AI summaryWorthing and Adur Joint Strategic Committee delegates authority to run a competitive tender for a managing agent at the Worthing Integrated Care Centre, where the £48,945,000 project remains delayed by ongoing water system issues including legionella detection.
Written from the decision and the officer reportPDF Pro
OutcomeNotedNotes water system update; delegates procurement to Service Director
Money£48,945,000 project budgetRevised in June 2026 after £2,420,310 capital increase
What happens nextMini-competition tender via Pagabo DPSIndicative 3-month procurement; water system handback by end of 2026
Who it affectsWICC tenants including NHS TrustsWeekly update meetings with stakeholders continue
What was decided
Members noted the report and the update on water system rectification progress, including indicative timelines. Report P6
Authority was delegated to the Service Director for Place and Economy to run a tender for a Property Management Company to act as Managing Agent and provide Facility Management Services. Report P7, P8, P33
Authority was delegated to appoint any necessary legal or consultancy services to complete WICC delivery and seek redress, within the authorised budget. Report P7, P9, P28
Why
The contractor Galliford Try has repeatedly missed water system handback deadlines; the council's own testing on 28 May 2026 found traces of legionella, disrupting the planned June 2026 handback. Report P11, P14, P15, P16, P17
The previously approved FM framework did not allow a property manager appointment, and further legal advice led officers to recommend a competitive Dynamic Purchasing System route instead of the June 2026 direct award to Bellrock. Report P21, P30, P31, P32
The Pagabo Dynamic Purchasing System provides a compliant Public Contract Regulations 2015 route with pre-approved suppliers, giving a transparent process to appoint both managing agent and facility manager. Report P33, P34, P35
What happens next
Preliminary market engagement in September 2026 to attract suppliers to the DPS, followed by a cost and quality evaluation over an indicative 3-month procurement window. Report P35, P38
Await the Contractor's remediation plan and testing framework, with the water system indicatively expected to be handed back by the end of calendar year 2026, subject to scope and delivery. Report P27
A fully detailed project review will be presented to the Joint Overview and Scrutiny Committee once the project is complete. Report P42
The money
£2,420,310 Capital budget increase approved by JSC in June 2026 due to delays, capitalised interest and rising fees Report P18
£48,945,000 Total revised project budget after the June 2026 increase Report P18
0.5 - 1% Framework fee that would have applied under the original GCS route Report P37
2-5% Typical fee range for other framework or DPS routes Report P37
2-3% Anticipated final framework fee under the Pagabo DPS Report P37
26 years Original projected break-even period for the facility Report P20
35 years Revised projected break-even period after delays and lost income Report P20
Options considered
Rejected: Direct award to Bellrock as Managing Agent (June 2026 proposal). Changes to legal framework requirements and further legal advice mean a compliant competitive process is now required Report P21, P30, P31
Chosen: Mini-competition via the Pagabo Dynamic Purchasing System (Public Contract Regulations 2015). Provides a transparent, compliant route allowing appointment of both managing agent and facility manager Report P31, P33, P34
Rejected: Government Commercial Agency (formerly CCS) framework. No longer a suitable framework or DPS route available via GCA Report P37
Implications
Financial: Persistent delays and inability to fully occupy the building have created shortfalls in rental income and service charge recovery and increased financing costs, with 2026/27 revenue shortfalls to be managed through the Property Risk Reserve. Report P19, P20
Legal: The Council continues to consider all legal remedies available for recovery of losses incurred, as part of an ongoing process. Report P28
Risk: The projected break-even point has extended from 26 to 35 years of full operation due to ongoing delays and lost income. Report P20
Staffing: Officers will need to appoint an external agency to develop the specification and extend existing legal support, all within the authorised budget from the June 2026 JSC. Report P36
Other: Close communications will be maintained with NHS tenants to ensure all necessary compliance assurances for their occupation of the WICC are met. Report P28, P40
Who and where
NHS Trusts and other NHS tenants of the WICC Report P16, P28, P40
West Sussex Worthing Limited (WSWL), the Developer Report P13, P24, P41
Galliford Try, the design and build Contractor Report P3, P13, P23
Adur District Council and Worthing Borough Council Report P80
Worthing residents and town centre users Report P55, P57, P64
Timeline
December 2024: Practical completion of the WICC was issued independently by the Employer's Agent Report P11
August 2025: Contractor accepted responsibility to take back the water system to rectify and recommission it Report P13
28th May 2026: Council's independent water testing found traces of legionella in specific locations Report P15
June 2026: JSC approved a £2,420,310 capital budget increase, raising total budget to £48,945,000; contractor's legionella sampling returned negative results Report P17, P18
July 2026: WSWL completed its own independent specialist survey of the water system Report P24
