and design principles, which delayed the scheme and increased costs, with a new team producing revised plans under the Football Foundation Grade 6 framework. Report P15, P18, P56
What happens next
Submit a Section 73 planning application and seek planning committee approval in May 2026. Report P20, P30
Tender the clubhouse construction in May/June 2026 and the pitch and facilities works in June/July 2026, with the Football Foundation leading the pitch procurement. Report P31, P32
Start construction in July 2026 and aim to have the new facility complete and operational in Autumn 2027 for the 2027/28 football season. Report P34, P35
The money
£3,790,500 Total revised project capital budget Report P9, P48, P55
£500,000 Pooled Business Rates via Adur Growth Deal with WSCC Report P7, P45
£150,000 Capital virement from Buckingham Park Pavilion allocation, providing 10% project contingency Report P8, P47
£2,000,000 Football Foundation Capital Grant Report P38
£100,000 Premier League Stadium Fund Report P39
£300,000 Russell Martin Foundation Donation Report P40
£500,000 Adur District Council Capital Programme 24/25 Report P44
£300,000 10% project contingency within total budget Report P54
Implications
Financial: Total capital budget is set at £3,790,500, including a 10% contingency, with full funding from the Football Foundation, Premier League Stadium Fund, Russell Martin Foundation, Sussex Police, Adur District Council capital programme and pooled business rates. Report P48, P55, P73, P75
Legal: The decision relies on section 111 of the Local Government Act 1972, section 3 of the Local Government Act 1999, section 1 of the Local Government (Contracts) Act 1997 and the Officer Scheme of Delegations, with grant spend required to avoid breach of funding terms or unlawful state aid. Report P79, P80, P81, P82, P83
Risk: Risks include subterranean utility surprises, environmental mitigation, planning changes under S73, procurement outcomes, and the long-term viability of the Russell Martin Foundation as tenant, mitigated through an FRI lease and the ability to seek a new provider. Report P23, P57, P68, P70, P77
Equalities: The project is assessed under the Equality Act 2010 general duty and is designed to provide inclusive, multi-generational community amenities, with Secured by Design principles to support community safety. Report P61, P96, P103
Climate: The design includes a Sustainable Urban Drainage System, new green landscaping and an environmental mitigation action plan for slow worms and a possible bat roost, with further surveys in April 2026. Report P21, P64, P107
Who and where
Southwick Football Club and its supporters, who will use the new pitch and clubhouse Report P13, P88
Russell Martin Foundation, as the prospective tenant and operating charity Report P13, P70, P92
Local community in Southwick, including underrepresented and multi-generational groups Report P88, P91, P99
Football Foundation and Premier League Stadium Fund as majority funders Report P24, P38, P39
Sussex Police as a small grant funder and community safety partner Report P43, P102
West Sussex County Council as partner in the Adur Growth Deal Report P3, P45
Timeline
19 February 2026: Partners site visit Report P27
5.00pm on 13 March 2026: Call-in deadline for the decision
May 2026: Section 73 planning permission and agreement for lease and funding agreements Report P30
May/June 2026: Construction tendering for the clubhouse Report P31
June/July 2026: Construction tendering for pitch and facilities led by the Football Foundation, plus pre-construction and contracting phase Report P32, P33
July 2026: Construction commencement Report P34
Autumn 2027: New facility expected to be complete and operational for the 2027/28 football season Report P35
Plain English for the jargon
3G pitch: Third generation artificial football pitch surface
FRI Lease: Full Repairing and Insuring lease, under which the tenant handles repairs, maintenance and insurance
SUDS: Sustainable Urban Drainage System, used on site to manage surface water runoff
S73 application: Application under section 73 of the Town and Country Planning Act to vary conditions or make minor material amendments to an existing planning permission
Pooled Business Rates: Business rates income pooled through the Adur Growth Deal with West Sussex County Council
Expression of Interest: Process being used to invite private investment proposals for the Buckingham Park Pavilion project
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemJSC/120/25-26
Resolved
