Decision 1. Welcomed and noted the successful funding applications and congratulated everyone involved in bringing this forward; and 2. Agreed to recommend to the Executive that the CHORD funding allocation approved for this project by the Council is now committed and drawn down in accordance with the THI criteria. (Reference: Report by Head of Economic Development)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The Rothesay Townscape Heritage Initiative (THI) has been successful in attracting funding from Heritage Lottery Fund, Historic Scotland and Leader. The project will now move to implementation phase and run for a period of five years.
Recommendations
2.1That the CHORD Programme Management Board note the successful funding applications and agree to recommend to the Executive that the CHORD funding allocation approved for this project by the Council is now committed, and will be drawn down in accordance with the THI criteria.
3. DETAIL
3.1A THI is a heritage led regeneration scheme for a selected area within the Rothesay Town Centre Conservation Area. Rothesay THI concentrates on a defined core area and includes Guildford Square and surrounding streets. The proposed THI includes:
• The regeneration of Guildford Square including the redevelopment of a key gap site. • Shopfront improvements in Guildford Square and along Albert Place. • Comprehensive repairs to target buildings, including 1-3 Montague Street, 11-13 Montague Street, 21-27 Montague Street, Duncan's Hall and the former Guildford Court Hotel. • Small repair grants. • Community engagement, activities and events. • Training in the built heritage. • Promotion of factoring and maintenance.
3.2In May 2009 Rothesay was awarded a Stage One pass from Heritage Lottery Fund for Rothesay THI. Throughout 2009 / 2010 the Stage Two bid was developed, approved by the Rothesay CHORD Project Board and submitted in May 2010.
3.3To supplement the THI, an application was also made to the Historic Scotland Conservation Area Regeneration Scheme (CARS) fund. This fund provides financial assistance for area based regeneration and conservation initiatives undertaken by local authorities.
3.4An application was also made to Leader to contribute to the THI Training and Education Programme. This aims to complement the wider regeneration project to ensure a sustainable long-term future for the island and to encourage economic growth through increased tourism.
3.5The funding bids have all been submitted on the basis of the previously agreed CHORD funding allocation for this project of £500k. (Please refer to decision made by the Council, 27/11/08.) In submitting the funding applications, these funding were being committed, subject to a successful outcome. 3.6 The total funding package attracted for this project is as follows:
Funding source Amount Argyll and Bute Council 499,900 Heritage Lottery Fund 1,500,000 Historic Scotland 499,933 Leader 107,839 TOTAL* 2,623,896 * includes £16,224 of carry forward funds from 2010/2011.
4. IMPLICATIONS
POLICY The delivery of the CHORD programme fits with the Council’s Corporate Plan, Single Outcome Agreement and approved Development Plan policy for town centre regeneration. The economic outcomes from these projects will contribute to the Government’s Economic Strategy. FINANCIAL The Council has made available the sums requested to progress each of the CHORD projects to Full Business Case. PERSONNEL The resources have been allocated to progress the CHORD Programme. EQUAL Each CHORD project will be required to comply with Equal Opportunities. OPPORTUNITIES LEGAL Each of the CHORD projects will require differing levels of legal resources to ensure their timely delivery. Resources have been allocated within each project.
Robert Pollock, Development and Infrastructure Services, Head of Economic Development 09 May 2011
For further information - please contact Nicola Debnam, CHORD Programme Manager Development and Infrastructure Services 01546 604120
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow CHORD Programme Management Board at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.