Mid Argyll, Kintyre & the Islands Area Committee agreed this item on Wednesday 3 April 2013. Below is the council's own wording, with the papers it was decided on.
Decision Members agreed: 1. To note the report 2. That the Roads Performance Manager would circulate funding details to Members in regards to the totality of Kinloch Road , Campbeltown 3. That the Roads Performance Manager would bring a report to the MAKI Business Day in May detailing the additional Capital funding which will be available to MAKI following the Council decision of 21 March, 2013. This paper will provide 2 clear options for consideration. 4. (a) The use of the additional funding in accordance with the current asset-based/geographical allocation of the funding. (b) The use of the funding purely on an asset management/engineering needs basis. (Reference: Report by the Executive Director of Development and Infrastructure, dated 28 March, 2013, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Mid Argyll, Kintyre & the Islands Area Committee
Summary
1.1This report advises Members of the progress being made with regard to the delivery of the overall Roads Reconstruction Programme 2012 - 15. This report reviews the works carried out in Year 1, 2012-13 and the proposed programme for year 2, 2013-14.
1.2In 2011, the Council decided to increase investment in upgrading its road network following successive poor winters, and subsequently delivered a £7M programme of works which made an immediate and positive impact on the Council’s roads network. In February 2012, the Council approved a further £21M investment in roads reconstruction for 2012-15.
Recommendation
2.1That Committee notes the progress of the Roads Reconstruction Programme for 2012-13 and the proposals for 2013-14 within the £21M works
3 DETAIL
3.1The focus of the roads reconstruction programme has been to recover the network through the delivery of a mix of carriageway resurfacing schemes, patching/surface dressing and insitu road surface recycling, which follow the principles set out within the proposed Roads Asset Management and Maintenance Strategy.
3.2The summary table below highlights the positive and visible impact of the works undertaken to date. By March 2013 the Council had upgraded over a quarter of its “A” class roads and almost 300km of roads in total, within the last 24 months, as indicated below.
Table 3.2 Road Treatment % Treatment % Total Treatment Total Treatment category 2011/12 2012/13 Length as a % of network length 2011-13 A 55.76 km = 10% 93.37 km = 17% 149.13 km 27% B 26.846 km = 4% 58.912 km = 10% 87.76 km 14% C 12.374 km = 3% 4.008km = 1% 16.38 km 4% U 18.860 km = 3% 17.553 km = 2% 36.41 km 5% 289.68km
3.3The current 3 year capital investment programme will allow the Council to upgrade over 50% of its class A roads and 30% of its class B roads by 2015, which will make a significant and positive impact upon the local economy, connectivity and the quality of life of our communities.
1 3.4 The Roads Reconstruction Programme has been delivered by a mixed economy model with the Council’s in house team delivering carriageway resurfacing and patching works across the Council area. In Mull, Islay, Jura and Kintyre resurfacing and patching works have been delivered by the Council’s contractual partner Breedon and their locally based sub-contractors. Unit cost for surfacing carried out by the Councils in-house teams compare favourably with unit costs from Breedon’s. Surfacing dressing has been delivered by Kiely Brothers who were awarded the contract for the Council wide area.
3.5The Capital budget was accelerated in Year 1 of the £21M budget to achieve an early benefit to road condition and partly as preparation for future year’s operations. A record of the impact on the Capital budget, scheme by scheme in the MAKI Area for Year 1 is attached in Appendix 1a-c.
3.6The above service delivery model will be used in the Year 2 programme for the Council network as indicated in the Schemes List for the MAKI Area as detailed in Appendix 2. At present the Budget allocation is based on the re-profiled sum remaining in the £21M programme, distributed approximately equally over the remaining year 2 and 3.
3.7Recently announced additional funding from the Scottish Executive which the Council has allocated to additional Roads schemes are at present being assessed. A future paper will detail these schemes and how they may affect the sequence of operations. Where operational efficiency dictates, the present sequence of schemes will be adjusted, which may result in some sites commencing at earlier or later dates.
4 CONCLUSION
4.1This report updates Members on the progress being made to upgrade the Council’s road network through the delivery of the Roads Reconstruction Programme 2012-15.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an...
Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.