That the use of Pooled Business Rates be approved as set out in the Adur Growth Deal at £500,000, and formally allocate the full amount to this scheme, increasing the total budget by the same amount. 2. That a capital virement of £150,000 from the Buckingham Park Pavilion capital allocation in the capital programme be approved, to provide a 10% project contingency for this scheme, noting that the Buckingham Park project is to be delivered through an Expression of Interest process seeking private investment. 3. That the overall capital budget for the project of £3,790,500 be approved, to be funded as set out in section 4.8. 4. That authority be delegated to the Service Director for Place & Economy, in consultation with the Cabinet Member for Regeneration and Economy, to agree and sign all relevant grant funding agreements, including with the Football Foundation and Premier League Stadium Fund. 5. That authority be delegated to the Service Director for Place & Economy, in consultation with the Cabinet Member for Regeneration and Economy, to award and complete contracts for all associated services necessary for the delivery of the scheme within agreed procurement frameworks and within the budget envelope identified, with all funding confirmed ahead of commencement. 6. That authority be delegated to the Service Director for Place & Economy, in consultation with the Cabinet Member for Regeneration and Economy, to enter into and execute the agreement for lease and subsequent lease with the Russell Martin Foundation, subject to the Russell Martin Foundation having complied with the condition precedents specified in the agreement for lease. Call In: The call-in deadline for decisions will be 5.00pm on 13 March 2026.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1. The purpose of this report is to provide Members with a further update on the Southwick FC scheme to upgrade the pitch (3G), infrastructure and build a new Clubhouse.
1.2. To formally allocate an additional £500,000 to the capital scheme budget from Pooled Business Rates, via WSCC/ADC Growth Deal, in support of necessary onsite infrastructure as per the Joint Strategic Committee decision on 9th December 2025.
1.3. To approve the allocation and virement of £150,000 in capital funding from the Buckingham Park Pavilion project capital allocation, which is now being delivered through an Expression of Interest process seeking private capital investment. This will ensure a 10% project contingency is in place ahead of the scheme taking place.
1.4. To note changes in the project delivery approach and the updated scheme budget of £3,790,500, and the revised programme. 2. Recommendations
2.1. The Joint Strategic Committee is recommended to:
1.) Approve the use of Pooled Business Rates as set out in the Adur Growth Deal at £500,000, and formally allocate the full amount to this scheme, increasing the total budget by the same amount.
2.) Approve a capital virement of £150,000 from the Buckingham Park Pavilion capital allocation in the capital programme to provide a 10% project contingency for this scheme, noting that the Buckingham Park project is to be delivered through an Expression of Interest process seeking private investment.
3.) To approve the overall capital budget for the project of £3,790,500 to be funded as set out in section 4.8.
4.) Delegate authority to the Service Director for Place & Economy, in consultation with the Cabinet Member for Regeneration and Economy, agree and sign all relevant grant funding agreements, including with the Football Foundation and Premier League Stadium Fund.
5.) Delegate authority to the Service Director for Place & Economy, in consultation with the Cabinet Member for Regeneration and Economy, to award and complete contracts for all associated services necessary for the delivery of the scheme within agreed procurement frameworks and within the budget envelope identified, with all funding confirmed ahead of commencement.
6.) Delegate authority to the Service Director for Place & Economy, in consultation with the Cabinet Member for Regeneration and Economy, to enter into and execute the agreement for lease and subsequent lease with the Russell Martin Foundation, subject to the Russell Martin Foundation having complied with the condition precedents specified in the agreement for lease. 3. Context
3.1. Adur council has been working in partnership with the Russell Martin Foundation (RMF) in the development of the Southwick FC grounds since 2021. The project attracted Football Foundation and Premier League Stadium funding in September 2024. Initial plans for the new clubhouse, 3G pitch and upgraded sporting and leisure facilities received planning approval in August 2023.
3.2. In March 2025 the council instructed Red Loft Consultancy as Project Delivery Managers and shortly afterwards MGAC (Brighton) as cost consultants and project administrators.
3.3. The Southwick FC site is in a poor state of repair and is heavily restricted in terms of size, subterranean utilities, necessary access requirements from existing tenancy agreements (media masts) and other existing easements. It was felt that these restrictions had not been sufficiently considered by the original external design team and they were replaced in November 2025.
3.4. A cost analysis for areas not included within the original scope of the clubhouse and/or pitch and facilities procurement was undertaken, including the necessary replacement of the boundary treatments.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.