CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Adur District Council / Worthing Borough Council
Joint Strategic Committee, Tuesday 8 September 2026 at 6.30pm

Worthing Integrated Care Centre Updates

Noted Committee 1 paper

AI summaryWorthing and Adur Joint Strategic Committee delegates authority to run a competitive tender for a managing agent at the Worthing Integrated Care Centre, where the £48,945,000 project remains delayed by ongoing water system issues including legionella detection.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNotes water system update; delegates procurement to Service Director
Money£48,945,000 project budgetRevised in June 2026 after £2,420,310 capital increase
What happens nextMini-competition tender via Pagabo DPSIndicative 3-month procurement; water system handback by end of 2026
Who it affectsWICC tenants including NHS TrustsWeekly update meetings with stakeholders continue

What was decided

Members noted the report and the update on water system rectification progress, including indicative timelines. Report P6

Authority was delegated to the Service Director for Place and Economy to run a tender for a Property Management Company to act as Managing Agent and provide Facility Management Services. Report P7, P8, P33

Authority was delegated to appoint any necessary legal or consultancy services to complete WICC delivery and seek redress, within the authorised budget. Report P7, P9, P28

Why

The contractor Galliford Try has repeatedly missed water system handback deadlines; the council's own testing on 28 May 2026 found traces of legionella, disrupting the planned June 2026 handback. Report P11, P14, P15, P16, P17

The previously approved FM framework did not allow a property manager appointment, and further legal advice led officers to recommend a competitive Dynamic Purchasing System route instead of the June 2026 direct award to Bellrock. Report P21, P30, P31, P32

The Pagabo Dynamic Purchasing System provides a compliant Public Contract Regulations 2015 route with pre-approved suppliers, giving a transparent process to appoint both managing agent and facility manager. Report P33, P34, P35

What happens next

Preliminary market engagement in September 2026 to attract suppliers to the DPS, followed by a cost and quality evaluation over an indicative 3-month procurement window. Report P35, P38

Await the Contractor's remediation plan and testing framework, with the water system indicatively expected to be handed back by the end of calendar year 2026, subject to scope and delivery. Report P27

A fully detailed project review will be presented to the Joint Overview and Scrutiny Committee once the project is complete. Report P42

The money

  • £2,420,310 Capital budget increase approved by JSC in June 2026 due to delays, capitalised interest and rising fees Report P18
  • £48,945,000 Total revised project budget after the June 2026 increase Report P18
  • 0.5 - 1% Framework fee that would have applied under the original GCS route Report P37
  • 2-5% Typical fee range for other framework or DPS routes Report P37
  • 2-3% Anticipated final framework fee under the Pagabo DPS Report P37
  • 26 years Original projected break-even period for the facility Report P20
  • 35 years Revised projected break-even period after delays and lost income Report P20

Options considered

  • Rejected: Direct award to Bellrock as Managing Agent (June 2026 proposal). Changes to legal framework requirements and further legal advice mean a compliant competitive process is now required Report P21, P30, P31
  • Chosen: Mini-competition via the Pagabo Dynamic Purchasing System (Public Contract Regulations 2015). Provides a transparent, compliant route allowing appointment of both managing agent and facility manager Report P31, P33, P34
  • Rejected: Government Commercial Agency (formerly CCS) framework. No longer a suitable framework or DPS route available via GCA Report P37

Implications

  • Financial: Persistent delays and inability to fully occupy the building have created shortfalls in rental income and service charge recovery and increased financing costs, with 2026/27 revenue shortfalls to be managed through the Property Risk Reserve. Report P19, P20
  • Legal: The Council continues to consider all legal remedies available for recovery of losses incurred, as part of an ongoing process. Report P28
  • Risk: The projected break-even point has extended from 26 to 35 years of full operation due to ongoing delays and lost income. Report P20
  • Staffing: Officers will need to appoint an external agency to develop the specification and extend existing legal support, all within the authorised budget from the June 2026 JSC. Report P36
  • Other: Close communications will be maintained with NHS tenants to ensure all necessary compliance assurances for their occupation of the WICC are met. Report P28, P40

Who and where

  • NHS Trusts and other NHS tenants of the WICC Report P16, P28, P40
  • West Sussex Worthing Limited (WSWL), the Developer Report P13, P24, P41
  • Galliford Try, the design and build Contractor Report P3, P13, P23
  • Adur District Council and Worthing Borough Council Report P80
  • Worthing residents and town centre users Report P55, P57, P64

Timeline

  • December 2024: Practical completion of the WICC was issued independently by the Employer's Agent Report P11
  • August 2025: Contractor accepted responsibility to take back the water system to rectify and recommission it Report P13
  • 28th May 2026: Council's independent water testing found traces of legionella in specific locations Report P15
  • June 2026: JSC approved a £2,420,310 capital budget increase, raising total budget to £48,945,000; contractor's legionella sampling returned negative results Report P17, P18
  • July 2026: WSWL completed its own independent specialist survey of the water system Report P24
  • September 2026: Preliminary market engagement on the Pagabo DPS planned Report P35
  • 8 September 2026: Joint Strategic Committee meeting considered this report
  • 18 September 2026: Call-in deadline for this decision at 5.00pm
  • End of calendar year 2026: Indicative timeline for water system handback to the Council, subject to scope and delivery Report P27
  • Later in 2026: Next WICC update to be presented to the JSC Committee Report P38

