Decision The Committee:- i. Agreed to the recommendations in the paper in relation to the Island of Bute. ii. Agreed to continue consideration of the recommendations in the paper in respect of the Cowal area to the April Area Committee, to allow further information to be submitted regarding the totality of spend for the next 2 years, and details of the surface dressing programme to be included. (Reference: Report by the Area Roads & Amenity Services Manager dated 13 th March 2007 – submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
This report advises Members of proposals for schemes under the Capital works programme.
Recommendation
Members are asked to note the proposals
Background
3.1The Council’s Capital works programme details the roads reconstruction at £1.186m This is the lowest amount within the 5 year programme. The amount translates into the allocation for Bute and Cowal at 20% £0.2372m. Next year the allocations are £2,428m and £0.4856m. Because of the dip in the allocation profile it is proposed to accelerate spend from 08-09 into 07-08 thus giving the proposed spend this year of £354,818. [The initial assessment of works required this year amounted to £551,246]
3.2The proposals for the works programme are developed from our inspections of the road network and assessment of road condition and residual life.
3.3Works include some surface dressing operations. This is to supplement the main surface dressing programme carried out under the Revenue Works programme, details of which are yet to finalise and be advised to Members
3.4Details of the proposals have been circulated to members for comment and the responses included
3.4.1 Consideration of the works at Dunoon Grammar school v the proposed works on Bencorrum and Ardenslate Road – the carriageway at this location is requiring attention now and it may be that our works can be programmed before the demolition and removal works at the school. The works will be programmed to avoid the two activities clashing 3.4.2 Details of the £75,000 for B836 – whilst this is listed as a contribution the works will be done under the control of the Department and this Capital funding will attract other funding from external sources, the total scheme cost being £0.8- 0,9m. At the time of writing the other funding is still to be confirmed. Our proposals would change if the other funding fell.
F:\moderngov\data\published\Intranet\C00000242\M00002781\AI00033771\12270307CapoitalWorksProgramme0.doc 1 of 4 13 March 2007 3.4.3 What about the landslip at Kilbride Road – this scheme is being designed an early indications show likely cost to be in the region of £250K – this will require capital funding from the centre additional to the area allocation
3.5The details of locations which are listed in Appendix A may be subject to change depending on the B836 project situation. Any changes would be notified to the Committee for approval
Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with...
Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.