ROADS CAPITAL RECONSTRUCTION PROGRAMME 2024/25 - UPDATE REPORT
AgreedCommittee3 papers
Environment, Development and Infrastructure Committee agreed this item on Thursday 20 June 2024. Below is the council's own wording, with the papers it was decided on.
Decision The Environment, Development and Infrastructure Committee – 1. endorsed the amended programme of capital works for 2024-25; and 2. agreed that details of each Area Committee’s programme would be forwarded on to individual Elected Members. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated June 2024, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
Recommendation
2.1It is recommended that the Environment, Development and Infrastructure Committee:
• Endorses the amended programme of capital works for 2024-25 • Agrees that details of each area committee’s programme will be forwarded on to individual Elected Members.
3.0DETAIL
3.1It has come to my attention that the roads reconstruction programme presented to Members in March 2024 was based on a desktop exercise using various sources of data as well as having input from Members as part of the Area Committee business days held last year. Whilst the desktop exercise provides a good starting basis for developing the final programme, it doesn’t reflect detailed local course visual inspections and as noted in the March report, would not reflect any winter deterioration experienced on the road network.
3.2The local course visual inspections and measurements were carried out later than normal mainly due to resourcing issues as a result of the response to the large- scale flood and road closure incidents experienced last year from October 2023 and the knock-on effect this has had on workloads, in addition to sickness absence of some key individuals involved in the process. 3.3 The local course visual inspections and measurements now carried out by officers have identified, in some areas, where the original programme reported in March, should be amended. All schemes costings have been updated now that measurements have been carried out. There are new schemes added into the programme and schemes that have now become unaffordable that have had to be de-prioritised; it should be noted that schemes raised by Members at the Area Business Days have remained in the programme. Details of the new schemes and those that are no longer affordable are noted in Appendix 1 and are summarised below. The full revised programme is included in Appendix 2.
MAKI
A total of 31 Schemes were presented to the EDI Committee totaling £2.48M The updated report presents a total of 31 Schemes with the same budget of £2.48M. However there have been changes to some scheme costings and:
• 2 schemes added in Mid Argyll and 2 schemes rescheduled. • 1 scheme added on Kintyre with 3 rescheduled. • 2 schemes added on the islands and 1 scheme rescheduled.
Members are asked to note:
a. There is an estimated outturn over budget allowance of £33,395.21, for Mid Argyll, this was because of the urgent need to include the C43 Crinan Canal works where the Council are responsible for maintaining the surface over Loch 4. Failure to carry out this work may well lead to a malfunction in the bridge mechanical system which would cause issues for Scottish Canals which we would potentially be liable for.
b. There is an estimated outturn over budget allowance of £27,103.49 for Kintyre, this is preparation work for the 2025-26 Surface Dressing works.
c. There is an estimated outturn under budget allowance of £8,895.48 for the island work. Should this remain, the budget will roll into next years island works.
If the costs remain in excess of the relevant area budget, we will draw down from next year’s capital budget as has been done in previous years.
B&C
A total of 20 schemes were presented to the March EDI Committee totaling £1.6M.
The updated report presents a total of 21 Schemes with the same budget of £1.6M. However there have been changes to some scheme costing and:
• 1 Scheme added in Cowal with 3 schemes rescheduled. • 4 Schemes added in Bute with 1 scheme rescheduled.
Members are asked to note:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.