ROTHESAY TOWNSCAPE HERITAGE INITIATIVE COSTS

Noted Committee 1 paper

CHORD Programme Management Board noted this item on Tuesday 18 May 2010. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Decision 1. Noted that as a result of detailed survey work that has been undertaken, the original project objectives for the Rothesay THI will not be achieved to the scale originally envisaged. Hence, there is a risk that the stage two submission to the Heritage Lottery Fund (HLF) may not be successful; 2. Agreed that the THI should be seen as the beginning of a wider regeneration for Rothesay’s built heritage which will be reliant on the close working relationship with HLF and Historic Scotland; and 3. Agreed that there was no scope to alter CHORD funding allocations at this time. (Reference: Report by Head of Economic Development dated 7 May 2010, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to CHORD Programme Management Board

Summary

1.1The Rothesay Townscape Heritage Initiative (THI) stage two submission to Heritage Lottery Fund (HLF) is currently in preparation. A key element of the development work for this submission has been to undertake detailed survey work and to then produce detailed costings for the priority buildings within the THI area.

1.2This paper highlights the findings of this work, details the implications for the THI budget and reflects on the CHORD funding allocation for the two Rothesay projects.

Recommendations

2.1That the Programme Management Board:

• note that as a result of detailed survey work that has been undertaken, the original project objectives for the Rothesay THI will not be achieved, to the scale originally envisaged. Hence, there is a risk that the stage two submission to Heritage Lottery Fund (HLF) may not be successful. • agree that the THI should be seen as the beginning of a wider regeneration for Rothesay’s built heritage which will be reliant on a close working relationship with HLF and Historic Scotland (HS). • provide advice to the Rothesay CHORD Project Board in respect of the CHORD funding allocation and between the two projects.

3. DETAIL

3.1A key part of developing the Rothesy THI stage two submission has been undertaking detailed survey work of the priority buildings with the THI area and from that determining the detailed costings associated with repairing/bringing back into use these buildings.

3.2From the detailed survey work undertaken it is clear that the condition of many of these buildings and the associated costs to repair is much greater than originally anticipated. The implication of this for the THI is that less will be achieved than was originally anticipated with the budget that has been allocated.

3.3The stage one approval was based on an overall budget of £2.5 million with £1.5 million coming from HLF, £500,000 from the Council CHORD Programme and the remaining £500,000 being sought from other funding sources such as Historic Scotland’s Conservation Area Regeneration Scheme (CARS), another round of which is due to be launched this month.

3.4Based on the outcome of the detailed survey work undertaken the total estimated cost of the works, based on the stage one submission, would be in excess of £7 million.

3.5In light of the above there is now a need to prioritise those buildings that are most in need and to do this in partnership with HLF to ensure that we secure a successful stage two submission. 3.6 In working with the two key funding partners, HLF and HS, both organisations have informally enquired about:

a) the CHORD funding allocation to each project (Rothesay THI - £0.5m, Rothesay Pavilion - £1.9m), and; b) the possibility of funds allocated to Rothesay Pavilion being utilised for the THI.

3.7Officers have advised HLF and HS that the allocations were derived from an Outline Business Case process and that each Project Board is responsible for managing their projects within the funding allocated to them and for levering external funding as appropriate.

3.8Given the prioritisation process that the THI project is faced with, additional funding will be sought from sources that can support eligible elements of the project, e.g. LEADER to cover costs such as staff costs, training, community engagement, etc. This would assist in preserving as much of the original “pot” as possible for the original objectives of the project, i.e. restoration of the built heritage.

3.9It should be noted that there are limited additional funding sources to assist with the works to buildings due to many of them being in private ownership.

3.10The Pavilion is a Council owned asset. The Full Business Case is at a very early stage and the final project costs are not yet known. Therefore, the implication of utilising funds from this project to assist the THI cannot yet be quantified.

4. IMPLICATIONS

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ROTHESAY TOWNSCAPE HERITAGE INITIATIVE COSTSReport 55 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 7 attended
DH
Douglas HendryOfficer, present
SL
Sally LoudonOfficer, present
RM
Councillor Robert MacintyreMember, apologies
SM
Sandy MactaggartOfficer, expected
FM
Fiona McCallumSecretary, expected
DW
Councillor Dick WalshMember, present
BW
Bruce WestOfficer, present

On this subject at Argyll and Bute

Search all
  1. ROTHESAY TOWNSCAPE HERITAGE INITIATIVE COSTSThis decision
  2. Rothesay townscape heritage scheme - march 2024 final updateNoted
  3. Rothesay townscape heritage scheme - december 2023 updateAgreed
  4. Rothesay townscape heritage - hlf awardDecided
  5. Rothesay townscape heritage phase two - heritage lottery fund offer of awardAgreed
  6. Rothesay townscape heritage initiative - successful funding applicationsNoted

More from Argyll and Bute CHORD Programme Management Board

All decisions
MeetingDecisionOutcome
5 Mar 2013 Chord programme update - highlight / progress reportDecision The CHORD Programme Board – 1. Noted the report. 2. Agreed that a brief paper containing the detail that had... Noted Open
5 Mar 2013 Chord consultancy frameworkDecision The CHORD Programme Board noted the verbal update. (Reference: Verbal update by CHORD Programme Manager) Noted Open
5 Mar 2013 Lorn arc updateDecision The CHORD Programme Management Board noted the information provided in the presentation. (Reference: Present... Noted Open
5 Mar 2013 Strategic programme board - discussion paperDecision The CHORD Programme Management Board – 1. Agreed to recommend the proposed formation of a Strategic Programm... Agreed Open
13 Feb 2012 LORN ARCDecision Noted the updated position. (Reference: Verbal report by CHORD Programme Manager) E1 Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies