Helensburgh CHORD Project Board, Tuesday 5 April 2011 at 4.00pm

PROJECT PLAN

Noted Committee 1 paper

Helensburgh CHORD Project Board noted this item on Tuesday 5 April 2011. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Decision Noted the update on the progress of the Project Plan. Agreed to ascertain procedure to be followed in the event that any objections to the proposed Traffic Regulation Order are received and distribute findings to Chairperson.
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Helensburgh CHORD Project Board

11-02-22 Helensburgh CHORD Single Contract Rev H ID Task Name Duration Start Finish Predecessors Half 1, 2010 Half 2, 2010 Half 1, 2011 Half 2, 2011 Half 1, 2012 Half 2, 2012 Half 1, 2013 D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M 1

2 Appointment 4 wks Mon 14/12/09 Fri 08/01/10

3 Stage C 24 wks Mon 11/01/10 Fri 25/06/10 2

4 Consultation 16 wks Mon 08/03/10 Fri 25/06/10

5 Stage D Design Development 14 wks Mon 28/06/10 Fri 01/10/10 3,4

6 Buildability Workshop 0.2 wks Wed 06/10/10 Wed 06/10/10

7 Stage D Cost Report 3.2 wks Mon 18/10/10 Mon 08/11/10

8 Stage D - Project / Programme Board Approval 3.6 wks Tue 09/11/10 Thu 02/12/10 7

9 Planning / LBC Application 15.4 wks Fri 03/12/10 Mon 21/03/11 8

10 TRO 34.4 wks Tue 02/11/10 Wed 29/06/11

11 Draft TRO 14.8 wks Tue 02/11/10 Fri 11/02/11

12 TRO Consultation with emergency services 3 wks Fri 18/02/11 Thu 10/03/11

13 TRO Press Advert 0.2 wks Thu 31/03/11 Thu 31/03/11

14 TRO Public Consultation 4 wks Fri 01/04/11 Thu 28/04/11

15 TRO Exhibition 1 wk Mon 11/04/11 Fri 15/04/11

16 TRO Exhibition Manned Date 0.2 wks Thu 14/04/11 Thu 14/04/11

17 TRO 19.6 wks Mon 14/02/11 Wed 29/06/11 11

18 Stage E Detail Design 24 wks Fri 03/12/10 Thu 19/05/11 8

19 Stage E Cost Plan 7 wks Fri 08/04/11 Thu 26/05/11

20 Stage F Production Info 4 wks Fri 27/05/11 Thu 23/06/11 19

21 Project / Programme FBC approval 2 wks Thu 30/06/11 Wed 13/07/11 9,20,17

22 Billing 5 wks Thu 14/07/11 Wed 17/08/11 20,21

23 Stage G/H TenderAction 5 wks Fri 24/06/11 Thu 28/07/11 20

24 PQQ 6.4 wks Thu 14/07/11 Fri 26/08/11 21

25 PQQ Scoring 2 wks Mon 29/08/11 Fri 09/09/11 24

26 Tender issues/returned 5 wks Mon 12/09/11 Fri 14/10/11 25,23

27 Tender scoring 2 wks Mon 17/10/11 Fri 28/10/11 26

28 Board approval of Contract Award 3 wks Mon 31/10/11 Fri 18/11/11 27

29 Standstill 2 wks Mon 21/11/11 Fri 02/12/11 28

30 Stage J Mobilisation 6 wks Mon 05/12/11 Fri 13/01/12 29

31 Stage K Construction 60 wks Mon 16/01/12 Fri 08/03/13 30

Task Summary Rolled Up Progress Project Summary Project: Helensburgh CHORD Progress Rolled Up Task Split Group By Summary

Milestone Rolled Up Milestone External Tasks Deadline

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PROJECT PLANReport 20 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Argyll and Bute

Search all
  1. PROJECT PLANThis decision
  2. Simplified planning zones: proposed closure of projectAgreed
  3. Simplified planning zones: proposed closure of projectAgreed
  4. Argyll estates: inveraray project masterplan - mast 1/5 argyll and bute local development plan (2015): argyll estates, inveraray (ref: 13/02860/mplan)Agreed
  5. Simplified planning zones pilot projectAgreed
  6. Waitrose planning contribution - project highlight report and updateNoted

More from Argyll and Bute Helensburgh CHORD Project Board

All decisions
MeetingDecisionOutcome
9 Feb 2012 Highlight/Progress ReportDecision Noted the update on the progress of the Highlight/Progress Report. (Ref: Report by CHORD Project Manager, da... Noted Open
9 Feb 2012 Helensburgh Chord Risk RegisterDecision Noted the update on the current progress of Risk Register. (Ref: Report by CHORD Project Manager, dated 1 Fe... Noted Open
9 Feb 2012 Project PlanDecision Agreed to note the update by the CHORD Design Team. Agreed that updates will be provided, to the Board at th... Agreed Open
5 Apr 2011 Highlight progress reportDecision To note the update on the progress of the Highlight/Progress Report. Noted Open
5 Apr 2011 Helensburgh chord risk registerDecision To note the update on the progress of the Risk Register. Noted Open