Plain English for the jargon

  • WICC: Worthing Integrated Care Centre, a health facility bringing together NHS services including GP, dentistry, mental health and pharmacy
  • WSWL: West Sussex Worthing Limited, the developer of the WICC project
  • DPS: Dynamic Purchasing System, a procurement route under the Public Contract Regulations 2015 using pre-approved suppliers
  • Legionella: Bacteria that can cause Legionnaires' disease, found in building water systems
  • BREEAM: Building Research Establishment Environmental Assessment Method, a sustainability standard for buildings
  • EPC: Energy Performance Certificate, showing the energy efficiency of a building
  • GCS: Government Commercial Agency, formerly Crown Commercial Service (CCS)
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemJSC/43/26-27

Resolved

That the contents of the attached report be noted and the update on the water system rectification progress, including indicative timelines; 2. That authority be delegated to the Service Director for Place & Economy to: a. Complete a tender exercise to appoint a Property Management Company to act as Managing Agent for the WICC and who will also provide the Facility Management Services. This delegation includes finalising all procurement and contracts to effect the appointment, subject to this being through a compliant process and within budget. b. To appoint any necessary legal or consultancy services required to complete the delivery of the WICC and seek redress providing the appointments are within the authorised budget. Call In: The call-in deadline for decisions will be 5.00pm on 18 September 2026.
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

1.​ Purpose

This report updates Members on:-

1.1.​ The works that continue to progress to rectify the water system undertaken by the design and build Construction Contractor Galliford Try (the Contractor) and by West Sussex Worthing Ltd (the Developer) in the Worthing Integrated Care Centre (WICC)

1.2.​ The report sets out the proposed step to undertake a mini-tender competition via a compliant Dynamic Purchasing System (Public Contract Regulations 2015) for the appointment of the Property Management Services for the WICC. 2.​ Recommendations

2.1.​ The Joint Strategic Committee is recommended to:

2.1.1.​ Note the contents of this report and the update on the water system rectification progress, including indicative timelines.

2.1.2.​ To delegate authority to the Service Director for Place & Economy to:

1.​ Complete a tender exercise to appoint a Property Management Company to act as Managing Agent for the WICC and who will also provide the Facility Management Services. This delegation includes finalising all procurement and contracts to effect the appointment, subject to this being through a compliant process and within budget.

2.​ To appoint any necessary legal or consultancy services required to complete the delivery of the WICC and seek redress providing the appointments are within the authorised budget.

3.​ Background

3.1.​ Practical completion of the WICC was issued independently by the Employers Agent in December 2024. Immediate concerns resulted in the identification of Legionella and other systematic issues such as inconsistent temperature controls and the requirement for the replacement of water pumps and immersion heaters by the Contractor.

3.2.​ Continuous concerns with the defective water system led to the Council undertaking its own independent expert investigation of the associated issues. Escalation of these concerns by the Council to the Developer were not adequately addressed by the Contractor.

3.3.​ This led to further evidence being presented to the Contractor through the Developer, West Sussex Worthing Limited (WSWL). Eventual acceptance by the Contractor to take back the water system to rectify, and recommission it was agreed and the Contractor took back its responsibility in August 2025.

3.4.​ The remediation works attempted by the Contractor have so far failed to fully rectify the water system, with several deadlines for handback of the water system to the council being missed and further delayed.

3.5.​ The Contractor had been anticipating a revised handback timeline of early June 2026. However this didn’t materialise as the Council conducted independent water testing on 28th May 2026 which proved traces of legionella in specific locations in the building.

3.6.​ This unexpected development disrupted the planned June 2026 handback. The Council awaiting updated programme and final commissioning, subsequently notified the Developer, the Contractor, and stakeholders (including the NHS Trusts) while awaiting the Contractor's response program and further testing.

3.7.​ Subsequently, legionella sampling undertaken by the contractor in June 2026 did result in negative results being recorded. Although, it was evident at that time that wider systematic water system issues still needed to be addressed.

3.8.​ Due to the ongoing delays, capitalised interest on borrowing, and rising legal and specialist consultancy fees, the JSC Committee in June 2026 approved a capital budget increase of £2,420,310. This raised the total revised project budget at the time to £48,945,000.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Worthing Integrated Care Centre UpdatesReport 234 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 11 attended
JG
Councillor Jeremy GardnerChair, present
BA
Councillor Becky AllinsonVice-Chair, present
LC
Councillor Lee CowenAdur Member, present
AH
Councillor Andrew HarveyAdur Member, present
SJ
Councillor Saffa JanAdur Member, absent
AL
Councillor Adrienne LoweAdur Member, absent
CB
Councillor Caroline BaxterWorthing Member, present
JT
Councillor John TurleyWorthing Member, present
SC
Councillor Sophie CoxWorthing Member, present
DF
Councillor Dom FordWorthing Member, present
MM
Councillor Martin McCabeWorthing Member, present

On this subject at Adur & Worthing

Search all
  1. Worthing Integrated Care Centre UpdatesThis decision
  2. Worthing Integrated Care Centre UpdatesNoted
  3. Worthing Integrated Care Centre: UpdateNoted
  4. Update on the Worthing Integrated Care CentreNoted
  5. Update on Worthing Integrated Care Centre and Multi Storey Car ParkNoted
  6. Worthing Integrated Care Centre ProjectApproved

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies