Decision The Policy and Resources Committee accepted the Heritage Lottery Fund offer of grant based on the purposes as detailed within the submitted report; and delegated authority to the Chief Executive to sign the permission to start letter once all necessary preconditions had been satisfied. (Reference: Report by Executive Director – Development and Infrastructure Services dated 30 June 2017, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The purpose of this report is to request that Members accept Heritage Lottery Fund’s grant offer of £1,888,500 to deliver a Townscape Heritage (TH) in Rothesay, which was made to the council on 20 June 2017.
1.3The award will be used for the following approved purposes:
1. To deliver a programme of building repairs to under-used and vacant town centre properties as outlined in the second round application.
2. To deliver a programme of learning, skills development and engagement to sustain project benefits and enable the local community to celebrate Bute’s heritage, as outlined in the second round application.
1.4Rothesay TH will be delivered over a 5-year period from 1 October 2017 to 30 September 2022, and will seek to deliver the following:
5 priority building repairs Traditional window repairs 8 shopfront restorations Activities, skills and capacity building programme – heritage and maintenance Activities, skills and capacity building programme – growing and supporting a creative industry Wayfinding and connectivity improvements
Recommendations
2.1That Members agree to accept the Heritage Lottery Fund offer of grant based on the afore-mentioned approved purposes and delegate authority to the Chief Executive to sign the permission to start letter once all the necessary pre conditions have been satisfied.
1 ARGYLL AND BUTE COUNCIL Policy and Resources
DEVELOPMENT AND INFRASTRUCTURE SERVICES 17 August 2017
Rothesay Townscape Heritage – HLF Grant Award
3.0INTRODUCTION
3.1The purpose of this report is to request that Members accept Heritage Lottery Fund’s grant offer of £1,888,500 to deliver a Townscape Heritage (TH) in Rothesay, which was made to the Council on 20 June 2017.
3.2The award will be used for the following approved purposes:
1. To deliver a programme of building repairs to under-used and vacant town centre properties as outlined in the second round application
2. To deliver a programme of learning, skills development and engagement to sustain project benefits and enable the local community to celebrate Bute’s heritage, as outlined in the second round application.
3.3This report also requests that Members delegate authority to the Chief Executive to sign the permission to start letter, which will enable the project to commence and allow the drawdown of grant over a 5-year period until 30 September 2022.
4.1That Members accept the Heritage Lottery Fund offer of grant based on the afore- mentioned approved purposes and delegate authority to the Chief Executive to sign the permission to start letter once all the necessary pre conditions have been satisfied.
5.0DETAIL
5.1At their meeting of 20 August 2015, the Policy and Resources Committee agreed that the council should submit a first round application to HLF to seek funding for a second phase of heritage-led regeneration in Rothesay, which would continue and build on the momentum of the successful Townscape Heritage Initiative (THI), which concluded on 31 March 2016. At the meeting, the committee also agreed to the need to identify council match funding of £200,000, which has since been confirmed at the Council’s budget meeting of 23 February 2017. The council also agreed to submit a Conservation Area Regeneration Scheme (CARS) funding bid to Historic Environment Scotland (HES) for £500,000 towards the Rothesay TH. This bid was successful and
2 was awarded to the council on 9 February 2017 as part of the Round 7 CARS awards but was predicated on a successful stage two TH approval from HLF.
5.2Subsequent to a successful round one application to HLF, at their meeting of 21 April 2016, Council agreed to the HLF Terms of Grant and delegated authority to the Chief Executive to sign and agree the terms. These were subsequently accepted by the Chief Executive on submission of the council’s stage two application on 2 March 2017.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-...
Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.