SCOTTISH GOVERNMENT - FUNDING OF SCHOOLS FOR THE FUTURE PROJECTS; PROPOSED NEW SCHOOL FACILITIES FOR DUNOON AND CAMPBELTOWN; GOVERNANCE AND OTHER MATTERS
NotedExecutive2 papers
Executive noted this item on Thursday 19 April 2012. Below is the council's own wording, with the papers it was decided on.
Decision The Executive - 1. Noted the content of the report and supplementary paper; 2. Agreed the Governance arrangements as contained in paragraph 4.2 and Appendix 1 of the report; 3. Agreed the New Project Request (NPR) as requested in paragraph 5.1 of the report and contained in Appendix 2 of the report and instructed the Executive Director – Customer Services to lodge this with SFT and hubco; 4. Noted the affordability position as outlined in paragraph 6.3 and detailed at Appendix 3 of the report; 5. Agreed to the earmarking of the funds and for the purpose as contained in paragraph 6.2 of the report; 6. Noted the position in regard to the consideration of shared working at paragraph 7.1 of the report; 7. Noted that the Scottish Futures Trust has commended the consultation activity carried out to date in respect of the Dunoon area shared primary and pre five campus project outlined in the supplementary briefing note prepared by the Executive Director; and 8. Agreed a commitment to ongoing dialogue with stakeholders, staff, parents and community once preliminary design work has been completed, prior to the commitment of significant expenditure on the proposal. (Reference: Joint Report by Executive Director – Community Services and Executive Director – Customer Services dated April 2012, submitted and supplementary report by Executive Director – Community Services dated 19 April 2012, tabled) #
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
2.1The Executive is asked to note this report and;
2.1.1 Agree the Governance arrangements as contained in paragraph 4.2 and Appendix 1 of this report;
2.1.2 Agree the New Project Request (NPR) as requested in paragraph 5.1 hereof and contained in Appendix 2 of this report and instruct the Executive Director – Customer Services to lodge this with SFT and hubco;
2.1.3 Note the affordability position as outlined in paragraph 6.3 and detailed at Appendix 3 hereof;
2.1.4 Agree to the earmarking of the funds and for the purpose as contained in paragraph 6.2 hereof;
2.1.5 Note the position in regard to the consideration of shared working at paragraph 7.1 hereof.
Background
3.1Argyll and Bute Council is an authority with a clear focus on education as a key priority. Providing a high quality environment conducive to learning and teaching is a key goal for the Council that needs to be achieved in a financial environment that demonstrates Best Value, Continuous Improvement and Value For Money, with projects that are affordable to the Council. This fully supports the Council’s overall vision for the Education Service. The Council has previously approved outline 1 business cases for the establishment of a new Campbeltown Grammar and Dunoon Area Primary Shared Campus (to replace the existing buildings housing each of St Mun’s Primary, Kirn Primary and Dunoon Primary schools).
3.2Revenue Funded Project The Scottish Government has advised the Council that funding awarded from the “Scotland’s Schools for the Future” project (SSF) for the proposed new school facilities at Campbeltown Grammar and Dunoon Area Primary Shared Campus is to be provided on a revenue basis. The Scottish Government have set out the key conditions and guidance for procuring bodies receiving revenue finance and the conditions and guidance have been accepted by the Council .
The Council has agreed, as part of its 2012/13 budget, to make funding available for a project to build new education facilities in Dunoon and Campbeltown. The proposed capital plan will support the corporate outcome of our young people having the skills, attitudes and achievements to succeed throughout their lives by improving the quality of the school estate and raising the condition of school buildings.
The Council has further agreed that this project will be delivered in accordance with the Scottish Government’s requirements through the Scotland’s Schools for the Future programme. As described above, the Scottish Government requires that the Council should have in place a Project Team with the relevant skills in order to deliver a revenue funded project of this nature.
The Council has met with the Scottish Futures Trust (SFT) who have confirmed that the projects for the proposed improved school facilities will be procured through the hub Design, Build, Finance and Maintain (DBFM) model. The SFT are managing the Scotland’s Schools for the Future Programme on behalf of the Government and are intended to provide a centre of expertise and advice on the development, funding, structuring, procurement and management of these projects.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
SCOTTISH GOVERNMENT: FUNDING OF SCHOOLS FOR THE FUTURE PROJECTS; PROPOSED NEW SCHOOL FACILITIES FOR DUNOON AND CAMPBELTOWN; GOVERNANCE AND OTHER MATTERSSupplementary
9SCOTTISH GOVERNMENT - FUNDING OF SCHOOLS FOR THE FUTURE PROJECTS; PROPOSED NEW SCHOOL FACILITIES FOR DUNOON AND CAMPBELTOWN; GOVERNANCE AND OTHER MATTERSThis decision
SCOTTISH GOVERNMENT - FUNDING OF SCHOOLS FOR THE FUTURE PROJECTS; PROPOSED NEW SCHOOL FACILITIES FOR DUNOON AND CAMPBELTOWN; GOVERNANCE AND OTHER MATTERSThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.