Decision The Environment, Development and Infrastructure Committee – 1. endorsed the proposed programme of capital works for 2024/25; and 2. agreed that details of each Area Committee’s programme would be forwarded on to individual Elected Members. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated February 2024, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
Executive summary
1.1The Roads Reconstruction Programme has been structured in line with the Roads Asset Management and Maintenance Strategy. The focus has been to arrest the rate of decline and provide an overall improvement in condition as has been demonstrated in the Annual Status and Options Report. In previous years this has been achieved through the delivery of a mix of carriageway resurfacing, edge strengthening, patching/surface dressing and in-situ road surface recycling. These treatments have been designed to seal the road to stop the ingress of water, improve ride quality and reduce the number of reactive repairs. This has resulted in an overall improvement in road conditions. Without this investment and works there would have been a significant deterioration in condition and a detriment to the travelling public, economic opportunity and tourism.
1.2Attached to this report is a draft programme for roads reconstruction schemes for 2024/25. This programme has been designed using the current Road Condition Index (RCI) which is produced by the national road condition survey data. In addition to the RCI data, information such as road traffic collisions, known development, activities such as timber harvesting and skid condition (of the carriageways surface) which is measured by a separate survey are also considered together with information brought forward from Elected Members during agreed Area Business Days with officers from Roads and Infrastructure Service. This information is considered at officer level when appropriate engineering judgement is also applied to ensure that maximum benefit can be derived from the available investment.
1.3As per previous years any post winter deterioration may result in some adjustment to the programme to ensure that the best rates of return in terms of whole life costs can be achieved.
1.4It is recommended that the Environment, Development and Infrastructure Committee:-
• Endorses the proposed programme of capital works for 2024/25 • Agrees that details of each area committee’s programme will be forwarded on to individual Elected Members. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE 21 MARCH 2024 SERVICES
ROADS CAPITAL RECONSTRUCTION PROGRAMME 2024/25
2.0INTRODUCTION
2.1This report provides details of the proposed roads reconstruction programme for 2024/25. The programme is based on the 2024/25 allocation of a total of £8.0M.
2.2The additional funding allocated at the Council meeting on 23 February 2023 meant that there was an £8M programme for both this financial year and for last year. This level of investment is welcomed and enables substantial programmes of works to be delivered across the road network focusing on arresting deterioration and where possible improving road condition.
Recommendation
3.1It is recommended that the Environment, Development and Infrastructure Committee:-
• Endorses the proposed programme of capital works for 2024/25 • Agrees that details of each area committee’s programme will be forwarded on to individual Elected Members.
4.0DETAIL
4.1The focus of the roads reconstruction programme has been to recover the network through the delivery of a mix of carriageway resurfacing schemes, patching/surface dressing and in-situ road surface recycling, which follow the principles set out within the Roads Asset Management Plan.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.