Resolved
Decision To note the update on the progress of the Highlight/Progress Report.
Helensburgh CHORD Project Board noted this item on Tuesday 5 April 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision To note the update on the progress of the Highlight/Progress Report.
HIGHLIGHT / PROGRESS REPORT Transforming the Town Centre – Traffic Management & Streetscape Improvements PROJECT NAME: Project Manager: Helen Ford and Improvements & Redevelopment of the West Bay Esplanade Reporting Period: 12/11/10 – 5/4/2011 Date report prepared: 25 March 2011 Project stage: Preparation of Full Business Case Project stage completion date: 13/7/11
Tolerance levels for this stage: Project Plan + / - 15 working days Project budget + / - 10%, or £10,000 whichever is greater
Progress – please refer to Project Plan (Columns 1 and 2 refer to Project Plan version xx Columns 3 and 4 refer to revised Plan version xx Key products completed this period Key products outstanding this period Revised Key products for next reporting Delivery (including those completed ahead of schedule) (including brief explanation of why product delivery period 6/4/2011 – 26/7//11 date outstanding) date Planning Permission granted for Colquhoun Stage E detail design originally March End May Stage E detail design - including End May Square 2011 now May due to elements of stage F 2011 proposed phasing of works 2011 works brought forward and additional scope of works i.e. refurbishment of toilets; extended area for TRO (waiting time 30mins – 60mins); agreeing maintenance regime for esplanade etc. Overall Programme Plan remains unchanged TRO Stage 1 and 2 consultation complete TRO secured End June TRO Notice Advertised 2011
Design layout for refurbishment of toilets FBC completed End July approved 2011
Asbestos survey for Toilet block completed
Additional Topo survey completed
Art Strategy prepared for presentation to Board on 5.4.11
d:\moderngov\data\published\intranet\c00000420\m00004597\ai00058427\hho1hh02highlightreport5april20110.doc Signage proposals prepared
EKOS Economic Impact Assessment completed – Executive summary circulated to Project Board Communication Plan 2011 to Project Implementation circulated to Project Board for approval.
Risk Ref. Risk Current status Previous Revised RAG status RAG status HH01 Unable to secure planning approval Planning approval granted 16 March 2011. Controllable Closed R004 HH01 Works to Sea Wall Any works required will require to be funded from Negligible Closed R013 Council costal protection budget HH01 Water damage to Esplanade Design solution /material selection has reduced risk Undesirable Controllable R015 HH01 Changes occur to brief after stage D freeze. Change control procedures agreed, only minor Undesirable Controllable R038 changes to date HH01 Design not fully defined at tender stage Stage D signed off, planning granted. Undesirable Controllable RO42 HH01 Substantial amendments to scheme due to planning Planning granted 16 March 2011 Negligible Closed RO45 restrictions HH01 Change in Council Policy re parking, planning and TRO Planning granted, parking position confirmed and TRO Undesirable Controllable RO55 changes agreed with Council.
HH01 Head of Roads post vacant Post filled March 2011 Undesirable Closed RO70
Budget Management – please refer to Resource Allocation Schedule Total budget available to complete this stage: Forecast expenditure for current financial year Actual Expenditure (as reported at end of February Variance if Required 2010/11 2011) HH01 £115,000 £105,394 Not required HH02 £118,688 £105,234 Not required Total £233,688 £210,628
Any further information 1. Budget Above current year actual expenditure of £210,628 covers invoices dated up to the end of January 2011 (ten months of expenditure) and represents 90% of the forecasted financial year spend. Design Team’s January invoice for £12,637 missed the February run date and therefore the next reporting period at the end of March will include both their January and February invoices.
Table below shows current forecast expenditure to progress to FBC against approved FBC budget, saving of £243,606. This is due to two main factors, the competitive fee achieved at tender stage and approval to go for a “single contract”.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HIGHLIGHT PROGRESS REPORTReport | 77 KB | DownloadRead as text |
Follow Helensburgh CHORD Project Board at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Feb 2012 | Highlight/Progress ReportDecision Noted the update on the progress of the Highlight/Progress Report. (Ref: Report by CHORD Project Manager, da... | Noted | Open |
| 9 Feb 2012 | Helensburgh Chord Risk RegisterDecision Noted the update on the current progress of Risk Register. (Ref: Report by CHORD Project Manager, dated 1 Fe... | Noted | Open |
| 9 Feb 2012 | Project PlanDecision Agreed to note the update by the CHORD Design Team. Agreed that updates will be provided, to the Board at th... | Agreed | Open |
| 5 Apr 2011 | Helensburgh chord risk registerDecision To note the update on the progress of the Risk Register. | Noted | Open |
| 5 Apr 2011 | Project planDecision Noted the update on the progress of the Project Plan. Agreed to ascertain procedure to be followed in the ev... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.