Resolved
Decision The Bute and Cowal Area Committee considered and noted the contents of the report. (Reference: Report by Executive Director with responsibility for Development and Economic Growth, dated February 2024, submitted)
Bute and Cowal Area Committee noted this item on Tuesday 5 March 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Bute and Cowal Area Committee considered and noted the contents of the report. (Reference: Report by Executive Director with responsibility for Development and Economic Growth, dated February 2024, submitted)
1.1The purpose of this report is to update members on the progress of the Rothesay Townscape Heritage (TH) scheme as the programme nears completion.
1.2The 5 year programme, which started in September 2017, was due to complete in September 2022. As a result of the COVID-19 pandemic and the subsequent impact on the construction industry, completion was delayed until 31st December 2023. Further contractor and weather related delays now mean the programme will have a final completion date of 31st March 2024 to allow for these final transformational projects to be completed as planned.
1.3The programme has made a transformational difference to the town centre of Rothesay including:
• 4 priority buildings restored with a 5th due to complete by end of March 2024. This includes the new Argyll and Bute Council Customer Service hub at 37 Victoria Street. • 4 shopfronts restored with a 5th due to complete by end March 2024. • 9 traditional window projects completed. • 14 training and community engagement events held involving School Pupils and Homeowners. • 1 Community pop-up shop and innovation space created.
That members of the Bute and Cowal Area Committee note and consider the content of the report. ARGYLL AND BUTE COUNCIL BUTE AND COWAL AREA COMMITTEE
DEVELOPMENT AND ECONOMIC GROWTH 5 MARCH 2024
ROTHESAY TOWNSCAPE HERITAGE SCHEME – MARCH 2024 FINAL UPDATE
2. INTRODUCTION
2.1The purpose of this report is to update members on the progress of the Rothesay Townscape Heritage (TH) scheme as the programme nears.
2.2The 5 year programme which started in September 2017 was due to complete in September 2022. As a result of the COVID-19 pandemic and the subsequent impact on the construction industry, completion was extended until 31st December 2023 to allow for all of the regeneration projects to complete as planned. Further contractor and weather related delays now mean the programme will have a final completion date of 31st March 2024 to allow for all of these transformational projects to be completed as planned.
2.3The Rothesay Townscape Heritage (TH2) Project is a £2.8m jointly funded grant programme focusing on the regeneration of historic buildings as well as traditional skills, training and community engagement.
2.4Rothesay TH is part funded by the Scottish Government, The European Community Argyll and the Islands LEADER Programme 2014-2020, Historic Environment Scotland, National Lottery Heritage Fund, Highlands and Islands Enterprise, Smarter Choices Smarter Places, and Argyll and Bute Council.
2.5The programme has made a transformational difference to the town centre of Rothesay including:
• 4 priority buildings restored with a 5th due to complete by end of March 2024. This includes the new Argyll and Bute Council Customer Service hub at 37 Victoria Street • 4 shopfronts restored with a 5th due to complete by end of March 2024. • 9 traditional window projects completed. • 14 training and community engagement events held involving School Pupils and Homeowners. • 1 Community pop-up shop and innovation space created. 3. RECOMMENDATIONS
3.1It is recommended that members of the Bute and Cowal Area Committee note and consider the content of the report.
4. DETAIL
4.1Rothesay Townscape Heritage (TH) Scheme is primarily a heritage and regeneration focused grants administration scheme that involves substantial amounts of dialogue and commitment with property owners, both residential and business, and the wider community to see the economic regeneration realised. A large component of the programme is also dedicated to raising awareness of the historic built environment and celebrating the heritage and culture of the Isle of Bute.
4.2The scheme has been transformational for the town centre and has delivered visual improvements benefitting those who live, work and visit this historic town.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ROTHESAY TOWNSCAPE HERITAGE SCHEME: MARCH 2024 FINAL UPDATEReport | 201 KB | DownloadRead as text |
Follow Bute and Cowal Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | Charts (argyll and the isles)Decision The Bute and Cowal Area Committee considered and noted the information provided in the presentation. (Refere... | Noted | Open |
| 1 Sep 2026 | Area committee quarterly performance reports fq1 2026/27Decision The Bute and Cowal Area Committee noted the performance and supporting commentary as presented. (Reference: ... | Noted | Open |
| 1 Sep 2026 | Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with... | Agreed | Open |
| 1 Sep 2026 | Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director... | Noted | Open |
| 1 Sep 2026 | Cruach mhor and clachan flats windfarm trustsDecision The Bute and Cowal Area Committee noted these updates, which are the most recent of the annual updates requi... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.