September 2026: Preliminary market engagement on the Pagabo DPS planned Report P35
8 September 2026: Joint Strategic Committee meeting considered this report
18 September 2026: Call-in deadline for this decision at 5.00pm
End of calendar year 2026: Indicative timeline for water system handback to the Council, subject to scope and delivery Report P27
Later in 2026: Next WICC update to be presented to the JSC Committee Report P38
Plain English for the jargon
WICC: Worthing Integrated Care Centre, a health facility bringing together NHS services including GP, dentistry, mental health and pharmacy
WSWL: West Sussex Worthing Limited, the developer of the WICC project
DPS: Dynamic Purchasing System, a procurement route under the Public Contract Regulations 2015 using pre-approved suppliers
Legionella: Bacteria that can cause Legionnaires' disease, found in building water systems
BREEAM: Building Research Establishment Environmental Assessment Method, a sustainability standard for buildings
EPC: Energy Performance Certificate, showing the energy efficiency of a building
GCS: Government Commercial Agency, formerly Crown Commercial Service (CCS)
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemJSC/43/26-27
Resolved
That the contents of the attached report be noted and the update on the water system rectification progress, including indicative timelines; 2. That authority be delegated to the Service Director for Place & Economy to: a. Complete a tender exercise to appoint a Property Management Company to act as Managing Agent for the WICC and who will also provide the Facility Management Services. This delegation includes finalising all procurement and contracts to effect the appointment, subject to this being through a compliant process and within budget. b. To appoint any necessary legal or consultancy services required to complete the delivery of the WICC and seek redress providing the appointments are within the authorised budget. Call In: The call-in deadline for decisions will be 5.00pm on 18 September 2026.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1. The works that continue to progress to rectify the water system undertaken by the design and build Construction Contractor Galliford Try (the Contractor) and by West Sussex Worthing Ltd (the Developer) in the Worthing Integrated Care Centre (WICC)
1.2. The report sets out the proposed step to undertake a mini-tender competition via a compliant Dynamic Purchasing System (Public Contract Regulations 2015) for the appointment of the Property Management Services for the WICC. 2. Recommendations
2.1. The Joint Strategic Committee is recommended to:
2.1.1. Note the contents of this report and the update on the water system rectification progress, including indicative timelines.
2.1.2. To delegate authority to the Service Director for Place & Economy to:
1. Complete a tender exercise to appoint a Property Management Company to act as Managing Agent for the WICC and who will also provide the Facility Management Services. This delegation includes finalising all procurement and contracts to effect the appointment, subject to this being through a compliant process and within budget.
2. To appoint any necessary legal or consultancy services required to complete the delivery of the WICC and seek redress providing the appointments are within the authorised budget.
3. Background
3.1. Practical completion of the WICC was issued independently by the Employers Agent in December 2024. Immediate concerns resulted in the identification of Legionella and other systematic issues such as inconsistent temperature controls and the requirement for the replacement of water pumps and immersion heaters by the Contractor.
3.2. Continuous concerns with the defective water system led to the Council undertaking its own independent expert investigation of the associated issues. Escalation of these concerns by the Council to the Developer were not adequately addressed by the Contractor.
3.3. This led to further evidence being presented to the Contractor through the Developer, West Sussex Worthing Limited (WSWL). Eventual acceptance by the Contractor to take back the water system to rectify, and recommission it was agreed and the Contractor took back its responsibility in August 2025.
3.4. The remediation works attempted by the Contractor have so far failed to fully rectify the water system, with several deadlines for handback of the water system to the council being missed and further delayed.
3.5. The Contractor had been anticipating a revised handback timeline of early June 2026. However this didn’t materialise as the Council conducted independent water testing on 28th May 2026 which proved traces of legionella in specific locations in the building.
3.6. This unexpected development disrupted the planned June 2026 handback. The Council awaiting updated programme and final commissioning, subsequently notified the Developer, the Contractor, and stakeholders (including the NHS Trusts) while awaiting the Contractor's response program and further testing.
3.7. Subsequently, legionella sampling undertaken by the contractor in June 2026 did result in negative results being recorded. Although, it was evident at that time that wider systematic water system issues still needed to be addressed.
3.8. Due to the ongoing delays, capitalised interest on borrowing, and rising legal and specialist consultancy fees, the JSC Committee in June 2026 approved a capital budget increase of £2,420,310. This raised the total revised project budget at the time to £48,945,000.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.